HomeMy WebLinkAboutInformation Update 0323211
AGENDA
INFORMATION UPDATE
March 23, 2021
5:00 PM,
I.INFORMATION UPDATE
I.A.Engineering Update
I.B.Grants Improvement
1
MEMORANDUM
TO: Mayor and City Council
FROM: Trish Aragon, P.E., City Engineer
Pete Rice, P.E., Division Manager
THROUGH: Scott Miller, Public Works Director
MEMO DATE: March 10, 2021
RE: Information Only – Summary of January 25th and February 1st
Worksession
SUMMARY: Attached are the summaries of the worksession topics that were discussed
during the January 25, 2021 and Feb 1 ,2021 Worksession.
Topics of the January 25th worksession included the following:
• Paepcke Transit Hub Project
• Park and Midland
• Jail Trail Project
Topics of the February 1st worksession included the following:
• Neighborhood Traffic Calming Policy
• Lake Avenue Ped Bikeway
• Sidewalk Deferred Zones and Sidewalk Maintenance
• Critical Pedestrian Connections
• Safety in the Core
CITY MANAGER COMMENTS:
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
2
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and City Council
FROM: Michael Horvath, PE
THROUGH: Pete Rice, PE & Trish Aragon, PE
MEETING DATE: January 25, 2021
RE: Paepcke Transit Hub Project
SUMMARY OF DISCUSSION: Staff presented on two additional items requested by
Council during the November 16th Work Session. These items included the winterization
of the shelter and an additional crosswalk at the western leg of the Main St crossing.
The shelter options presented were a “enclosed” and a “slim” shelter. The “enclosed”
shelter did not allow for ADA access and created pinch points at either end of the shelter
with the site constraints. A truly enclosed shelter similar to down valley BRT stops needs
considerable width to achieve ADA access and assure a proper distance from the bus on
the roadway. Due to the tight constraints of the site, a wider bus shelter is very difficult to
achieve. The current design with in the slim shelter does provide protection with glass
panels on both sides and allows for ADA access. Staff recommended a slim shelter with
the addition of an on-demand infrared heater to keep users warm.
The western leg of the Main St crossing was presented by staff. Including the crossing
within the overall intersection design corresponds with the guidance provided by MUTCD.
It allows for greater pedestrian connectivity and ease throughout the corridor. It also
allows south bound bikers on Garmisch to dismount and cross with the use of an RRFB
without crossing on coming traffic. For these reasons, staff recommended the inclusion
of the western crosswalk. CDOT will need to approve the additional RRFB prior to
implementing the addition into the project.
Staff/Council received an “Alternative Bus Stop Location Study” from the property owners
at 125 S Garmisch the afternoon of the work session. The alternatives were re-routing
the busses down Aspen St or moving the bus stop in front of the Molly Gibson Lodge.
Several options depicted bus movements that were not accurate towards the MCI turn
radius that is utilized for the BRT. Staff reiterated that the design team along with staff
have investigated these options earlier in the project and presented drawbacks to each
option not presented in the consultant report.
COUNCIL DIRECTION: Council understood the site constraints and the need for ADA
access for the shelter. The slim shelter was the preferred design, but wanted staff to
3
provide as much protection from the elements as possible in this design. Heating
elements were a favored approach by Council.
Council agreed that adding a RRFB to the western leg of the Main St crossing makes
sense for safety and pedestrian flow reasons. The MUTCD was an item that pushed staff
and design team to make the decision to include it, but the RRFB will need to be approved
by CDOT before implementing.
Most Council members understood the proposed location of the bus stop and agreed that
the alternatives in the document were not applicable. Council directed staff to continue
with design into the recommended design.
NEXT STEPS:
1. Investigate weather protection for the shelter
2. Incorporate western crossing utilizing RRFB in the design
3. Final construction documents are being finalized and sent in for permits by June, 2021.
4
1
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and Council
FROM: Pete Rice, PE, Engineering Division Manager
Raquel Flinker, Project Manager II
THROUGH: Tricia Aragon, PE, City Engineer
MEETING DATE: January 25, 2021
RE: Park and Midland
SUMMARY OF DISCUSSION:
Staff presented an update on the following topics for the Park and Midland
neighborhood:
1. Traffic report findings
2. Park and Hopkins Avenue intersection improvements
3. Anticipated impacts for each option
4. Community survey results
5. Recommendations on solutions
The traffic report concluded that:
• Speeding is not present on Park Avenue between Hopkins and Midland Avenue,
confirming traffic data previously collected by Staff
• The one‐way configuration could likely result in increased speeds in the
neighborhood without additional traffic calming measures
• The enhancement of pedestrian crossing of Park Avenue at Hopkins Avenue is
recommended
• The sidewalk connection on the east side of Park Avenue between Hopkins
Avenue and Midland Avenue is recommended
Based on the traffic report recommendations, in November, stop signs were placed at
the intersection of Hopkins and Park Avenue to create a better interaction between
vehicles and pedestrians. Per Council’s direction, additional improvements to this
intersection will be investigated as part of the schematic design.
The community survey included feedback from 56 participants, 90% residing within the
neighborhood. Below are the results for each option:
1. Completing sidewalk on Park Avenue, maintaining two-way traffic: 68% support
2. One-way streets: 24% support
3. Improvement of the Hopkins and Park Avenue intersection and Hopkins trail
drainage: 80% support
4. No further action: 50% support
5
COUNCIL DIRECTION:
Council agreed to begin schematic design of a sidewalk connection on Park Avenue
maintaining two-way traffic. Council requested that any widening be done with equity in
mind to both the east and west sides of the roadway, as a small number of residents
could be significantly impacted by these changes.
Council directed improvements of the Hopkins and Park Avenue intersection and
Hopkins trail drainage as part of this effort. Additional outreach is requested to assure
the residents along Park Avenue, between Hopkins and Midland avenue, continue to be
engaged in the design process.
Council also requested that the project to address drainage concerns on Midland
Avenue be implemented on an early schedule. The drainage concerns of the
community and issues during the winter became clear to Council after the outreach
summary. The project was originally scheduled to be designed in 2025 and staff
indicated they would introduce the project into the 2022 budget process.
NEXT STEPS:
1. Begin schematic design of a sidewalk connection on the east side of Park
Avenue incorporating improvements to the Hopkins and Park Avenue
intersection and Hopkins trail drainage. Schematic design is anticipated to be
complete in the summer 2021. The design will be provided internally by staff with
items like survey, landscape design and possible electrical design being provided
by consultants using the budget allocated for the project.
2. Incorporate the project to address drainage concerns along Midland Avenue as
part of the 2022 budget discussion.
6
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and City Council
FROM: Michael Horvath, PE
THROUGH: Trish Aragon, P.E., City Engineer
Pete Rice, P.E., Division Manager
MEETING DATE: January 25, 2021
RE: Jail Trail Project
SUMMARY OF DISCUSSION: Staff introduced Council to the Jail Trail project. The
project team has coordinated with County staff to move the design to a 90% design
development level. The design is being led internally by staff. Staff touched on the benefits
of the new design mainly the increase usability of a 7.5% trail compared to the difficult
existing conditions of a 12% trail.
Staff presented the design elements incorporated into the proposed corridor to ease that
constraint and soften the pedestrian experience. The link is a critical connection for bikers
between the Rio Park and upper Galena Plaza that will only increase in use once the city
offices are finalized. Over the years, users have expressed the difficulty of utilizing this
connection on a bike due to the 12% slope.
Staff developed several alternatives internally trying to alleviate the steep slope. As
discussed in the presentation, achieving ADA would be incredibly difficult and expensive
including options like raising the Rio Grande Drive, utilizing switchbacks that are not ideal
for bikers or lowering the path below the existing building foundation footprints. Staff
presented in detail the solution that achieving the 7% slope was the best solution for the
project and most cost efficient with the understanding this design does not meet ADA
requirements. Design elements presented included tiered walls and vegetation along the
walls.
An additional discission include the explanation of the requirement for the County to
replace the storm line below the trail as part of a 2018 building permit. Essentially, the
trail will be disturbed as part of this commitment, but staff saw the opportunity to work with
the county to greatly improve the function of this connection by lowering the grade. The
project was presented as a County/City collaboration to improve the entire corridor. The
County is responsible to replace the storm sewer in an IGA agreement between the City
and the County.
COUNCIL DIRECTION: Council members understood the need for the project and the
benefit of the decreased slope. A few stated they avoid trail because of winter conditions
7
and slope. Two great concerns were the project budget and that the completed trail would
not meet ADA requirements. The project cost was too high for Council. Staff stated they
would do a professional cost estimate and review with Council. Additionally, the “hallway”
feeling was perceived to create a dark user experience that was not worth the price tag.
Council requested cost estimates of ways to improve the corridor through a reduction in
scope and work on improving the slope to meet ADA standards. Staff is to review the
material options for more permeability and improve the wayfinding through the corridor.
Council indicated the project was competing against different needs in the city for funding
and may not be a priority, but more information is required.
NEXT STEPS:
1. Staff will obtain a professional cost estimate.
2. Investigate additional options that may reduce the cost.
3. Review ADA alternatives.
3. Investigate permeable surfaces.
4. Improve wayfinding in design.
5. Schedule Worksession for Summer 2021 to review the work items above.
8
1
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and City Council
FROM: Raquel Flinker, Project Manager II
Pete Rice, PE, Engineering Division Manager
THROUGH: Tricia Aragon, PE, City Engineer
MEETING DATE: February 1, 2021
RE: Neighborhood Traffic Calming Policy
SUMMARY OF DISCUSSION:
Staff presented the Neighborhood Traffic Calming Policy. The policy addresses
speeding concerns and was created with the following objectives:
1. Develop a clear process for addressing vehicle speed concerns.
2. Produce an understandable document to refer community members to for
guidance on the traffic calming process.
3. Clearly delineate traffic calming issues separately from other safety issues.
4. Develop a mechanism to implement traffic calming measures consistently
throughout the City.
Below is the process flow chart for the policy:
9
2
Figure 1 – Traffic calming measure implementation process.
Depending on what thresholds the issue triggers during the evaluation step, it follows
different routes.
COUNCIL DIRECTION:
Council agreed on the one-year trial period for this policy, where staff tests out the
process and collects feedback from the community. After the trial period, Staff will return
to Council with a final version of the policy for adoption via a City ordinance.
NEXT STEPS:
1. Begin roll-out and outreach for the Neighborhood Traffic Calming Policy
implementation by Spring 2021
10
3
11
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and City Council
FROM: Carly McGowan, Project Manager I
Pete Rice, PE, Engineering Division Manager
THROUGH: Tricia Aragon, PE, City Engineer
MEETING DATE: February 1, 2021
RE: Lake Avenue Ped-Bikeway
SUMMARY OF DISCUSSION: Staff presented the implementation of the next segment
of the ped-bikeway to Council. The section referred to as the Lake Ave Ped-Bikeway runs
from North St and 4th St to Hallam and Garmisch along North St, Lake Ave, First St,
Francis St, and Garmisch St. The proposed segment is the next piece implemented from
the Bicycle and Pedestrian Master Plan, which underwent rigorous public process prior
to finalizing.
Staff reviewed the existing bicycle and pedestrian infrastructure with Council to
demonstrate the purpose of the north-south segment of the ped-bikeway. The Lake
Avenue Ped Bikeway allows for pedestrians and bikers to connect from the existing
infrastructure on Hallam Street with a safe route to several entities including the Music
Tent. Staff also outlined the plan to add Sharrows along Gillepsie St to create a more
seamless bicycle connection to the Music Tent and Physics Center.
Staff discussed safety concerns at Triangle Park which is located along the proposed
ped-bikeway. Speeding is not present in this area, but there is a safety concern
surrounding the park based on staff observations. Staff met with neighbors on August
24th, 2020 to discuss concerns. From that meeting, Staff believes that a ped-bikeway in
the area will be a salve to many of the neighbor concerns regarding park safety. Staff
plans to follow up in this area and determine whether additional non-infrastructure
measures should be taken to protect the safety of park users.
COUNCIL DIRECTION:
Council supports the ped-bikeway moving forward with a communications plan for
education community residents who are directly affected as well as the broader
community.
NEXT STEPS:
1. Staff will work with the Communications Department to flesh out a communications
plan for the new segment of ped-bikeway to notify neighbors as well as the broader
community. This will take place In March and April of 2021.
12
2. Following the communication plan development, Staff will implement the new ped-
bikeway segment in Spring of 2021.
3. Over the course of 2021, Staff will monitor the success of the ped-bikeway.
13
1
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and City Council
FROM: Raquel Flinker, Project Manager II
THROUGH: Tricia Aragon, PE, City Engineer
MEETING DATE: February 1, 2021
RE: Sidewalk Deferred Zones and Sidewalk Maintenance
Sidewalk Deferred Zones
SUMMARY OF DISCUSSION:
Staff informed Council on the City’s Sidewalk Master Plan. The Master Plan was
updated in 2015 as part of the City’s Pedestrian Bike Plan and excludes sidewalks in
several areas.
Property owners are required to install a sidewalk along street frontage adjacent to their
property, unless the area of the city is considered "Sidewalk Free" in accordance with
the City Sidewalk master plan. If no sidewalk is installed adjacent to the property, the
City requires the property owner to sign a sidewalk agreement. This agreement allows
the city to complete the missing link of sidewalk in the future with the property owner
reimbursing the City for the associated costs.
The Sidewalk Master Plan has been a valuable document for the City in guiding
development and improving our streets to make them pedestrian friendly.
COUNCIL DIRECTION:
Council was interested in revising the City’s Sidewalk Master plan.
NEXT STEPS:
Staff will come back to Council with a Master Plan Update Project as part of the 2022
budget process
Sidewalk Maintenance
SUMMARY OF DISCUSSION:
Staff presented a recommendation to clarify Title 21 language regarding the
responsibility to maintain, repair and improve sidewalks, curbs and gutters by adjacent
properties. The figures below clarify the responsibility of properties along the alleys.
14
2
Figure 1 – Area of responsibility for sidewalks, driveways, curbs and gutters repair and snow maintenance
Figure 2 – Area of responsibility for sidewalks, driveways, curbs and gutters replacement and/or new
installation
COUNCIL DIRECTION:
After some discussion, Council requested more information prior to making a decision
including cost estimates for the City to take on this responsibility and feedback from
property owners and developers. Some of Council is also interested in knowing how
other Cities maintain this infrastructure.
15
3
Council directed staff to return at future regular Council meeting with an ordinance
clarifying that it is the responsibility of the properties along the alleys to maintain, repair
and improve pedestrian and drainage infrastructure adjacent to alleys.
NEXT STEPS:
1. Staff will estimate the costs for the City to maintain, repair and replace pedestrian
and drainage infrastructure in front of alleyways by Summer 2021
2. Staff will investigate how other cities handle the maintenance, repair and
replacement of sidewalks, curbs and gutters in front of alleys by Summer 2021,
3. During the summer of 2021, Staff will schedule a work session and then return to
a regular Council meeting with an ordinance clarifying that it is the responsibility
of the properties along the alleys to maintain, repair and improve pedestrian and
drainage infrastructure adjacent to alleys.
16
1
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and Council
FROM: PJ Murray, Project Manager
Pete Rice, PE, Engineering Division Manager
THROUGH: Tricia Aragon, PE, City Engineer
MEETING DATE: February 1, 2021
RE: Critical Pedestrian Connections
SUMMARY OF DISCUSSION: Staff presented an update on the Top Critical Pedestrian
Connections in town based on community, staff, and Council input. Below is a list of the,
2021 planned pedestrian connection projects and the future approved pedestrian
connection projects.
2021 Planned Project Locations:
1. Paepcke Park – Paepcke Transit Hub
2. Original St & Ute Ave
3. Gibson Ave
4. Mill St & Puppy Smith
Future Planned Projects
5. S Garmisch St (2022)
6. Spruce St (2022)
7. Koch Park (2024)
8. Francis Whitaker Park (2025)
9. Puppy Smith St (TBD)
Financial decisions were not required during the work session. No further action was
requested of council during the work session. Council was given the opportunity to
reprioritize the future planned projects if they felt it necessary.
COUNCIL DIRECTION: Council supports the list of Top Critical Pedestrian Connections
and did not choose to reprioritize the future planned projects.
Council directed staff to coordinate installation timing of the pedestrian connection along
Gibson Ave with the neighboring property (931 Gibson Ave) to prevent a dead-end
sidewalk link and to include the extension of sidewalk east on Gibson Ave to complete
this pedestrian connection to Park Circle. This includes coordinating tree removal with
Parks Department and tie in locations to the neighboring property. Council also asked
staff to include pedestrian connectivity options for Gibson Ave, to the west of Neale Ave
intersection, as a future critical pedestrian connection.
17
NEXT STEPS:
1. Complete designs for the 2021 planned pedestrian connection projects and
advertise the project through Bidnet to select a contractor. Contract to be approved
in a Council meeting in spring 2021.
2. Project manager for the 2021 projects will coordinate the timeline for the Gibson
Ave sidewalk connection project this spring, prior to construction. Pending
progress of 931 Gibson Ave private development, the connection on Gibson Ave
may occur in an out-year instead.
3. Fall 2021, staff will begin designs for the 2022 projects.
4. In early 2022, staff will update Council on the status of the Top Critical Pedestrian
Projects in Aspen.
18
1
WORK SESSION SUMMARY MEMORANDUM
TO: Mayor and Council
FROM: PJ Murray, Project Manager
Pete Rice, PE, Engineering Division Manager
THROUGH: Tricia Aragon, PE, City Engineer
MEETING DATE: February 1, 2021
RE: Safety in the Core
SUMMARY OF DISCUSSION: Council during the fall of 2020 work session and budget
session, requested Engineering to present measures to increase the safety for
pedestrians within the core. Conflict between users in the core occurs where safe,
dedicated space for pedestrians is terminated into the intersection or where infrastructure
is lacking (for example, roadways without bike infrastructure). The core predominately
favors vehicle travel and the imbalance between users can create unsafe conditions.
Staff presented two options to Council on how to improve safety in the downtown core.
1. Continue to implement intersection improvements individually that increase safety
for pedestrians and improve bicycle routing. This approach provides small
incremental improvements at intersections, but impact of the benefit is limited to
the intersection boundary.
2. To expand the improvements beyond the intersection boundaries by using a
holistic approach that considers the function of the entire corridor (intersections +
roadway). This approach would include improvements to the right-of-way (ROW)
cross section and provide safe, dedicated space for all users which improves the
overall safety of the core corridors. Staff recommended that concepts be
developed and presented to Council at a later date with options for testing these
concepts.
The Pedestrian and Bicycle Masterplan identified locations in the Core where
improvements could be implemented that were confirmed by staff:
Intersections:
1. Hopkins and Monarch
2. Hopkins and Mill St
3. Mill and Hyman
4. Hopkins and Galena
5. Galena and Hyman
6. Galena and Cooper
19
7. Durant and Mill
8. Spring and Cooper
Corridors:
1. Hopkins Ave Corridor
2. Mill St Corridor
3. Galena St Corridor
COUNCIL DIRECTION: Council supports the Engineering Department developing
concepts for corridor improvements and presenting ways to test these improvements in
the downtown core. All council members agreed that there is an opportunity for shifting
the priority of our streets from vehicle dominate to prioritize a balance between all users.
The improvements in the core should be consistent and replicable so that users can
expect interactions at the intersections and roadways to be similar.
Impacts of these improvements should be included in a future work session per Council’s
request. Council agreed that these improvements should be explored however there are
concerns as these improvements are implemented in the core, other areas of town may
experience the impacts. An example that was given is that if parking is decreased in the
core, the residential neighborhoods will experience higher vehicle presence.
NEXT STEPS:
1. The living lab at the intersection of Spring and Cooper (City Market) will be installed
Spring 2021. Data will be collected for analysis on the success of the project
through the life of the project (Spring 2021-Fall 2021). This design will evaluate the
benefits and lessons learned to present as a model template that could be applied
to intersections in the core. A driving goal is to present consistency within the core
for mode users.
2. Staff will continue to implement intersection improvement projects in the Core as
outlined in the Capital Improvement Plan.
3. Staff will develop concepts for ROW cross sections that accommodate safe,
designated areas for pedestrians and bicycles in a more holistic approach to
present to Council at a future work session. Staff will also explore options for
testing these corridor modifications. The date staff will present at another Work
Session will be determined. Estimated session to be during the summer of 2021.
20
1 | Page
INFORMATION MEMORANDUM
TO: City Council
FROM: Karen Harrington, Quality Office Director
THROUGH: Alissa Farrell, Administrative Services Director
Sara Ott, City Manager
MEETING DATE: March 23, 2021
RE: Grants Program Improvements - Next Steps
REQUEST OF COUNCIL
This is an information only memo. Staff is providing information on the next steps and the
direction provided by Council at its February 22, 2021 meeting regarding grant program
improvements.
BACKGROUND
On November 18, 2019, City Council provided direction to proceed with an evaluation of the
City’s grants programs. The primary study focus was on discerning whether and how to 1) bring
additional consistency, transparency and equity to the programs; 2) streamline and strengthen
the programs for community and grantee benefit, and 3) update and enrich the grant review
approach and processes. On February 22, 2021, Point b(e) (PBe), the City’s consultant, presented
its grant program evaluation findings and recommendations.
PROJECT RECOMMENDATIONS
The grant program recommendations are wide-ranging and encompass suggestions that will
affect the program end-to-end. The recommendations include the following:
1. Shift the timelines
2. Redefine the staffing structure
3. Consolidate the programs
4. Create multi-year partnership grants
5. Redesign and codify review committees
6. Develop strategic priorities for the funding
7. Develop scoring criteria that match the funding priorities
8. Modify the grant applications
9. Develop a communication campaign
The Grant Program Evaluation Recommendations report was previously provided to Council in
its February 22, 2021 packet. It contains the details associated with each recommendation.
21
2
SUMMARY AND NEXT STEPS
Council found value in the comprehensive approach taken to the study and its recommendations.
In general, Council approved moving forward while also providing feedback.
Staff will execute the updated Gantt chart (Exhibit A) and move forward with the following
priorities immediately:
• Transition of the dates of the grant cycle, with a grant application opening date of
November 1, 2021.
• Develop and implement the steering committee. The steering committee shall then
provide direction and oversight in the implementation of the review sub-committees.
Each review committee shall have a liaison to the steering committee.
• Staff provided immediate communication to all stakeholders regarding the approved
grants program enhancements. Staff have begun the development of a well-conceived
communication campaign to compliment the timing of the grants program
improvements.
All other recommendations shall progress in accordance to the updated Gantt Chart. The Gantt
Chart now has an updated timeline and includes further review of a potential program for capital
projects separation along with the addition of the appeal process.
Staff will also further discuss options for continual administrative costs. In the short term,
existing staff in the Quality Office with support from the City Manager’s Office will administer the
program and provide continuity while reprioritizing current workload. This model is not
sustainable in the long run. PBe suggested that typical administrative costs for grants programs
range from 5-20% of the overall fund with the median at 7 percent. This would translate to
approximately $101,000 annually. Further evaluation will include a consultant versus a part-time
staffing model to manage the administration, coordination, communication and long-term grants
program management. In addition, staff are planning to make a funding request for software.
Staff currently anticipate planning for software acquisition in 2021 (existing approaches will be
used for the 2022 grant cycle) and deploying software for the 2023 grant cycle if funding is
approved.
In the development of the funding priorities and associated scoring criteria, staff will encourage
the steering committee to vett options. Options may include stable long-term anchors such as
goals in the AACP to set funding priorities. Another option may include augmentation of Council
goals for the development of the scoring criteria. The scoring criteria would then match the
funding priorities through a scoring matrix as recommended by PBe. Additional information from
Council concerning what community outcomes are imperative shall be garnered to provide
strategic direction on the development of the criteria.
In conclusion, since the meeting, staff has:
• Sent an initial notification about the changes to the grantee community (Exhibit B)
• Updated information on the City’s grants website.
22
3
• Begun discussing the process for the composition of the steering committee and the new
review committees.
• Begun outlining the grants communication plan.
• Begun conversation to separate budget lines for HHS grants and HHS intergovernmental
agreements (IGAs).
• Updated the project schedule
23
4
Exhibit A. Updated Project Schedule
TASKS 21-Feb 21-Mar 21-Apr 21-May 21-Jun 21-Jul 21-Aug 21-Sep 21-Oct 21-Nov 21-Dec 21-Jan 21-Feb 21-Mar 21-Apr
Finalize grant round opening date
Initial communication with grantees and reviewers re
changes
Open 2022 grant round
Finalize amount of 2022 grant funds (Council)
Close 2022 grant round
Review applications
Bring funding recommendations to Council
Distribute contracts
Distribute funding
Evaluate staffing structure or consultant approach.
Select staffing option
Separate funding line for HHS grants and HHS IGAs
Communicate process change to HHS applicant pool
Develop committee options for City Manager review
Approve committee structure and charters
Solicit committee members
Train committee members
Implement committee changes
Prepare guidance document on City priorities
Share guidance with Steering Committee (SC)
Collaborate with SC to propose grant funding priorities
that are in alignment with City priorities
Develop agreement on purpose/use/role of scoring
criteria
Develop draft scoring criteria, based on priorities
Design appeal process
Develop draft application forms (under $10,000, over
$10,000, potentiall capital)
Implement final forms in 2022 grant cycle
Verify target audiences
Develop draft communication plan
Send initial message re grant cycle and other upcoming
changes
Develop additional key messages re 2022 cycle
Select communication media, timing and frequency
Implement touch points according to timelines
Plan for partnerships: Develop/update eligibility criteria,
gather key stakeholder feedback, develop grant
parameters and monitoring process for 1 and 3-year
grants
Implement Partnership grants (2023 grant cycle)
Plan for new software: Define process and
requirements; develop RFQ; advertise; evaluate
proposals
Select and contract with vendor
Develop and go-live for 2023 grant cycle
Secure grants software
Align scoring criteria with funding priorities
Modify grant applications
Develop communication campaign
Shift the grants timeline
Redefine staffing structure
Consolidate grant programs
Create 3-year partnership grant program
Redesign and codify grant committees
Develop strategic priorities for funding
24
5
Exhibit B. Initial Correspondence with Grantees Regarding Upcoming Program Changes
Sent February 26, 2021 to all grantees on City contact lists:
Good afternoon to each of you,
Since 2011, the City of Aspen has contributed more than $13 million in grant funding to our
local non-profits in recognition of the vital role they play in our community. A deep enrichment
in education, arts and culture, mental and physical health, the environment and other facets of
our lives in the valley occurs because of your efforts.
In recognition of the richness your efforts bring to the fabric of our community, and the
importance of our grant’s programs, City Council approved a grants evaluation study in late
2019. The start of the project was delayed until fall 2020 because of COVID. Many of you
participated in the project, some serving as Steering Committee members and others
participating in the grantee survey our consultants (Point b(e)) distributed. At its Work Session
on February 22, City Council discussed the study recommendations and approved moving
forward with the proposed improvements.
As we move forward with the details for implementation, we will further discuss specific areas
with Council; however, overall consensus to move forward with the general recommendations
has been provided. If you would like to review the Council packet or listen to the discussion, it
will soon be posted here: https://www.cityofaspen.com/1225/Current-City-Webcast-Meetings-
Agendas
While many details are yet to be developed, we wanted to let you know as soon as possible
about the changes so you can plan accordingly. Among the shifts you will see are the following:
• Changes to the grant application timelines: First and foremost, the grant cycle is being
shortened. Instead of opening the 2022 grant round in the spring, we will open it in the
fall. The exact date is not yet settled, but you can expect it to be in November. The
date of the funds distribution will remain in April.
• Integrated City grant programs: The City will be integrating all of its grants programs,
separating the HHS granting process from the County. Specific program funding areas
(Wheeler, Community Nonprofit, and HHS) will remain.
• Streamlined grant application forms: The application form will be improved, and we
will have separate applications forms for small requests ($10,000 or less) and larger
requests.
• Clarified grant priorities and review criteria: Clarity in the purposes of the grant
programs and the ends they are trying to achieve is important. Conversations this year
25
6
will seek that clarification and translate it into funding priorities. Those funding
priorities will then be reflected in more transparent and shared review criteria.
• A refresh of our grant committees: We have had dedicated grant reviewers for many
years who have carried a heavy load. This year, we will be lightening that load, creating
an overarching policy-oriented Steering Committee, and separate review committees
for each of our three grant programs. This approach shares the work, while also
providing an opportunity for more community members to participate in the programs.
Other improvements we’ll be working on, but which we don’t anticipate implementing until the
2023 grant cycle, include the deployment of a more robust grant management software tool
and the deployment of a 3-year grant partnership option.
As we move forward with crafting the details, we will share email updates, opportunities for
input, and notices of virtual outreach sessions regularly. Thank you again for your commitment
to making Aspen and the broader valley a wonderful place to live! If you have questions about
the upcoming changes, please feel free to contact Karen Harrington at
karen.harrington@cityofaspen.com or at 970-456-8259.
26