HomeMy WebLinkAboutresolution.council.043-21 RESOLUTION #43
(Series of 2021)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN,
COLORADO, APPROVING A CONTRACT CHANGE ORDER #1 PACKAGE
BETWEEN THE CITY OF ASPEN AND SHAW BUILDERS LLC,
AUTHORIZING THE CITY MANAGER TO EXECUTE SAID CONTRACT
CHANGE ORDER ON BEHALF OF THE CITY OF ASPEN, COLORADO.
WHEREAS, there has been submitted to the City Council a Contract Change
Order#1 package between the City of Aspen and Shaw Builders LLC, a true and
accurate copy of which is attached hereto as "Exhibit A";
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO,
That the City Council of the City of Aspen hereby approves the Contract
Change Order#1 package between the City of Aspen and Shaw Builders LLC, a
copy of which is annexed hereto and incorporated herein, and does hereby
authorize the City Manager to execute said Contract Change Order#1 package on
• behalf of the City of Aspen.
INTRODUCED, READ AND ADOPTED by the City Council of the City of
Aspen on the 271h day of April, 2021.
Torre, Mayor
I, Nicole Henning, duly appointed and acting City Clerk do certify that the
foregoing is a true and accurate copy of that resolution adopted by the City Council
of the City of Aspen, Colorado, at a meeting held April 27, 2021.
r
_ n
Nicole Henning, City Clerk
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
ICXr1IUIt A - Snaw buncierS unange Vraer 4 1
SHAW Change Order No. 01
PROJECT: CHANGE ORDER NUMBER: 01
Burlingame Ranch Phase 3 DATE: April 14,2021
Section 2,Township 10 South, Range 85 West of the
6th P.M.
TO CONTRACTOR:
Shaw Builders LLC
300 Kalamath Street
Denver,CO 80223
THE CONTRACT IS CHANGED AS FOLLOWS:
CO Item# PCO# Description Amount
001 002 Radon Allowance Use $33,707.24
001 004 Balcony Waterproofing Allowance Use ($55,056.81)
001 005 Integral Gutter Allowance Use $7,936.64
001 019 Credit for Removal of Trusses ($22,659.60)
001 020 Knifeplates Allowance Use $8,250.65
001 021 Building Material Escalation $134.995.95
001 022 Carport Material Escalation $87,826.93
001 031 Mech, Elec, Conc for Addendum 002 $174,675.01
Net Total: $369,676.01
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWChange Order No. 01
Original Contract sum was $27,581,107.00
Net change by previously authorized Change Orders $0.00
The Contract sum prior to this Change Order was $27,581,107.00
The Contract sum will be INCREASED by this Change Order in the amount of $369,676.01
The new Contract sum including this change order $27,950,783.01
The Contract time will be unchanged.
The date of Substantial Completion as of the date of this Change Order therefore is September 01,2022.
NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER.
Shaw Builders LLC Aspen,City of
Contractor Owner
300 Kalamath Street,Denver,CO 80223 130 Galena Street,Aspen,CO 81611
Address Address
Mark Hendrickson Sara Oft
• Y•
Name � ley \ -�/Z� Name �� O
By (Signature) / By (Signature) "'
4/28/21 5/4/2021 1 11:02:32 AM PDT
Date Date
r
u
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
r-amonimmag� No. 002
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
• No.002 Radon Allowance Use .. 2/1/2021
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal:
Per discussion with 359 we do not need to upgrade the vapor barrier for radon. If we need to increase the current
10 mill vapor barrier to 15 or 25 there will be additional cost.
Cost Summary for Item 1 Plumbing
Phase Description Quantity Unit Price Amount
• 015510- -002 Radon Allowance Use 1 LS 67,792.00 67,792.00
Net Total for Item 1: $67,792.00
Description Percentage Amount
DIC Insurance 0.25% 169.48 Total Item #1: $73,153.00
Warranty Reserve 0.61% 413.53
Cloud Technology Service 0.14% 94.91 Time Extension: NONE
Bonds 0.80% 542.34
Fee 6.00% 4,140.74
Subtotal: $5,361.00
Cost Summary for Item 3 Fans
Phase Description Quantity Unit Price Amount
015100- -002 Radon Allowance Use 1 LS 6,760.00 6,760.00
Net Total for Item 3: $6,760.00
Description Percentage Amount
DIC Insurance 0.25% 16.90 Total Item #3: $7,294.58
Warranty Reserve 0.61% 41.24
Cloud Technology Service 0.14% 9.46 Time Extension: NONE
Bonds 0.80% 54.08
Fee 6.00% 412.90
Subtotal: $534.58
•
Page I of 3
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW Pending Change Order
No. 002
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
Cost Summary for Item 6 Electrical
Phase Description Quantity Unit Price Amount
016000- -002 Radon Allowance Use 1 LS 12,647.00 12,647.00
Net Total for Item 6: $12,647.00
Description Percentage Amount
DIC Insurance 0.25% 31.62 Total Item #6: $13,647.14
Warranty Reserve 0.61% 77.15
Cloud Technology Service 0.14% 17.71 Time Extension: NONE
Bonds 0.80% 101.18
Fee 6.00% 772.48
Subtotal: $1,000.14
`.Cost Summary for Item 7 Radon Allowance Use
Phase Description Quantity Unit Price Amount
018160- -002 Radon Allowance Use 1 LS -65,000.00 -65,000.00 •
Net Total for Item 7. $-65,000.00
Description Percentage Amount
DIC Insurance 0.25% -162.50 Total Item #7: $-70,140.20
Warranty Reserve 0.61% -396.50
Cloud Technology Service 0.14% -91.00 Time Extension: NONE
Bonds 0.80% -520.00
Fee 6.00% -3,970.20
Subtotal: $-5,140.20
Cost Summary for Item 8 Washed Rock
Phase Description Quantity Unit Price Amount
002300- - Earthwork&Site Utilities 1 LS 9,038.00 9,038.00
Net Total for Item 8: $9,038.00
Description Percentage Amount
Bonds 0.80% 72.30 Total Item #8: $9,752.72
Fee 6.00% 552.04
DIC Insurance 0.25% 22.60 Time Extension: NONE
Warranty Reserve 0.61% 55.13
Cloud Technology Service 0.14% 12.65
Subtotal: $714.72
Page 2 of 3
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW Pending Change Order
No. 002
Burlingame Ranch Phase 3 Project No:20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
Grand Total PCO#002: $33,707.24
Total Time Extension: NONE
Submitted By: Shaw Builders LLC
Signature Date 4/28/21
•
Name Mark Hendrickson, Project Manager
Page 3 of 3
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
581 N.Commercial Dr.
+ Grand Junction,CO 81505
970245-0171--Fax 970245-3855
wwtar.cookeys.com
CHANGE ORDER
Attn: Mark Hendrickson Date: 1-8-2021
Project#:Burlingame Phase 3
Reference:Adddendum 2
Sheets: Cast Iron Risers/Radon piping
RADON PIPING
Description of Change: Supply PVC pipe and fittings for radon piping in crawl space and vented out
roof. Excludes exhaust fans and controls provided by Comfort air.Vapor barrier and sealing of
barrier provided by other.
1. Material: Sch 40 PVC pipe and fittings $16,931.00
2. Labor: $43,030.00
3.Taxe: 9.2% $1,557.65
4. Profit and Overhead 10%: $6,151.86
5.Total: $67,670.51
Textura Fee: $121.80
Total this change: $67,792.31
VERTICAL CAST IRON RISERS
des '' ti�on of change: Install vertical cast iron risers to horizontal point of connection provi
Gruden. Pr delest for each section of pipe installed by Cookeys for local inspec ccludes
rough testing of manu ed piping.
1. Materials:Cast iron pipe, Test Tees, Misc rtt' S. $66,263.51
2. Labor: $102,087.00
3.Taxes 9.2% $6,096.24
4. Profit and Overhead 10° $17,444.67
Textura Fee: $345.00
Total anger $19 , 6-82,
The Original Contract Sum-----__—_ ___ $1,262,197.00
Net change by previously approved change orders- $0.00
The contract sum prior to this change order------------------_-------------------_ $1,262,197.00
The contract sum will be increased/decreased by---- ___----- 260,029.00
The new contract sum including this change order- $1,522,226.00
This change order becomes part of and is subject to all of the terms, conditions, and provisions of the above •
referenced subcontract.
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
,COMFORT R.of Grand Junction,
HEATIN_G;COOLIGN &SHEET METAL - -�-�-- r
746 Scarlet Drive •`z,Grand Junction,CO 81505
Phone: 970-254-1170-Fax:•970-254-1178
Addendum 002
To: Shaw Construction Date: January 13,2021
Job: Burlinggame Ranch
Attn: Mark Hendrickson
Phone: 970-242-9236
Fax:
Scope of Work: HVAC
Item 1: Install crawlspace ventilation and radon exhaust fans
Cr� ce Exhaust System- 13 Systems
Exha� ns and exhaust ducting
Intake ducting wall cap
Dehumidification con d outdoor air temperature cutoff switch
Pricing-$3,200.00 per system
Total Crawlspace Exhaust System $41.600.
Radon Venting
Radon Exhaust Fan
- Manometer on negative side of fan
- Radon Piping by Others
Pricing-$520.00 per system
Total Radon Exhaust Fans- $6,760.00
•
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
EMAIL:LASSITERELECTRIC(gGMAIL.COM
RFC#01
CUSTOMER: January 26,2021
SHAW CONSTRUCTION
760 HORIZON DRIVE
GRAND JUNCTION,CO 81506
MARK HENDRICKSON
markhenddckson@shawconstruction.net
SCENARIO:
ADDENDUM#2 WAS ISSUED WITH ELECTRICAL REVISIONS IADDITIONS
REASON:
PER ADDENDUM#2,ADDITION OF RADON FAN CIRCUITS
SOLUTION:
L.E.I.TO PRICE ALL TIME AND MATERIAL FOR ADDED SCOPE
WE HEREBY PROPOSE TO PROVIDE LABOR AND MATERIALS FOR THE FOLLOWING
INSTALLATION LOCATED AT:
BURLINGAME PHASE 3
PER PLANS AND SPECIFICATIONS FROM:
359 DESIGN ADDENDUM#2 PLAN SET DATED:12116120
EI-01-08
ELECTRICAL POWER PLAN BUILDING 8 HOURSPER s85/HR Mlsc
QTY Item EACH REM LABOR MATERIAL
1 EF-2 EAST BUILDING;HOOK UP ONLY 2 $170.00 $48.00
1 EF-3 EAST BUILDING;HOOK UP ONLY 2 $170.00 $48.00
1 EF-2 WEST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
1 EF-3 WEST BUILDING;HOOK UP ONLY@ 120' 6 $510.00 $210.00
E1-01-09
ELECTRICAL POWER PLAN BUILDING 9 HOURS PER t85/HR Mlsc
QTY Item EACH REM LABOR MATERIAL
1 EF-2 WEST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-3 WEST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-2 EAST BUILDING;HOOK UP ONLY Q 120' 6 $510.00 $210.00
1 EF-3 EAST BUILDING;HOOK UP ONLY C 120' 6 $510.00 $21000
Page 1 of 3
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
• E7.01.10
ELECTRICAL POWER PLAN BUILDING 10 HOURSPER SBsfHR Mac
QTY Item EACH ITEM LABOR MATERIAL
1 EF-2;HOOK UP ONLY 1.5 $127.50 $46.00
1 EF-3;HOOK UP ONLY 1.5 $127.50 $48.00
E1-01.11
ELECTRICAL POWER PLAN BUILDING 11 HOURSPER f85fHR Mac
QTY Item EACH REM LABOR MATERIAL
1 EF-2;HOOK UP ONLY 1.5 $127.50 $48.00 '
1 EF-3;HOOK UP ONLY 1.5 $127.50 $48.00
E1-01-12
ELECTRICAL POWER PLAN BUILDING 12A
HOURSPER faSMR MaC
QTY Item EACH ITEM LABOR MATERIAL
1 EF-2 WEST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-3 WEST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-2 EAST BUILDING;HOOK UP ONLY 120' 6 $510.00 $210.00
1 EF-3 EAST BUILDING;HOOK UP ONLY 120' 6 $510.00 $210.00
E1-01-12
ELECTRICAL POWER PLAN BUILDING 12B
HOURSPER f851HR MISC
QTY Item EACH REM LABOR MATERIAL
1 EF-2 WEST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-3 WEST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-2 EAST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
1 EF-3 EAST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
E1-01.13
ELECTRICAL POWER PLAN BUILDING 13 HOURSPER f85MR Mac
QTY Item EACH ITEM LABOR MATERIAL
1 EF-2 EAST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
• 1 EF-3 EAST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-2 WEST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
1 EF-3 WEST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
E1-01-14
ELECTRICAL POWER PLAN BUILDING 14
HOURSPER f85MR MISC
QTY Item EACH ITEM LABOR MATERIAL
1 EF-2 EAST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-3 EAST BUILDING;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-2 WEST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
1 EF-3 WEST BUILDING;HOOK UP ONLY @ 120' 6 $510.00 $210.00
E1-01-15
ELECTRICAL POWER PLAN BUILDING 15 HOURSPER f851HR Mac
QTY Item EACH REM LABOR MATERIAL ,
1 EF-2;HOOK UP ONLY 1.5 $127.50 $48.00
1 EF-3;HOOK UP ONLY 1.5 $127.50 $48.00
Page 2 of 3
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
RFC: •
LABOR $8,500.00
PROJECT ENGINEERING $300.00
MATERIAL;MISCELLANEOUS $3,384.00
TAX ON MATERIALS-EXEMPT $0.00
TOTAL LABOR&MATERIALS $12,184.00
ALLOWED 10%FOR PROFIT/OVERHEAD(MATERIAL ONLY) $338.40
GRAND TOTAL LABOR&MATERIALS $12,522.40
BOND FEE 1%OF TOTAL $125.22
TOTAL LABOR,MATERIALS,BOND: $12,647.62
FIXTURES:FIXTURES SUPPLIED BY OWNER AND INSTALLED BY ELECTRICIAN MUST BE UL APPROVED.IF
NOT UL APPROVED,THERE MAY BE ADDITIONAL CHARGES TO HAVE MADE SO. FIXTURES MUST BE MADE
AVAILABLE TO HANG PRIOR TO FINAL INSPECTION OR THERE MAY BE ADDITIONAL CHARGES.
INSTALLATION OF OWNER-SUPPLIED FIXTURES AFTER FINAL INSPECTION WILL BE BILLED AS A
CHANGE AT CHANGE ORDER RATES.
BOXES:ELEVATIONS AND LOCATIONS FOR ALL BOXES ARE REQUIRED PRIOR TO START OF JOB. IF THESE ARE
UNAVAILABLE AT START,THERE MAY BE AN EXTRA FEE APPLIED TO INSTALL BOXES OR DEMO AFTER ROUGH IN.
PAYMENTS:PAYMENT IS DUE WITHIN 30 DAYS OF INVOICE DATE. OVERDUE PAYMENTS ARE SUBJECT TO 1.5%
MONTHLY INTEREST. CUSTOMER EXPRESSLY AGREES TO PAY CONTRACTOR'S REASONABLE ATTORNEYS'FEES
FOR COLLECTION.
LABOR:PRICE IS BASED ON WORK BEING PERFORMED DURING NORMAL LASSITER ELECTRIC,INC.
HOURS OF OPERATION AND DOES NOT INCLUDE ACCELERATION OF A FIXED SCHEDULE OR OVERTIME.
ANY ACCELERATED SCHEDULE WILL BE DISCUSSED WITH G.C.PRIOR TO START OF NEW SCHEDULE.
TAXES:ANY CHANGE IN TAX RATES DURING THE DURATION OF THE PROJECT WILL RESULT IN USAGE OF THE
CURRENT TAX RATE(FOR BILLING PURPOSES)AS OPPOSED TO THE TAX RATE ON THIS PROPOSAL.
SHAW CONSTRUCTION HAS REVIEWED THE ABOVE REQUEST FOR CHANGE TO BE PERFORMED AT:
BURLINGAME PHASE 3 ADDENDUM 92
WE AGREE TO ACCEPT THIS REQUEST FOR CHANGE AND ABIDE BY THE TERMS STATED THEREIN.
Page 3 of
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
92GGjt4 Aspen Digger
41 0075 Sopris Ave,
0 Z Carbondale,CO 81623
41 970-963-2157
To: Shaw Construction Contact: Jamie Neyers
Address: 760 Horizon Drive Phone: (970)242-9236
Grand 3unction,CO 81506 Fax: (970)241-5618
Project Name: Burlingame Phase III Bid Number: 20230311 SH
Project Location: Burlingame Ranch,Aspen,CO Bid Date: 11/3/2020
Item O Item Description Estimated Quantity Unit Unit Price Total Price
23.5 Crawlspace Slab Prep Change Order 705.00 TON $12.82 $9,038.10
Total Bid Price: $9,038.10
Notes:
• The above prices do not include Performance and Payment Bond.Add 3%if bond is required.
' The above prices do not include Permits.
The above prices do not include any utility shut off or abandonment.
• The above prices do not Include accepting payment via credit card or online payment services.If these services are required,please add 3%.
4/1/20213:15:12 PM Page 1 of 1
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
No. 004
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
PCO No. 004 Balcony Waterproofing Allowance Use Date Sent:
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal:
Cost Summary for Item 4 Balcony Waterproofing Allowance Use
Phase Description Quantity Unit Price Amount
007310- -004 Electrical 1 LS 107,164.00 107,164.00
Net Total for Item 4: $107,164.00
Description Percentage Amount
DIC Insurance 0.25% 267.91 Total Item #4: $115,638.53
Warranty Reserve 0.61% 653.70
Cloud Technology Service 0.14% 150.03 Time Extension: NONE
Bonds 0.80% 857.31
Fee 6.00% 6,545.58
Subtotal: $8,474.63
Cost Summary for Item 5 Balcony Waterproofing Allowance Use
Phase Description Quantity Unit Price Amount
018320- -004 Allowance Credit 1 LS -255,220.00 -255,220.00
Net Total for Item 5: $-255,220.00
Description Percentage Amount
DIC Insurance 0.25% -638.05 Total Item #5: $-275,402.80
Warranty Reserve 0.61% -1,556.84
Cloud Technology Service 0.14% -357.31 Time Extension: NONE
Bonds 0.80% -2,041.76
Fee 6.00% -15,588.84
Subtotal: $-20,182.80
Page I of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW Pending Change Order
i No. 004
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
,Cost Summary for Item 6 Balcony Waterproofing Allowance Use
6,931 sf @ 6.00/sf for protection board
6,931 sf @ 4.00/sf for plywood
Painting @ 4.00/sf painting plywood
Phase Description Quantity Unit Price Amount
006150- -004 Protection Board and Plywood Pe; 1 LS 97,034.00 97,034.00
Net Total for Item 6: $97,034.00
Description Percentage Amount
DIC Insurance 0.25% 242.59 Total Item #6: $104,707.46
Warranty Reserve 0.61% 591.91
Cloud Technology Service 0.14% 135.85 Time Extension: NONE
Bonds 0.80% 776.27
Fee 6.00% 5,926.84
Subtotal: $7,673.46
Grand Total PCO#004: $-55,056.81
Total Time Extension: NONE
Submitted By: Shaw Builders LLC
,1 ,
Signature Date 4/28/21
Name
Mark Hendrickson, Project Manager
Page 2 of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SChange Order Request Form
5470 Lincoln St.
Denver, CO 80216
303-758-7663
Project Name and Location
Burlingame Ranch-Phase III-EPDM
0045 Mining Stock Pwky.Aspen, CO
Contractor/CM/DB Name
Shaw Construction
Basis of Change Order
Error/Omission Differing Site Condition
Owner Request Field Resolution e
Value Engineering Other
Adjustment to the Contract Time for Completion* Adjustment to the Contract Sum
Contract Days Changed 48 Original Contract Amount $519,103.00
Revised Completion*Date Change Order Amount! $107,164.00
Revised Contract Sum $626,267.00
Description(attach additional pages as necessary)
Building: Lower Units EPDM Integral GXeaer units
Building 8 (956 SF) $14,400
Building 9 (1,034 SF) $16,954 Building 10 (720 SF) $12,341 Building 11 (790 SF) $12,510 Building 12 (1,280 SF) $17,316 Building 13 (1,059 SF) $14,298 Building 14 (303 SF) $7,112 Building 15 (789 SF) $12,233
$107,164.00
Justification(attach additional pages as necessary)
Sequencing of additional trades may affect contract days added.
This Change Order identifies and provides full and complete satisfaction for all direct and indirect costs,including interest and all related
extensions to the Contract Time for Completion*,for the described changes in this scope of the Work and shall not serve as the basis for a
cumulative impact Claim.
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
No. 005
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
PCO No. 005 Integral Gutter Allowance Use Date Sent: 2/12/2021
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal:
No heat trace has been included in the reconciliation for the allowance. If heat trace is added we will submit as a
separate change order.
Cost Summary for Item 1 Integral Gutter Allowance Use
Phase Description Quantity Unit Price Amount
007310- -005 General Conditions 1 LS 32,355.00 32,355.00
Net Total for Item 1: $32,355.00
Description Percentage Amount
DIC Insurance 0.25% 80.89 Total Item #1: $34,913.64
Warranty Reserve 0.61% 197.37
Cloud Technology Service 0.14% 45.30 Time Extension: NONE
Bonds 0.80% 258.84
Fee 6.00% 1,976.24
Subtotal: $2,558.64
Cost Summary for Item 2 Integral Gutter4Allowance Use
Phase Description Quantity Unit Price Amount
018190- -005 General Conditions 1 LS -25,000.00 -25,000.00
Net Total for Item 2: $-25,000.00
Description Percentage Amount
DIG Insurance 0.25% -62.50 Total Item #2: $-26,977.00
Warranty Reserve 0.61% -152.50
Cloud Technology Service 0.14% -35.00 Time Extension: NONE
Bonds 0.80% -200.00
Fee 6.00% -1,527.00
Subtotal: $-1,977.00
Page I of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
No. 005
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
Grand Total PCO#005: $7,936.64
Total Time Extension: NONE
Submitted Bye: Shaw Builders LLC
Signature ��'` Date 4/28/21
Name Mark Hendrickson, Project Manager
Page 2 of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
D• Change Order Request Form
5470 Lincoln St.
Denver, CO 80216
303-758-7663
Project Name and Location
Burlingame Ranch-Phase III-EPDM
0045 Mining Stock Pwky.Aspen, CO
Contractor/CM/DB Name
Shaw Construction
Basis of Change Order
Error/Omission Differing Site Condition
Owner Request Field Resolution X
Value Engineering Other
Adjustment to the Contract Time for Completion* Adjustment to the Contract Sum
Contract Days Changed 48 Original Contract Amount $519,103.00
Revised Completion*Date Change Order Amount, $107,164.00
Revised Contract Sum $626,267.00
Description(attach additional pages as necessary)
Building: Lo er Units EPDM Integral Gutters at lower units
• Building 8 (956 SF) 14,40 $3,530
Building 9 (1,034 SF) 6,9 4 $4,609
Building 10 (720 SF) 02,341 $3,878
Building 11 (790 SF) Al2,23
$3,910
Building 12 (1,280 SF) $6,239
Building 13 (1,059 SF) $4,367
Building 14 (303 SF) $1,944
Building 15 (789 SF) $3,878
$32,355.00
Justification(attach additional pages as necessary)
Sequencing of additional trades may affect contract days added.
This Change Order identifies and provides full and complete satisfaction for all direct and indirect costs,Including interest and all related
extensions to the Contract Time for Completion*,for the described changes in this scope of the Work and shall not serve as the basis for a
cumulative impact Claim.
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW Pending Change Order
No. 019
Burlingame Ranch Phase 3 Project No:20268-
Section 2,Township 10 South, Range 85 West of the 6th P.M.
Aspen, CO 81611
PCO No.019 Credit for removed trusses Date Sent:3/15/2021
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal:
Credit for removed trusses#8,9, 13, 14
Cost Summary for Item 1 Credit for removed trusses -
Phase Description Quantity Unit Price Amount
006165- -019 Credit for removed trusses#8,9, 13, 14 1 LS -20,999.00 -20,999.00
Net Total for Item 1: $-20,999.00
Description Percentage Amount
DIC Insurance 0.25% -52.50 Total Item#1: $-22,659.60
Warranty Reserve 0.61% -128.09
Cloud Technology Services 0.14% -29.40 Time Extension: NONE
Bonds 0.80% -167.99
Fee 6.00% -1,282.62
Subtotal. $-1,660.60
Grand Total PCO#019: $-22,659.60
Total Time Extension: NONE
Submitted By. Shaw Builders LLC
Signature " -"' ' Date 4/28/21
Name Mark Hendrickson,Project Manager
Page 1 of 1
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
4PSHAW PRICING REQUEST
PCO#: 3
SUBMITTED TO: SHAW BUILDERS,LLC. DATE: 03/12/21
CREDITED TO: SHAW BUILDERS,LLC. JOB#: 20268-70
JOB NAME: Burlingame Ranch 3
CHANGE DOCUMENT: Credit for Removed Trusses#8,9,13,14
PLEASE FURNISH ALL MATERIALS AND LABOR NECESSARY TO COMPLETE THE FOLLOWING WORK AND CHARGE OUR ACCOUNT AS NOTED BELOW.
WORK TO BE COMPLETED: Perform the work associated with the above change Request.
DESCRIPTION QTY UM UNIT COST LABOR MATERIAL EQUIP. SUBCONTR.
LABOR 127 HR $57 (9,800.00)
MATERIALS LS (9,290.00)
i i i i I i --d
SUB-TOAL (19,090.00) 0.00
SUB-TOTAL W/ 10 %OH&P 1 (20,999.00)1 0.00
TOTAL COST 1 (20,999.00)
THE ABOVE WORK IS TO BE PAID FOR AT ACTUAL COST OF LABOR AND MATERIALS.
CREATED BY: Will Meyer DATE: 03/12/21
NOTES:
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
Doug Sehr
E.Smith Road
Builders. 176 0 e1+332884214
Aurora,Co 80011
fax+303 287 1922
Does It Best: www.buildersdenver.com
Proposal Submitted To: Joel Page: 1 of 2 Date: 2/9/2021
Name: Shaw Construction Job Name: Burlingame Apts
Address: 300 Kalamath St Address:
City: Denver State: CO City: Aspen State: CO
-------------------------------------------------------------------------------------------------------------------------------------
Roof Trusses:Pitch per print,24"o.c.;75-10-10 loading,Deflection,and Heel Height Per Plan.
Includes roof trusses,truss to truss/beam hardware,H2.5a clips,blocking panels per plans,valley trusses,component engineering,
placement plans,and jobsite delivery.Excludes All 2x materials,parapets,LVL beams,bridging and bracing.
Plans dated 6-19-20 marked 90 CD.
Bldg 8 Roof: $29,120 Bldg 12 Roof: $48,860
Bldg 9 Roof: $28,230 Bldg 13 Roof: $28,650
Bldg 10 Roof: $15,050 Bldg 14 Roof: $28,560
Bldg 11 Roof: $15,070 Bldg 15 Roof: $15,200
Total: $208,740 plus tax
Bldg 10 Truss Option: Add$17,030
Bldg 11 Truss Option: Add$13,300
Bldg 15 Truss Option: Add$19,280
** Option to replace roof joist as per plan. 20"heel on low end with 0.25/12 pitch. We included 5'parapets on each end.
Bldg 8 Truss Option: deduct$2,250
Bldg 9 Truss Option: deduct$2,250,
Bldg 13 Truss Option: deduct$2,250
Bldg 14 Truss Option: deduct$2,540
** Option do eliminate lower roof trusses at Pods B.
All prices exclude sales tax.
-------------------------------------------------------------------------------------------------------------------------------------
*****No sales tax is included in quoted price*****
We hereby propose to furnish materials complete in accordance with the above specifications for the sum of: see Above.Tax Excluded.
Submitted By: Doug Sehr
The undersigned hereby accepts in full the forgoing Proposal as a binding contract including the prices,specifications and conditions
set forth herein. Builders is hereby authorized to commence performance of the work as specified and payment will be made as set
forth above and per terms and conditions of credit application.
�2 III�I145
I I I I I
III II 1I 11111111116 III1I 1,1111111,11111111111117
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW Pending Change Order
No. 020
Burlingame Ranch Phase 3 Project No:20268-
Section 2,Township 10 South, Range 85 West of the 6th P.M.
Aspen, CO 81611
• No.020 Balcony, .. . Date Sent:3/15/2021
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel.,970-248-2619
Aspen, CO 81611 Fax:
Email.markhendrickson@shawconstruction.net
Description of Proposal:
Balcony, Breezeway,&Carport Knifeplates.
Cost Summary for Item:1 Balcony,Breezeway,&Carport Knifeplates
Phase Description Quantity Unit Price Amount
006165- -020 Balcony,Breezeway,&Carport Knifeplates 1 LS 63,646.00 63,646.00
Net Total for Item 1: $63,646.00
Description Percentage Amount
DIC Insurance 0.25% 159.12 Total Item#1: $68,679.13
Warranty Reserve 0.61% 388.24
Cloud Technology Services 0.14% 89.10 Time Extension: NONE
Bonds 0.80% 509.17
Fee 6.00% 3,887.50
Subtotal: $5,033.13
Cost Summary for Item 2 Timber to Modular Allowance
Phase Description Quantity Unit Price Amount
018280- -020 Allowance-Balcony,Breezeway,&Carport Knifeplates 1 LS -56,000.00 -56,000.00
Net Total for Item 2: $-561000.00
Description Percentage Amount
DIC Insurance 0.25% -140.00 Total Item#2: $-60,428.48
Warranty Reserve 0.61% -341.60
Cloud Technology Services 0.14% -78.40 Time Extension: NONE
Bonds 0.80% -448.00
Fee 6.00% -3,420.48
Subtotal: $4,428.48
Page I oft
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW Pending Change Order
No. 020
Burlingame Ranch Phase 3 Project No:20268-
Section 2,Township 10 South,Range 85 West of the 6th P.M.
Aspen, CO 81611
Grand Total PCO#020: $8,250.65
Total Time Extension: NONE
Submitted By: Shaw Builders LLC
1
Signature '' w Date 4/28/21
Name Mark Hendrickson, Project Manager
Page 2 of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
4PSHAW , PRICING REQUEST
i
PCO#: 5
SUBMITTED TO: SHAW BUILDERS,LLC. DATE: 03/12/21
CREDITED TO: SHAW BUILDERS,LLC. JOB#: 20268-70
JOB NAME: Burlingame Ranch 3
CHANGE DOCUMENT: Balcony,Breezeway,&Carport Knlfeplates
PLEASE FURNISH ALL MATERIALS AND LABOR NECESSARY TO COMPLETE THE FOLLOWING WORK AND CHARGE OUR ACCOUNT AS NOTED BELOW.
WORK TO BE COMPLETED: Perform the work associated with the above change Request.
DESCRIPTION QTY UM UNIT COST LABOR MATERIAL EQUIP. SUBCONTR.
MATERIALS LS 57,860.00
SUB-TOTAL W/ 10 %OH&P 1 63,646.00
TOTAL COST 1 $63,646.00
THE ABOVE WORK IS TO BE PAID FOR AT ACTUAL COST OF LABOR AND MATERIALS.
CREATED BY: Will Meyer DATE: 03/12/21
NOTES:
DocuSi9 n Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
P
Building
Lamwood Building base Knife Plates treatment Total
Building#8 20,850.00 5,810.00 2,840.00 29,500.00
Building#9 20,800.00 5,810.00 2,850.00 29,460.00
Building#10 19,700.00 5,560.00 3,140.00 28,400.00
Building#11 19,700.00 5,560.00 3,140.00 28,400.00
Building#12 25,180.00 5,560.00 3,550.00 34,290.00
Building#13 21,040.00 6,100.00 3,400.00 30,540.00
Building#14 17,580.00 4,100.00 2,490.00 24,170.00
Building#15 19,370.00 5,250.00 3,110.00 27,730.00
164,220.00 r43,750.00 24,520.00 232,490.00
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
Lamwood carport base Knife plates treatment Total
CP#8 11,700.00 1,900.00 2,120.00 15,720.00
CP#9 10,670.00 1,900.00 2,120.00 14,690.00
CP#10 6,920.00 1,200.00 1,230.00 9,350.00
CP#11 11,100.00 1,800.00 2,110.00 15,010.00
CP#12 13,550.00 1,950.00 2,700.00 18,200.00
CP#13 11,000.00 1,900.00 2,180.00 15,080.00
CP#14 8,790.00 1,560.00 1,680.00 12,030.00
CP#15 10,790.00 1,900.00 2,120.00 14,810.00
84,520.00 14,110.00 16,260.00 114,890.00
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
No. 021
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
PCO No. 021 Building Material Escalation Date Sent: 3/15/2021
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal:
Building Material Escalation-Framing
Cost Summary for Item . 1 Building Material Escalation
Phase Description Quantity Unit Price Amount
006165- -021 Building Material Escalation-Frar 1 LS 132,609.00 132,609.00
Net Total for Item 1: $132,609.00
Description Percentage Amount
DIC Insurance 0.25% 331.52 Total Item #1: $134,995.95
Warranty Reserve 0.61% 808.91
Cloud Technology Service 0.14% 185.65 Time Extension: NONE
Bonds 0.80% 1,060.87
Subtotal: $2,386.95
Grand Total PCO #021: $134,995.95
Total Time Extension: NONE
Submitted By: Shaw Builders LLC
_
Signature `,- Date 4/28/21
Mark a Protect Manager
Page I of 1
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
,DSHAW PRICING REQUEST
FEIMSEMINIONS11
PCO#: 9
SUBMITTED TO: SHAW BUILDERS,LLC. DATE: 03/11/21
CREDITED TO: SHAW BUILDERS,LLC. JOB#: 20268-70
JOB NAME: Burlingame Ranch 3
CHANGE DOCUMENT: Building Material Escalation
PLEASE FURNISH ALL MATERIALS AND LABOR NECESSARY TO COMPLETE THE FOLLOWING WORK AND CHARGE OUR ACCOUNT AS NOTED
BELOW.
WORK TO BE COMPLETED: Perform the work associated with the above change Request
DESCRIPTION QTY UM MIT CO LABOR MATERIAL EQUIP. SUBCONTR.
MATERIALS LS 132,608.98
SUB-TOTAL 0.00 132,608.98 0.00 $0.00
69:8 �—
L�0 ,
THE ABOVE WORK IS TO BE PAID FOR AT ACTUAL COST OF LABOR AND MATERIALS.
CREATED BY: Will Meyer DATE: 03/11/21
NOTES:
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
BILDINGS 8-15 PRICING AT BID PRICING AT CONTRACT TOTAL
MATERIAL ESCALATION
Dimensional SUM: $ 189,195.02 $ 283,397.96 $ 94,202.94
Timbers: $ 106,401.91 $ 139,553.88 $ 33,151.97
Loose Material: $ 82,793.11 $ 143,844.08 $ 61,050.97
Sheathing SUM: $ 68,696.78 $ 108,932.81 $ 40,236.03
Timbers: $ - $ - $ -
Loose Material: $ 68,696.78 $ 108,932.81 $ 40,236.03
EWP SUM: $ 21,842.96 $ 29,592.97 $ 7,750.01
Timbers: $ 21,842.96 $ 29,592.97 $ 7,750.01
Loose Material: $ - $ - $ -
Hardware SUM: $ 32,326.50 $ 37,994.86 $ 5,668.36
Timbers: $ - $ - $ -
Loose Material: $ 32,326.50 $ 37,994.86 $ 5,668.36
WRB SUM: $ 9,789.70 $ 9,789.70 $ -
Timbers: $ - $ - $ _
Loose Material: $ 9,789.70 $ 9,789.70 $ -
Decking SUM: $ 55,077.99 $ 39,829.13 $ (15,248.87)
Timbers: $ - $ - $
Loose Material: $ 55,077.99 $ 39,829.13 $ (15,248.87)
Panelized Board Footage: 45,082 Total Loose(BID PRICE): $ 238,894.38
Loose Dimensional R EiVP Board Footage: 119,338 Total Loose Contract: $ 330,600.89
Loose Sheathing Square Footage: 107,100 Total Loose Escalation: $ 91,706.51
Yard Allocation Cost(OH cY Fabrication): $ -
Total Timbers(BID PRICE): $ 128,244.87
Total Timbers Contract: $ 169,146.85
Total Timbers Escalation: $ 40,901.98
TOTAL BLD ESCALATION: $ 132,608.49
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
M�H
............
!2
771G-1-77-.1-
0
0
c�
c
cn
co
m
0
0
cu
v
ao
0
V
v
D
V
m
0
1100 300 D
CD
C.
80 ISO
A
c0
705 100
r
600 5o
500 D
Market aL
Market -at
400 so
i P i o�it act price
'20 21
Framing Lumber CoMpQslfe Prfca Oandam-Length' Ind'
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
No. 022
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
• No.022 Carport • Date Sent: 3/15/2021
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal:
Carport Material Escalation
Cost Summary for Item 1 Carport Material Escalation
Phase Description Quantity Unit Price Amount
006165- -022 Carport Material Escalation 1 LS 86,274.00 86,274.00
Net Total for Item 1: $86,274.00
Description Percentage Amount
DIC Insurance 0.25% 215.69 Total Item #1: $87,826.93
Warranty Reserve 0.61% 526.27
Cloud Technology Service 0.14% 120.78 Time Extension: NONE
Bonds 0.80% 690.19
Subtotal: $1,552.93
Grand Total PCO #022: $87,826.93
Total Time Extension: NONE
Submitted By: Shaw Builders LLC
✓.<<1 -'
Signature - ,-- Date 4/28/21
Name Mark Hendrickson, Project Manager
Page I of 1
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAW PRICING REQUEST
1FRIMIMAN111M., M4111
PCO#: 10
SUBMITTED TO: SHAW BUILDERS,LLC. DATE: 03/11,/21
CREDITED TO: SHAW BUILDERS,LLC. JOB#: 20268-70
JOB NAME: Burlingame Ranch 3
CHANGE DOCUMENT: Carport Material Escalation
PLEASE FURNISH ALL MATERIALS AND LABOR NECESSARY TO COMPLETE THE FOLLOWING WORK AND CHARGE OUR ACCOUNT AS NOTED BELOW.
WORK TO BE COMPLETED: Perform the work associated with the above change Request
DESCRIPTION QTY UM NIT COc LABOR MATERIAL EQUIP. SUBCONTR.
MATERIALS LS 86,273.88
SUB-TOTAL 0.00 86,273.88 0.00 $0.00
VERH 0.00 1 $0.00
AGO 941J
THE ABOVE WORK IS TO BE PAID FOR AT ACTUAL COST OF LABOR AND MATERIALS.
CREATED BY: Will Meyer DATE: 03/11/21
NOTES:
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
CARPORTS 8-15 PRICING AT BID PRICING AT CONTRACT TOTAL
MATERIAL ESCALATION
Dimensional SUM: $ 153,366.60 $ 197,951.76 $ 44,585.16
Timbers: $ 75,365.88 $ 84,520.00 $ 9,154.12
Loose Material: $ 78,000.72 $ 113,431.76 $ 35,431.04
Sheathing SUM: $ 28,418.48 $ 69,677.82 $ 41,259.34
Timbers: $ - $ - $ -
Loose Material: $ 28,418.48 $ 69,677.82 $ 41,259.34
EWP SUM: $ - $ - $ -
Timbers: $ - $ - $ -
Loose Material: $ - $ - $ -
Hardware SUM: $ 3,504.60 $ 3,746.73 $ 242.13
Timbers: $ - $ - $ -
Loose Material: $ 3,504.60 $ 3,746.73 $ 242.13
WRB SUM: $ 13,556.80 $ 13,744.05 $ 187.25
Timbers: $ - $ - $ -
Loose Material: $ 13,556.80 $ 13,744.05 $ 187.25
Decking SUM: $ - $ - $ -
Timbers: $ - $ - $
Loose Material: $ - $ - $ -
Paneli=ed Board Footage: - Total Loose(BID PRICE): $ 109,923.80
Loose Dimensional R E{VP Board Footage: 125,144 Total Loose Contract: $ 186,856.30
Loose Sheathing Square Footage: 104,288 Total Loose Escalation: $ 77,119.76
Yard Allocation Cost(OH&Fabrication): $ -
Total Timbers(BID PRICE): $ 75,365.88
Total Timbers Contract: $ 84,520.00
Total Timbers Escalation: $ 9,154.12
TOTAL BLD ESCALATION: $ 86,273.88
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
v
0
c�
c
U)
m
m
0
v
m
v
0o
0
v
0
D
V
m
b>
0
m
03
0
1.000 250,
N
V
V
0
W
Boy ________ ---- e__.__ .. __ -___-___ __ ___ __ _ __ __ __._ ISO. n
C7
A
W
7013 100
600 so
500 [per F71 F11 )l l� �. I � i iI J1 ` r L
{11i9/
40 ' Market t. _ -50
Bid Pirice Contract Prico
3t?�1 Q J F M A M J J A S O N D J F M`100
20 21.
Framing Lumber Composite Brice, ($1/mbf) n 'Oandnm Lengths Index
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change a Order
No. 031
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
PCO No.031 Mech, Elec, Conc.from Addendum 002 Date Sent:
Transmitted To: From:
Chris Everson, Senior Project Manager Mark Hendrickson, Project Manager
Aspen, City of Shaw Builders LLC
130 Galena Street Tel:970-248-2619
Aspen, CO 81611 Fax:
Email:markhendrickson@shawconstruction.net
Description of Proposal: This is only Mechanical, Electrical and Concrete changes for Addendum 002.
Concrete Window Well Changes will be priced in 100% CD's.
Cost Summary for Item 1 Mechanical Addendum 002
Phase Description Quantity Unit Price Amount
015100- -031 Mechanical Addendum 002 1 LS 28,600.00 28,600.00
Net Total for Item 1: $28,600.00
Description Percentage Amount
DIC Insurance 0.25% 71.50 Total Item #1: $30,861.69
Warranty Reserve 0.61% 174.46
Cloud Technology Service 0.14% 40.04 Time Extension: NONE
Bonds 0.80% 228.80
Fee 6.00% 1,746.89
Subtotal: $2,261.69
Cost Summary for Item 2 Electrical Addendum 002
Phase Description Quantity Unit Price Amount
016000- -031 Electrical Addendum 002 1 LS 14,524.00 14,524.00
Net Total for Item 2: $14,524.00
Description Percentage Amount
DIG Insurance 0.25% 36.31 Total Item #2: $15,672.56
Warranty Reserve 0.61% 88.60
Cloud Technology Service 0.14% 20.33 Time Extension: NONE
Bonds 0.80% 116.19
Fee 6.00% 887.13
Subtotal: $1,148.56
Page I of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
SHAWPending Change Order
No. 031
Burlingame Ranch Phase 3 Project No: 20268-
Section 2,Township 10 South, Range 85 West
Aspen, CO 81611
Cost Summa for Item 3 Concrete Addendum 002
Phase Description Quantity Unit Price Amount
003310- -031 Concrete Addendum 002 1 LS 118,750.00 118,750.00
Net Total for Item 3: $118,760.00
Description Percentage Amount
DIC Insurance 0.25% 296.88 Total Item #3: $128,140.76
Warranty Reserve 0.61% 724.38
Cloud Technology Service 0.14% 166.25 Time Extension: NONE
Bonds 0.80% 950.00
Fee 6.00% 7,253.25
Subtotal: $9,390.76
Grand Total PCO #031: $174,675.01
Total Time Extension: NONE
Submitted By: Sfhaw Builders LLC
Signature Date 4/28/21
Name Mark Hendrickson, Project Manager
Pap 2 of 2
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
COMFORT R oMr-And Jiunctioh- t"
� HEATING,COOLIN.i . FG::&"SHEET METAL _.. ..........,�,°r
746 Scarlet-Drive Grand Junction,CO 81505
Phone: 970-254-1170 Fax:•970-254-1178
Addendum 002
To: Shaw Construction Date: April 9,2021
Job: Burlinggame Ranch
Attn: Mark Hendrickson
Phone: 970-242-9236
Fax:
Scope of Work: HVAC
Dent 1: Install crawlspace ventilation and radon exhaust fans
Crawlspace Exhaust System- 13 Systems
- Exhaust Fans and exhaust ducting
- Intake ducting and wall cap
- Dehumidification control and outdoor air temperature cutoff switch
Pricing-$3,200.00 per system =$41,600
Credit for GMP base scope($13,000)
Total Crawlspace Exhaust System $28,600.00
R'a:Ma7nomet:er
nting
- haust Fan
a ative side of fan
- y OPristem
Toon Exhaust Fans- $6,7 0.
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
EMAIL:LASS/TERELECTRIC(cDGMAIL.COM
RFC#03
CUSTOMER: February 9,2021
SHAW CONSTRUCTION
760 HORIZON DRIVE
GRAND JUNCTION,CO 81506
MARK HENDRICKSON
markhendrickson@shawconstruction.net
SCENARIO:
ADDENDUM#2 WAS ISSUED WITH ELECTRICAL REVISIONS I ADDITIONS
REASON:
PER ADDENDUM#2 ADDITIONAL LIGHTING CIRCUITRY REQUIREMENTS
SOLUTION:
L.E.I.TO PRICE ALL TIME AND MATERIAL FOR ADDED SCOPE
WE HEREBY PROPOSE TO PROVIDE LABOR AND MATERIALS FOR THE FOLLOWING
INSTALLATION LOCATED AT:
BURLINGAME PHASE 3
PER PLANS AND SPECIFICATIONS FROM:
359 DESIGN ADDENDUM#2 PLAN SET DATED:12/16/20
C2.01
CIVIL
HOURS PER fBSMR MISC
QTY Item EACH ITEM LABOR MATERIAL
1 SITE NOTE 5 DISCONNECT/RECONNECT POLE LIGHT IN ITS NEW LOCATION; 12 $1,020.00 $210.00
ACTUAL RELOCATION BY OTHER
C5.01
STREET LIGHT HOURS PER LABOR Q MISC
QTY Item EACH ITEM f85MR MATERIAL
5 STREET LIGHT;HOOK UP ONLY FIXTURE BY OTHER @ 1 00'AVG. 12 $5,1DD.00 $1.050.00
BOLLARD FIXTURES HOURSPER LABOR@ MISC
OTY Item EACH ITEM f85M14 MATERIAL
-7 BOLLARD LIGHTS @ 100-AVG 10 -$5,950.00 -$2,023.00
RFC:#03
EXCLUSIONS:
STREET LIGHT FIXTURE AND BASE
Page 1 of 3
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
LABOR $170.00
PROJECT MANAGEMENT $300.00
MATERIAL;MISCELLANEOUS $763.00
MATERIAL;LIGHTING PACKAGE DELTA -$17,655.00
TAX ON MATERIALS-EXEMPT $0.00
TOTAL LABOR&MATERIALS -$17,948.00
ALLOWED 10%FOR PROFIT/OVERHEAD(MATERIAL ONLY) -$1,841.80
GRAND TOTAL LABOR&MATERIALS -$19,789.80
BOND FEE 1%OF TOTAL -$197.90
TOTAL LABOR,MATERIALS,BOND: -$19,987.70
Page 2 of 3
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
FIXTURES:FIXTURES SUPPLIED BY OWNER AND INSTALLED BY ELECTRICIAN MUST BE UL APPROVED.IF
NOT UL APPROVED,THERE MAYBE ADDITIONAL CHARGES TO HAVE MADE SO. FIXTURES MUST BE MADE
AVAILABLE TO HANG PRIOR TO FINAL INSPECTION OR THERE MAY BE ADDITIONAL CHARGES.
INSTALLATION OF OWNER-SUPPLIED FIXTURES AFTER FINAL INSPECTION WILL BE BILLED AS A
CHANGE AT CHANGE ORDER RATES.
BOXES:ELEVATIONS AND LOCATIONS FOR ALL BOXES ARE REQUIRED PRIOR TO START OF JOB. IF THESE ARE
UNAVAILABLE AT START,THERE MAY BE AN EXTRA FEE APPLIED TO INSTALL BOXES OR DEMO AFTER ROUGH IN.
PAYMENTS:PAYMENT IS DUE WITHIN 30 DAYS OF INVOICE DATE. OVERDUE PAYMENTS ARE SUBJECT TO 1.5%
MONTHLY INTEREST. CUSTOMER EXPRESSLY AGREES TO PAY CONTRACTOR'S REASONABLE ATTORNEYS'FEES
FOR COLLECTION.
LABOR:PRICE IS BASED ON WORK BEING PERFORMED DURING NORMAL LASSITER ELECTRIC,INC.
HOURS OF OPERATION AND DOES NOT INCLUDE ACCELERATION OF A FIXED SCHEDULE OR OVERTIME.
ANY ACCELERATED SCHEDULE WILL BE DISCUSSED WITH G.C.PRIOR TO START OF NEW SCHEDULE.
TAXES:ANY CHANGE IN TAX RATES DURING THE DURATION OF THE PROJECT WILL RESULT IN USAGE OF THE
CURRENT TAX RATE(FOR BILLING PURPOSES)AS OPPOSED TO THE TAX RATE ON THIS PROPOSAL.
SHAW CONSTRUCTION HAS REVIEWED THE ABOVE REQUEST FOR CHANGE TO BE PERFORMED AT:
BURLINGAME PHASE 3 ADDENDUM#2
WE AGREE TO ACCEPT THIS REQUEST FOR CHANGE AND ABIDE BY THE TERMS STATED THEREIN.
•
Page 3 of 3
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
EMAIL:LASSITERELECTRIC@GMAIL.COM
RFC#02
CUSTOMER: February 9,2021
SHAW CONSTRUCTION
760 HORIZON DRIVE
GRAND JUNCTION,CO 81506
MARK HENDRICKSON
markhendrickson@shawconstruction.net
SCENARIO:
ADDENDUM#2 WAS ISSUED WITH ELECTRICAL REVISIONS/ADDITIONS
REASON:
PER ADDENDUM#2,CONDUCTOR FEEDERS TO TRANSFORMER SIZE
CHANGE/MATERIAL MARKET PRICE INCREASE FROM 12n120 TO 1/26/21
SOLUTION:
L.E.I.TO PRICE ALL TIME AND MATERIAL FOR ADDED SCOPE
WE HEREBY PROPOSE TO PROVIDE LABOR AND MATERIALS FOR THE FOLLOWING
INSTALLATION LOCATED AT:
BURLINGAME PHASE 3
PER PLANS AND SPECIFICATIONS FROM:
359 DESIGN ADDENDUM#2 PLAN SET DATED:12/16/20
•
Page 1 of 4
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
E1-01-08
ELECTRICAL POWER PLAN BUILDING 8 HOURS PER $851HR MISC
QTY Item EACH ITEM LABOR MATERIAL
FEEDER CHANGE PER ADDENDUM#2 AND CITY OF ASPEN FEEDER
1 REQUIREMENTS.THIS PRICE REPRESENTS COST DELTA ON INFLATION AND 0 $0.00 $4.300.00
UPDATED FEEDER REQUIREMENTS FOR ALL RUNS TO BUILDING#8A&8B
E1-01-09
ELECTRICAL POWER PLAN BUILDING 9 HOURS PER $85/HR MISC
QTY Item EACH ITEM LABOR MATERIAL
FEEDER CHANGE PER ADDENDUM#2 AND CITY OF ASPEN FEEDER
1 REQUIREMENTS.THIS PRICE REPRESENTS COST DELTA ON INFLATION AND 0 $0.00 $4,300.00
UPDATED FEEDER REQUIREMENTS FOR ALL RUNS TO BUILDING#9A&9B
E1-01-10
ELECTRICAL POWER PLAN BUILDING 10 HOURS PER $85/HR MISC
QTY Item EACH ITEM LABOR MATERIAL
1 THIS PRICE REPRESENTS COST DELTA ON INFLATION FOR ALL RUNS TO BUILDING 0 $0.00 $2.400.00
#10
E1-01-11
ELECTRICAL POWER PLAN BUILDING 11 HOURS PER $851HR MISC
QTY Item EACH ITEM LABOR MATERIAL
1 THIS PRICE REPRESENTS COST DELTA ON INFLATION FOR ALL RUNS TO BUILDING 0 $0.00 $2,400.00
E1-01-12
ELECTRICAL POWER PLAN BUILDING 12A
HOURS PER SESMR MISC
QTY Item EACH ITEM LABOR MATERIAL
1 THIS PRICE REPRESENTS COST DELTA ON INFLATION FOR ALL RUNS TO BUILDING 0 $0.00 $2.230.00
#12A
E1-01-12
ELECTRICAL POWER PLAN BUILDING 12B HOURSPER $85/HR MISC
QTY Item EACHITEM LABOR MATERIAL
1 THIS PRICE REPRESENTS COST DELTA ON INFLATION FOR ALL RUNS TO BUILDING 0 $0.00 $2,835.00
#12B
Page 2 of 4
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B
E1-01-13 i
ELECTRICAL POWER PLAN BUILDING 13 HOURS PER $$5IHR MIX is
QTY Item EACHITEM LABOR MATERIAL
FEEDER CHANGE PER ADDENDUM#2 AND CITY OF ASPEN FEEDER
1 REQUIREMENTS.THIS PRICE REPRESENTS COST DELTA ON INFLATION AND 0 $0.00 $5,120.00
UPDATED FEEDER REQUIREMENTS FOR ALL RUNS TO BUILDING#13A&13B
E1-01-14
ELECTRICAL POWER PLAN BUILDING 14 HOURSPER $85IIi11 Mlsc
QTY Item EACH ITEM LABOR MATERIAL
1 THIS PRICE REPRESENTS COST DELTA ON INFLATION FOR ALL RUNS TO 0 $0.00 $3,920.00
BUILDINGS#14A&14B
E1-01-15
ELECTRICAL POWER PLAN BUILDING 15 HOURSPER $851HR Mlsc
QTY Item EACH ITEM LABOR MATERIAL
1 THIS PRICE REPRESENTS COST DELTA ON INFLATION FOR ALL RUNS TO 0 $0.00 $3,240.00
BUILDINGS#15
RFC:#02
LABOR $0.00
PROJECT MANAGEMENT $350.00
MATERIAL;MISCELLANEOUS $30,745.00
TAX ON MATERIALS-EXEMPT $0.00
TOTAL LABOR&MATERIALS $31,095.00
ALLOWED 10%FOR PROFIT/OVERHEAD(MATERIAL ONLY) $3,074.50
GRAND TOTAL LABOR&MATERIALS $34 169.50
BOND FEE 1%OF TOTAL $341.70
TOTAL LABOR,MATERIALS,BOND: $34,511.20
Page 3 of 4
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
FIXTURES:FIXTURES SUPPLIED BY OWNER AND INSTALLED BY ELECTRICIAN MUST BE UL APPROVED.IF
NOT UL APPROVED,THERE MAY BE ADDITIONAL CHARGES TO HAVE MADE SO. FIXTURES MUST BE MADE
AVAILABLE TO HANG PRIOR TO FINAL INSPECTION OR THERE MAY BE ADDITIONAL CHARGES.
INSTALLATION OF OWNER-SUPPLIED FIXTURES AFTER FINAL INSPECTION WILL BE BILLED AS A
CHANGE AT CHANGE ORDER RATES.
BOXES:ELEVATIONS AND LOCATIONS FOR ALL BOXES ARE REQUIRED PRIOR TO START OF JOB. IF THESE ARE
UNAVAILABLE AT START,THERE MAY BE AN EXTRA FEE APPLIED TO INSTALL BOXES OR DEMO AFTER ROUGH IN.
PAYMENTS:PAYMENT IS DUE WITHIN 30 DAYS OF INVOICE DATE. OVERDUE PAYMENTS ARE SUBJECT TO 1.5%
MONTHLY INTEREST. CUSTOMER EXPRESSLY AGREES TO PAY CONTRACTOR'S REASONABLE ATTORNEYS'FEES
FOR COLLECTION.
LABOR:PRICE IS BASED ON WORK BEING PERFORMED DURING NORMAL LASSITER ELECTRIC,INC.
HOURS OF OPERATION AND DOES NOT INCLUDE ACCELERATION OF A FIXED SCHEDULE OR OVERTIME.
ANY ACCELERATED SCHEDULE WILL BE DISCUSSED WITH G.C.PRIOR TO START OF NEW SCHEDULE.
TAXES:ANY CHANGE IN TAX RATES DURING THE DURATION OF THE PROJECT WILL RESULT IN USAGE OF THE
CURRENT TAX RATE(FOR BILLING PURPOSES)AS OPPOSED TO THE TAX RATE ON THIS PROPOSAL.
SHAW CONSTRUCTION HAS REVIEWED THE ABOVE REQUEST FOR CHANGE TO BE PERFORMED AT:
BURLINGAME PHASE 3 ADDENDUM#2
WE AGREE TO ACCEPT THIS REQUEST FOR CHANGE AND ABIDE BY THE TERMS STATED THEREIN.
•
Page 4 of 4
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-227710691FC4B _u i
V (PAGE I OF 3)
44e (REVISED)
CitETti4)
March 11,2021
ATTN TO: SHAW CONSTRUCTION
FROM: RUBEN VARGAS
(970)-379-6649 CELL
"CHANGE ORDER CO#2"
RE: BURLINGAME PHASE 3
DATE OF PRITS (12/17/2020)
"FOUNDATION 8 "
1.-
^Z'- ADD EXTTRA WALLS LS 7N WfNDPV 3,02 V- ,
3.-ADD MORE CONCRETE ON WALLS (2"THICKER ON LEDGE WALL ONLY)
FROM 16"& 18"THICK WALL AS PER CONTRACT TO 18"&20" THICK •
(BASE ON 13 YDS EXTRAS) $ 7,150.00
4.-REQUEST TO DO SINGLE SIDE WALL ONLY AT TOLL WALLS
-BASE ON 880 SF $ 13,200.00
" FOUNDATION 9"
-1. ADD EXTRA FOOTING0,
f
,2. ADD EXTRA WALLS T T S ON WIND 0-
f
3.-ADD MORE CONCRETE ON WALLS (2" THICKER ON LEDGE WALL ONLY)
FROM 16"& 18"THICK WALL AS PER CONTRACT TO 18"&20" THICK
(BASE ON 13 YDS EXTRAS) $ 7,150.00
4.-REQUEST TO DO SINGLE SIDE WALL ONLY AT TOLL WALLS
-BASE ON 880 SF $ 13,200.00
" FOUNDATION 10"
1.- ONE YARD EXTRA FOR ADDING FOOTING PADS $ 550.00
2.-ADD MORE CONCRETE ON WALLS (2ff THICKER ON LEDGE WALLS ONLY)
FROM 16"THICK WALL AS PER CONTRACT TO 18" THICK WALL
(BASE ON 8 YDS EXTRAS) $ 4,400.00
_ J ,'
DocuSign Envelope ID:BD71 DA7E-60E8-4AB0-A2A2-22771069FC4B ! t
V (PAGE 2 OF 3)
(REVISED)
C VE�
March 11,2021
ATTN TO: SHAW CONSTRUCTION
FROM: RUBEN VARGAS
(970)-379-6649 CELL
"CHANGE ORDER C0112"
RE: BURLINGAME PHASE 3
DATE OF PRITS (12/17/2020)
" FOUNDATION l l"
I.- ONE YARD EXTRA FOR ADDING FOOTING PADS $ 550.00
2.-ADD MORE CONCRETE ON WALLS (THICKER WALLS)
FROM 16" THICK WALL AS PER CONTRACT TO 18" THICK WALL
(BASE ON 8 YDS EXTRAS) $ 49400.00
• " FOUNDATION 12"
1. ADD-EX RA FOOTING . 0-
z.-AB 0-
3.-ADD MORE CONCRETE ON WALLS (2"THICKER ON LEDGE WALLS ONLY)
FROM 16"THICK WALL AS PER CONTRACT TO 18" &20" THICK
(BASE ON 18 YDS EXTRAS) $ 9,900.00
4.-REQUEST TO DO SINGLE SIDE WALL ONLY AT TOLL WALLS
-BASE ON 950 SF $ 14,250.00
" FOUNDATION 13"
- . ADD EXTRA F699FfN6-@N WfNB 0-
2. ADD L7lTPA WA14;S 9T �f V�I D , V
3.-ADD MORE CONCRETE ON WALLS (2"THICKER ON LEDGE WALL ONLY)
FROM 16"& 18"THICK WALL AS PER CONTRACT TO 18" &20" THICK
(BASE ON 13 YDS EXTRAS) $ 7,150.00
4.-REQUEST TO DO SINGLE SIDE WALL ONLY AT TOLL WALLS
-BASE ON 880 SF $ 13,200.00
DocuSign Envelope ID:BD71DA7E-60E8-4AB0-A2A2-22771069FC4B
n V (PAGE 1 OF 3)
�I 4e (REVISED)
March 11,2021
ATTN TO: SHAW CONSTRUCTION
FROM: RUBEN VARGAS
(970)-379-6649 CELL
"CHANGE ORDER CO#2"
RE: BURLINGAME PHASE 3
DATE OF PRITS (12/17/2020)
" FOUNDATION 14"
-1. ADD EXTRA FOOTING n
, V
D , 6-
3.-ADD MORE CONCRETE ON WALLS (2"THICKER ON LEDGER WALLS ONLY) •
FROM 16" & 18"THICK WALL AS PER CONTRACT TO 18"& 20" THICK
(BASE ON 10 YDS EXTRAS) $ 5,500.00
4.-REQUEST TO DO SINGLE SIDE WALL ONLY AT TOLL WALLS
-BASE ON 880 SF $ 13,200.00
" FOUNDATION 15"
1.-ONE YARD EXTRA FOR ADDING FOOTING PADS $ 550.00
2.-ADD MORE CONCRETE ON WALLS (THICKER WALLS)
FROM 16"THICK WALL AS PER CONTRACT TO 18" THICK WALL
(BASE ON 8 YDS EXTRAS) $ 4,400.00
TOTAL CHANGE ORDER REQUEST FOR THE BUILDINGS ONLY $ 142,125.00
Window Wells to be priced at 100% CD's ($23,375.00)
Total $118,750.00
NOTE
-ADD $ 35.00/YD FROM OCTOBER 15 2021 FOR WINTER CHARGES FROM CONCRETE
SUPPLIERS
RUBEN VARGAS