HomeMy WebLinkAboutFile Documents.624 E Cooper Ave.0010-2020-TSTR (4)1 | Page CONSTRUCTION MANAGEMENT PLAN for MEZZALUNA 624 EAST COOPER STREET ASPEN, COLORADO 81611 2 | Page Table of Contents : 1.0 GENERAL ................................................................................................. 2 2.0 PROJECT INTRODUCTION ........................................................................ 4 2.1 Project Location…….................................................................................. 4 2.2 Project Disturbance Area ........................................................................ 4 2.3 Project Description ................................................................................. 4 3.0 PROJECT DOCUMENTATION ................................................................... 5 3.1 Permitting................................................................................................ 5 3.2 Public Notification ................................................................................... 5 3.3 Project Sign .............................................................................................. 5 3.4 Contact List .............................................................................................. 6 4.0 PROJECT IMPLEMENTATION .................................................................... 7 4.1 Dates of Construction .............................................................................. 7 4.2 Hours of Construction.............................................................................. 7 4.3 Construction Schedule ............................................................................ 7 4.4 Adjoining Properties………........................................................................ 7 4.5 Project Fencing …………............................................................................ 7 4.6 Natural Environment .............................................................................. 7 4.7 Public Health and Welfare....................................................................... 7 3 | Page 5.0 PROJECT MANAGEMENT ………................................................................ 8 5.1 Parking Management............................................................................... 8 5.3 Emergency Access…................................................................................... 8 5.4 Staging Areas ............................................................................................. 8 6.0 TRAFFIC CONTROL ......................................................................................9 6.1 General .......................................................................................................9 6.2 Haul Routes................................................................................................. 9 6.3 Weight and Size Limitations of Vehicles ..................................................... 9 6.4 Delivery Requirements................................................................................ 9 7.0 PEDESTRIAN PROTECTION ………................................................................. 9 8.0 SEDIMENT AND EROSION CONTROL .......................................................... 9 8.1 Requirements.............................................................................................. 9 9.0 FUGITVE DUST CONTROL............................................................................. 9 9.1 Dust Control Plan......................................................................................... 9 10.0 EMISSIONS.................................................................................................. 9 10.1 General....................................................................................................... 9 10.2 Emissions from Diesel Powered Engines ................................................... 9 11.0 NOISE SUPPRESSION................................................................................... 9 11.1 General........................................................................................................ 9 11.2 Noise Suppression Plan................................................................................ 9 4 | Page 1.0 General 1.1 The purpose for this CMP is to let you know our plans for the Temporary Exterior Enclosure. 1.2 Total Square Footage of Area Elcosure = Approx. 640 SqFt 1.3 Total Square Footage of Soil Disturbance = Zero – N/A. 1.4 CMP Submission Certificate – Attached. 2.0 Project Location 2.1 Total Disturbance Area = Zero – N/A 2.2 Project Vicinity Map (Enlarged -Attached.) 2.3 The Project consists of a Temporary Exterior Enclosure. There will be NO effect on Public Utilities. 5 | Page 3.0 Project Documentation 3.1 Permit Types we will be submitting : Building Permit. A project update shall be provided to the public on a basis no less than monthly, via website on-site notices, or other accepted means of notification (per request of the City of Aspen). The first public notification shall occur no later than 10 days prior to construction. ALL properties within 300 Feet by letter. (3.2 - Notice - Attached.) 3.2 Project Sign will be constructed and posted within 30 days of Construction. (Appendix A – Project Sign – Attached.) 6 | Page 3.3 The currently planned Project Contacts and Construction Team is as follows : Owner : Mezzaluna Aspen 624 East Cooper Street Aspen, CO 81611 Architect : N/A Contractor : Rutgers Construction 256 Twining Flats Road, Aspen, CO 81611 Phone : (970) 925-8229 Project Manager : James Guest Phone : (970) 379-1195 email : james@rutgersconstruction.com Site Supervisor : TBD Safety & Traffic Control Officer : TBD EMERGENCY : Dial 911 Police Department : (970) 920-5400 Fire Department : (970) 925-8484 Pitkin County : (970) 920-5526 City of Aspen : (970) 920-5000 RFTA : (970) 925-8484 Holy Cross : (970) 945-5491 Source Gas : (970) 928-0401 Aspen Consolidated Sanitation : (970) 925-3601 7 | Page 4.0 Project Implementation 4.1 Dates of Construction : Currently, the work is scheduled to commence around the 7th December, 2020. It is estimated that the total duration will be 5 working Days, with a desired completion of 11th December 2020. 4.2 Hours of Construction : Construction hours will be limited to 8:30am – 5:30pm, Monday through Friday. Construction activities will not be permitted on Sundays or federally designated holidays. 624 East Cooper Street is inside of the Commercial Core and Central Resort Areas. 4.3 Construction Schedule : Monday 7th December through Friday 11th December 2020. 4.4 No excavation – N/A. 4.5 Project Fencing : N/A 4.6 Covid-19 Site Safety Plan Attached. 4.7 N/A – No Tree Issues. 8 | Page 5.0 Project Management 5.1 NO Right Of Way (ROW) will be needed for this permit. 5.2 Continuous access for emergency vehicles (police, fire, and ambulance) will be maintained on and around the project site. 5.3 We will be requesting approx. 2 parking spaces via Parking Permits. 5.4 Map showing locations of : N/A – Built off site then installed. 5.5 N/A 5.6 Staging and Materials : N/A - Temporary Structure Built Off Site. 5.7 Waste Management / Recycling : N/A - Temporary Structure Built Off Site. We will be removing ALL Trash via Rutgers Vehicles every day. 9 | Page 6.0 Traffic Control 6.1 Safety & Traffic Control Officer : N/A 6.2 Project Haul Routes : N/A 6.3 Construction Vehicles / Delivery Vehicles : N/A 6.4 Traffic Control Plan is not needed for this permit. 7.0 PEDESTRIAN PROTECTION - N/A 8.0 Sediment and Erosion Control – N/A 9.0 Fugitive Dust Control – N/A 10.0 Emissions - N/A 11.0 Noise Suppression – N/A Mezzaluna Aspen 624 East Cooper Street BUILDING PERMIT # TBD JOB SITE PHONE # 970-379-1195 EMERGENCY PHONE # 970-379-1195 970-379-5810 RUTGERS CONSTRUCTION, INC.RUTGERS CONSTRUCTION, INC. S ORIGINAL STN 3RD STLACET LN E COOPER A V ELONE P INE RDMATCHLESS DRSPRUCE STN 4TH STU T E A V E BRENDENCTW HOPKIN S A V E E HOPKINS AVEN GALENA STREGENT STN 2ND STVINESTDEAN ST RIOGRA N D E P L S 1ST STN GARMISCH STSOUTHAVE ALLEY OA K L N L A C E T C TCLEVELAND STN MONARCH STS HUNTER STS 3RD STN 1ST STS GALENA STS MONARCH STS WESTEND STS ASPEN STS 2ND STS MILL STS SPRING STS GARMISCH STALLEY N MILL STPARK AVES 4TH STW BLEEKE R S T N S P R I N G S T BAYST W MAIN ST ALLEY E SNARK S T JUSTICEEXWYDALEAVE E FRANCIS S T E HYMAN A V E NEALE AVEALLEY E BLEEKER S T TRA I N O R S LND G ALLEY S SPRING STOBERMEYERPLACE DR GIBSON AVERECYCLECIR DEAN ST N RIVERSIDEAVEALLEY LIBRARYALLEY ALLEY SUMMIT S T VINE STW FRANCIS S T W HYMAN A V E E DURANT A V E E MAIN ST ALLEY PARK CIRALLEY E COOPER A V E ALLEY ALLEY W HALLAM S T ALLEY ALLEY E BLEEKE R S T E HOPKINS A V E ALLEYGILBERT S T ALLEY DEAN ST E HALLAM S T COWENHOVENCTW COOP E R A V E MINERSTRAIL RD JUAN ST QUEE N S T MIDLANDAVEART PKYPARK C I R ASPEN MTN R D WA LNU T S T KING S T AJA X A V E ASPEN MTNCUTOFF RDRACE STC O T T O N W O O D L N LITTLECLOUD TRL PU P P Y S M I T H S T S RIVERSIDE AVEMA P L E L N WATERS A V E Central Resort Area and Commercial Core Area Map Central Resort Area Commercial Core Area Certificate of Completion THIS ACKNOWLEDGES THAT James Guest / Rutgers Construction HAS SUCCESSFULLY COMPLETED THE CITY OF ASPEN CONSTRUCTION MANAGEMENT COURSE 2018-11-09 CITY OF ASPEN, ENGINEERING DEPARTMENT DATE