To: City of Aspen Engineering Dept
From: John F Blatz, President, Clearwater Construction Management, Inc.
Construction Management Plan
Project Address – 800 Mill Street, Unit #10 – Fifth Avenue Condominiums
Project overview – as this is an interior remodel on a condominium building, several items from the
standard CMP are not applicable. Per the attached plans, the entire interior of the unit is going to have
finishes removed and replaced.
This submittal follows the CMP Checklist
1.0 General – not applicable as all work is interior
2.0 Project Introduction – not applicable as there is no disturbance beyond the interior work. Vicinity
map attached Exhibit “A”
3.0 Project Documentation – see attached plan submittals, complete with existing and proposed
conditions, HOA approvals, and required documents.
3.1 Permit Numbers TBD upon issuance
3.2 Project Notification – neighboring units will be notified by the HOA, and CCM shall
contact direct neighbors as work is ongoing
3.3 Project Sign – see attached Exhibit “B”
3.4 Contact List – see Building Permit Application for all contacts
4.0 Project Implementation –
4.1 Dates of Construction – 5 Months, start date depends on Permit
4.2 Hours of Construction - Construction hours will be limited to 7:30am – 5:30pm Monday
through Friday and 9:00am- 5:00pm on Saturday. All activities generating noise in excess
of 80 decibels will require a noise suppression plan and be restricted to operating
between 9:00am – 5:00pm Monday through Friday. Additional prohibited construction
days are as follows:
• Sundays
• Food and Wine Weekend (Friday-Sunday)
• 4th of July (Day and any associated weekend)
• Memorial Day Weekend
• Labor Day Weekend
• Thanksgiving Day
• Christmas Week (12/25 – 1/1)
4/16/2018
4.3 Construction Schedule – See attached Schedule Exhibit “C”
5 Months, start date depends on Permit
4.5-4.7 – Not applicable as related to Parks, Trees, and Fencing
5.0 Site Management
5.4 Map – HOA shall designate areas available for staging, parking, and toilet. Our plan is to remove
finishes into a trailer and haul off immediately, and all materials delivered to be stored in the unit
for security.
6.0 Traffic Control – not applicable as no large trucks are required for this project. Deliveries shall be in
small trucks or pickup trucks
8.0 Sediment and Erosion Control – not applicable for this work
9.0 Fugitive Dust Control – Dust shall be contained to the unit and we will use vacuums or containment
to control dust. We also use sweeping compound on the floor to help control dust. Our 3rd party
safety inspector provides plans and equipment guidance for this
10.0 Emissions – not applicable for this work
11.0 Noise Suppression – General
The noise limit for construction is 80 decibels measured at the property line of the
construction site. All construction equipment shall be adequately muffled and
maintained to minimize project noise. The installation of noise barriers is the
minimum technique to suppress noise, especially when jack hammering of
concrete occurs.
11.1 - Noise Suppression Plan
All activity that generates noise in excess of 80 decibels requires a noise
suppression plan and is restricted to operating between the hours of 9am and
5pm Monday through Friday. Neighboring occupants will be notified of noise
prior to work being done as a courtesy. Contractor shall use blankets as
necessary to contain noise and unit door shall be closed when not in use
Please feel free to contact me with any addenda to this plan. My cell is 970.379.3709
and my email is jblatz@ccmaspen.com.
Best regards,
John F Blatz, President
4/16/2018
4/16/2018
800 S Mill StPage 1of 2800 S Mill St - Google MapsVicinity MapEXHIBIT A4/16/2018
VOGEL REMODEL
800 Mill Street
Unit # 10
Permit # ZZZZ.2018.XXXX
24 Hour Emergency Contact:970.379.3709
ALL VISITORS MUST CHECK IN AT THE
CONSTRUCTION OFFICE TRAILER
Project Sign
EXHIBIT B