HomeMy WebLinkAboutFile Documents.210 N Mill St.0016-2019-BROF (6)Construction Narrative for 210 N Mill Street, Aspen, Co.
Contractor: American Heritage Restoration
We will be removing two roofing systems
The first one will be EPDM
The second one will be Built Up with pea gravel
We will be removing and replacing the cap Metal on the walls
installing 60 Mill GAF fully adhered TPO.
installing GAF ISO Insulation, mechanically attached to a plywood deck
installing ¼” Primed densdeck
installing new taper and crickets to maximize roof drainage
removing and resetting all HVAC units and penetrations
The materials will be delivered by ABC Supply on November 1st. They will be
loading from the parking lot. They will not affect the main street or sidewalks
The dumpster and porta potty will be delivered Friday November 1st too.
The scaffold, stairs and trash chute will be erected on Saturday November 2nd.
Weather permitting, the work on the roof will start November 4th, weather
permitting.
The work area will be cordoned off with traffic posts and safety tape.
When work is finished, the dumpster and porta potty will be removed first, with 5
days, weather permitting.
The scaffold and trash chute will be removed ASAP after completion and inspection
of the roof.