Construction Management Plan
215 S. Monarch
Aspen, CO 81611
Prepared by:
Chris Laven
William H. Baker Construction
December 6, 2019
Contact Designations:
Contractor William H. Baker Construction
210 A.A.B.C. Suite MM
Aspen, CO 81611
Project Manager- Chris Laven
chris@whbconstruction.com
970-319-8070
Architect Forum Phi,
715 W. Main St. #204
Aspen, CO 81611
970-279-4157
Property Manager N/A
Owner Kawa Office
Daniel Ades
EMERGENCY 911
Aspen Fire Department 420 E. Hopkins Ave
Aspen, CO 81611
970-925-5532
Aspen Police Department 506 E. Main Street
Suite 102
Aspen, CO 81611
970-920-5320
Aspen Valley Hospital 0401 Castle Creek Road
Aspen, CO 81611
970-925-1120
Roaring Fork Transit 0051 Service Center Drive
Aspen, CO 81611
970-925-8484
Aspen School District 235 County Road 13A
Aspen, CO 81611
970-925-3760
Holy Cross 3799 HWY 82
Glenwood Springs, CO 81601
970-945-5491
City Of Aspen Water Dept. 500 Doolittle Drive
Aspen, CO 81611
970-920-5110
Source Gas 1-800-563-0012
Project Location: 215 S. Monarch St.
2.1 – Disturbance Area
This project consists of a remodel of an existing interior unit at 215 S.
Monarch St. The remodel is entirely at the interior therefor there will be no exterior
disturbance area. The project includes the removal of interior non-structural walls and
update to AV/IT systems for it’s intended use as an office space. Some new interior non-
structural walls will be installed.
Total Square footage of soil disturbance= 0 square feet.
2.2 – Location – See map below.
2.3 – Description
The project includes the removal of interior non-structural walls and update to
AV/IT systems for its intended use as an office space. Some new interior non-structural
walls will be installed.
3.0 Project Documentation
3.1 – There are no existing open permits for this residence. William H. Baker has a
current and valid contractor’s license in Aspen, Colorado. The license number is C-006139.
3.2 – WHB will provide notification to building occupants of pending construction
3.3 – A project sign is shown next below
3.4 – See phone list at the front of this document.
4.0 – Project Implementation
4.1 – Dates of Construction
Estimated project start date is February 1, 2020 and estimated finish date it
May 1, 2020.
During the Christmas week (12/26-12/31) Projects located in the Central Resort Area
(CRA) are not permitted to work on any exterior elements, however interior work may be
permitted with prior approval.
4.2 – Construction will occur during the normal work week – 7:30am -5:30pm. No
activity creating noise greater than 80 decibels is anticipated at the property line as all
work will be conducted at the interior of the building.
4.3 – This project is anticipated to take about 3 months.
4.4 – Adjoining Properties
WHB will notify immediate neighbors prior to construction.
4.5 – Project Fencing
No fencing will be required as the work occurs at the interior of the building
4.6 – No trees will be impacted by the construction work
4.7 – The exterior environment will not be affected.
5.0 ‐ Parking Management
5.1 – Parking Management. WHB will utilize the owners 5 parking spaces that are a
part of his lease along with on street parking as necessary
5.2 – Emergency Vehicle access and Ordinance 35
William H. Baker Construction and sub-contractors under the direction of
WHB Construction will maintain continuous emergency vehicle access, on and around the
site, including police, fire and ambulance services.
5.3 – Construction Parking Details – Construction parking details are understood.
5.4 – Staging Areas
WHB will utilize the interior of the building to store/stage materials and
tools along with 2 of the parking spaces that are covered by the building
5.5 – There will be no construction trailer. A portable restroom may be utilized for
the project, if so it will be placed in a the driveway.
6.0 – Traffic control
6.1 – Traffic will not be impacted unless permitted by the COA Engineering
department.
6.2 – Haul Routes
Deliveries will be routed per the haul route map below
6.3 – On-site vehicle limitations
No vehicles greater than 36’ and five tons in capacity will be employed
during the construction process.
6.4 - No roads will be closed due to our construction project. Delivery vehicles will
not idle for longer than five minutes.
7.0 – Pedestrian Protection
7.1 – General
All construction work to be completed within the property boundaries – no
danger to the public would be expected. No parking or storage of materials will interfere
with the sidewalks at two sides of the building.
8.0 – Sediment and erosion control
8.1 – Requirements
There is no excavation for this project and will therefore require no erosion
control. See permit documentation.
8.2 – This work does not occur on Smuggler Mountain.
9.0 – Fugitive Dust Control
9.1 – This project will not require any fugitive dust control.
9.2 – N/A
10.0 – Emissions
10.1 – General
All vehicles and equipment used on site will be properly maintained within
the manufacturer’s standards.
10.2 – Diesel powered engines will only be used for deliveries.
11.0 – Noise suppression
11.1 – General
No construction work resulting in noise over 80 decibels will occur at the
property line.
11.2 – No noise greater than 80 decibels will be generated at the property line.
11.3 – N/A - No noise greater than 80 decibels will be generated at the property line.
11.4 – See attached City of Aspen, Construction Noise Suppression Plan