HomeMy WebLinkAboutFile Documents.905 Chatfield Rd.0111.2018 (49).ARBKBuildingComment3
Subject: PlanCheck
Page Label: 1
Author: justinh
File Name: _Building Department Response.Architecture.905
ChatfieldRd.2018.04.pdf
Color:
Comment still outstanding,
building cannot fully approve this
permit until state demo license is
submitted.
_Building Department Response.Architecture.905 ChatfieldRd.2018.04.pdf (2)
Subject: PlanCheck
Page Label: 3
Author: justinh
File Name: _Building Department Response.Architecture.905
ChatfieldRd.2018.04.pdf
Color:
There was no sheet A-576 in the
submittal, please submit that
sheet.
Subject: PlanCheck
Page Label: 1
Author: justinh
File Name: American Hydrotech Hydroguard UL Class A. 905
ChatfieldRd.2018.04.pdf
Color:
The assembly you highlighted
uses a non-combustible deck,
which does not match your R1
assembly. Option 3 on this
listing works with a combustible
deck but does not match what
you have highlighted here or
drawn, the insulation and
surfacing materials are different.
Please submit different
documentation or revise your R1
detail to match option 3 on this
sheet.
American Hydrotech Hydroguard UL Class A. 905 ChatfieldRd.2018.04.pdf (1)
Subject: PlanCheck
Page Label: 1
Author: justinh
File Name: Aspen Line Grade Verification Form.905 Chatfield
Rd.2018.04.pdf
Color:
I do not see where this
benchmark is shown on the
survey, the SW corner of the lot
is marked as "#5 rebar yellow
plastic cap illegible" with no
elevation called out. Please
clarify or provide a different
elevation benchmark.
Aspen Line Grade Verification Form.905 Chatfield Rd.2018.04.pdf (1)
0111-2018-ARBK_BuildingComment1
Subject: PlanCheckPage Label: 1Author: justinh
File Name: Aspen Line Grade Verification Form.905 Chatfield
Road.2018.04.pdf
On what sheet is this shown? Ido not see where you haveclearly tied the building to theproperty line.
Aspen Line Grade Verification Form.905 Chatfield Road.2018.04.pdf (2)
Subject: PlanCheck
Page Label: 1Author: justinhFile Name: Aspen Line Grade Verification Form.905 Chatfield Road.2018.04.pdf
This is not what is called out inthe site plan general notes or
civil plan, verify that all plan setsconsistently call out the sameequation and revise this form asneeded. I believe what you areshowing is FF of the existinghouse.
Subject: PlanCheckPage Label: 1 - COVER - COVER SHEETAuthor: justinhFile Name: PlanSet.Architecture.905ChatfieldRd.2018.04.pdf
Submit a copy of your statelicense to demolish. You mayresubmit other responseswithout this document, butbuilding will not be able to fullyapprove your permit until this
has been submitted.
PlanSet.Architecture.905ChatfieldRd.2018.04.pdf (20)
Subject: PlanCheck
Page Label: A-100.1 - SITE PLAN -EXISTING & PROPOSED GRADEAuthor: justinhFile Name: PlanSet.Architecture.905ChatfieldRd.2018.04.pdf
Show utility meters on theelevations.
Subject: PlanCheckPage Label: A-101 - SNOWMELT PLANAuthor: justinhFile Name: PlanSet.Architecture.905ChatfieldRd.2018.04.pdf
Civil plans referencessnowmelted pavers, are theseintended to be pervious pavers? If so, provide a detail showing acompliant perforation patternthat maintains the R10 insulationvalue. Please see the attachedsnowmelt perforation calculatorfor assistance in designing a
compliant hole pattern.
On what sheet is thisshown? I do not seewhere you haveclearly tied thebuilding to theproperty line.
This is not what iscalled out in the siteplan general notes orcivil plan, verify that allplan sets consistentlycall out the sameequation and revisethis form as needed. I believe what you areshowing is FF of theexisting house.
Submit a copy of your state license to demolish. You mayresubmit other responses without this document, but building willnot be able to fully approve your permit until this has beensubmitted.SIDE YARDPROPERTY LINE
SETBACK
RE: LANDSCAPE
10'-0"
UTILITY METER LOCATIONS, RE: CIVIL
Show utility meters onthe elevations.
LIVING TERRACE
DN
DN
EXISTI TUB & TO BE
REAR YARD
PROPE
R
T
Y
L
I
N
E
10'-0"Civil plans referencessnowmelted pavers,are these intended tobe pervious pavers? Ifso, provide a detailshowing a compliantperforation pattern thatmaintains the R10insulation value. Please see theattached snowmeltperforation calculatorfor assistance indesigning a complianthole pattern.
Comment still
outstanding, building
cannot fully approvethis permit until statedemo license issubmitted.
Author: justinhFile Name: PlanSet.Architecture.905ChatfieldRd.2018.04.pdf this should be a mass wall whichdoes not appear on the report.
Please revise the ResCheckaccordingly or clarify where yourthermal envelope is in this
location.
Subject: PlanCheckPage Label: A-320 - WALL SECTIONS
Author: justinhFile Name: PlanSet.Architecture.905ChatfieldRd.2018.04.pdf
Clearly indicate how you willaccomplish the air sealing
requirements of 2015 IECC tableR402.4.1.1. Indicate thecontinuity of the air barrier and
where it is located throughoutthe building. Note locations that
require caulking, sealing, taping,etc at transitions betweendifferent materials (such as wall
to foundation, wall to roof, etc). The better detail provided the
easier it will be for the contractorand inspector to be successful. These details are a new 2015
code requirement now thatvisual inspection of the airbarrier is required in lieu of a
blower door test. See theattached examples of air sealing
details. You may use anymethod or combination ofmethods to accomplish this
requirement but the continuousair barrier must be clearly
identified. See the attachedexample sections and details foran example of the level of detail
we are looking for.
F4
W10 10'-6 5/8"12'-0"ResCheck properly,this should be a masswall which does notappear on the report. Please revise theResCheck accordinglyor clarify where yourthermal envelope is inthis location.
R2
5
Clearly indicate how you will accomplish the air sealingrequirements of 2015 IECC table R402.4.1.1. Indicate thecontinuity of the air barrier and where it is located throughoutthe building. Note locations that require caulking, sealing,taping, etc at transitions between different materials (such aswall to foundation, wall to roof, etc). The better detailprovided the easier it will be for the contractor and inspectorto be successful. These details are a new 2015 coderequirement now that visual inspection of the air barrier isrequired in lieu of a blower door test. See the attachedexamples of air sealing details. You may use any method orcombination of methods to accomplish this requirement butthe continuous air barrier must be clearly identified. See theattached example sections and details for an example of thelevel of detail we are looking for.
There was no sheet
A-576 in the submittal,
please submit thatsheet.
The assembly you highlighted uses a
non-combustible deck, which does not match
your R1 assembly. Option 3 on this listing works
with a combustible deck but does not match what
you have highlighted here or drawn, theinsulation and surfacing materials are different. Please submit different documentation or revise
your R1 detail to match option 3 on this sheet.
ASPEN LINE GRADE VERIFICATION FORMASPEN LINE GRADE VERIFICATION FORM Verification of Building Location by Building Contractor For Building and Permit Information, please refer to our website at: http://www.aspenpitkin.com/depts/41/
Exemption A City verification of building location is not needed when the project creates less the 200 square feet of new floor area. PART A: Complete and Submit as part of the Building Permit Application o Building / Job Address or Location: _____________________________________________ o Your Name (Person Completing Part A): ____________________________________________ o Your Company: ________________________________________________________________ o Plans must show horizontal dimensions that ‘tie’ the building to the property boundary. Are building ties shown? (circle one) ‘Yes’ ‘No’ o An elevation benchmark needs to be established on the site by a licensed surveyor and shown on the plans. What is the elevation of this benchmark? _________________________________ o If the garage is located within 10 feet of the roadway or sidewalk, provide spot elevation on the on the roadway or sidewalk. Is a spot elevation shown? ‘Yes’ ‘No’ ‘N/A’ o Provide the equation comparing site (surveyed) elevation to structure/ architectural plan elevation: (i.e., 100’ first floor elev = 7962.50’) _______________________________ ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------- PART B: Complete prior to first Foundation Inspection, by a licensed surveyor or an individual prequalified by the City
o Do field measured building ties to property match building ties shown on the plan? (circle one): ‘Yes’ ‘No’ o Surveyor needs to confirm that one spot on the top of the foundation wall is at the same elevation shown on the approved building plans.
I do not see where thisbenchmark is shown
on the survey, the SW
corner of the lot is
marked as "#5 rebar
yellow plastic cap
illegible" with no
elevation called out.
Please clarify or
provide a different
elevation benchmark.
Subject: PlanCheck
Page Label: A-109 LOWER LEVEL CRAWL SPACE
Author: justinh
File Name: PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf
Color:
Please change your code
reference to be IMC 306.4 as
well as the reference on A-120,
we have not adopted that portion
of the IRC.
PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf (6)
Subject: PlanCheck
Page Label: A-123 ENLARGED UPPER LEVEL FLOOR
PLAN
Author: justinh
File Name: PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf
Color:
Elevations show a deck with
guardrail in this location but floor
plans do not. Please revise.
Subject: PlanCheck
Page Label: A-202 EXTERIOR ELEVATIONS
Author: justinh
File Name: PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf
Color:
These openings must be smaller
than 4" if the guard is to restrict
the passage of a 4" sphere,
please revise your typ
dimension.
Subject: PlanCheck
Page Label: A-202 EXTERIOR ELEVATIONS
Author: justinh
File Name: PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf
Color:
This separation does not comply
with the required vent
termination clearances for the
ortal fireplace shown in its
installation instructions (3'
minimum between the vent and
any mechanical air intake),
please revise
Subject: PlanCheck
Page Label: A-501 TYP. WALL ASSEMBLIES
Author: justinh
File Name: PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf
Color:
Provide a detail showing stone
veneer flashing and weepholes
per 2015 IRC R703.8.5 and
R703.8.6
83'-6 3/8"
CRAWL SPACE
000
CONCRETE
168.00°1
0
5.0
0°
MECHANICAL
003
CONCRETECONCRETE
84'-0 3/8"
ALL CRAWL SPACES TO BE
UNVENTED PER IRC R 408.3
RE: MECH PLANS FOR
EXHAUST VENTILATION
ACCESS OPENINGS TO
CRAWLSPACE SHALL COMPLY
WITH M1305.1.4 PER IRC 2015
RE: MECHANICALL FOR
ACCESS LOCATIONS 165.00°ACCESS TO CRAWL SPAC
UNDER MASTER
Please change your
code reference to be
IMC 306.4 as well
as the reference on
A-120, we have not
adopted that portion
of the IRC.
GUEST BD
3
A-322
W6
W4
W4 W8
RD192.00°STONE PANEL WALL
WITH CAPSTONE
200.A
W8
5 1 1'-11 1/4"5 1/2"102.00°
Y
X
Elevations show a
deck with guardrail in
this location but floor
plans do not. Please
revise.
O
Y X
P
R
W V
PLANTER 3'-0"3'-0"3'-0"4" TYP4" TYP4" TYPMASTER FIREPLACE FLUSH POWER
STANCION, TYP.STANCION, TYP.
These openings must
be smaller than 4" if
the guard is to restrict
the passage of a 4"
sphere, please revise
your typ dimension.
R
Z
T
MASTER FIREPLACE FLUSH POWER VENT TERMINATION, RE: A-421
MECH GRILL, RE: MECH
This separation does
not comply with the
required vent
termination clearances
for the ortal fireplace
shown in its
installation instructions
(3' minimum between
the vent and any
mechanical air intake),
please revise
F.O.
EXT
1/2" PLYWOOD SHEATHING, RE:
STRUCTURAL
CLOSED CELL SPRAY FOAM, (R-35)
INTERIOR WALL FINISH VARIES, RE:
ROOM FINISH SCHEDULE
INT 3"RE: PLANS
Base TYP. INTER
1 1/2" = 1'-0"
STONE ANCHOR BRACKET LET
INTO STONE, RE: STRUCTURAL
ALL W/ STUCCO
TOTAL INSULATION R-VALUE = R-5
Provide a detail showing stone veneer flashing and weepholes
per 2015 IRC R703.8.5 and R703.8.6
Subject: PlanCheck
Page Label: A-520 FLOOR DETAILS
Author: justinh
File Name: PlanSet.Architecture.905 ChatfieldRd.2018.04.pdf
Color:
Revise all drawings
(architecturals, structurals, civils)
so grade is 6” or more below the
top of each foundation wall per
2015 IRC R404.1.6 (4" at stone
veneers). Alternatively, the City
will accept a lesser distance if all
of the following are provided.
Note this requirement at all
applicable wall sections and
details:
1.All wood materials within 6” of
grade to be protected from
decay per R317.1 5.
2.Waterproof membrane
extending up wall a minimum of
6” above grade.
3.Capillary break separating
concrete from wood materials.
FOS
F4 F2
T
W4
RE: RCPS
B.O
W6
SH
FOS
T.O. FINISH FLOORRE: PLANS
T.O. WALL
RE: STRUCTRE
T.O. PLANTER
RE: LANDSCAPE
PREFINISHED SHEET METAL
PERIMETER SURFACEDRAINAGE, RE: LANDSCAPE
PLANTER, RE: LANDSCAPE
1 1/2" = 1'-0"
OR AT UPPER LEVEL EXT. BALCONY 7 CANTILEVERED FLOOR @ C Revise all drawings (architecturals, structurals, civils) so grade is 6” or more
below the top of each foundation wall per 2015 IRC R404.1.6 (4" at stone
veneers). Alternatively, the City will accept a lesser distance if all of the following
are provided. Note this requirement at all applicable wall sections and details:
1.All wood materials within 6” of grade to be protected from decay per R317.1 5.
2.Waterproof membrane extending up wall a minimum of 6” above grade.
3.Capillary break separating concrete from wood materials.