Subject: PlanCheck
Page Label: A-200_EXTERIOR ELEVATIONS
Author: justinh
File Name: 0_ARCH_CHANGE ORDER 1.2.pdf
Color:
All the elevations and sections
should be revised and included
in this change order to show the
change in floor elevation and
removal of exterior decks. The
floor elevation change would
affect every elevation and
section. Currently several are
missing from the change order
set.
0_ARCH_CHANGE ORDER 1.2.pdf (1)
Subject: PlanCheck
Page Label: 2
Author: justinh
File Name: 17085-Building Permit Change Order 1 REMP
Calc-041619.pdf
Color:
The PV worksheet is filled out
incorrectly. The original group is
at 165 degrees from true south
per the plan (roof slopes to the
north) and the new 6 panel
group is at 180 degrees from
true south. Unless a new
inverter is being proposed the
inverter capacity should be
10kW per the originally
submitted spec. Please revise
the form to accurately depict the
solar system being proposed.
Please also confirm that the new
group of 6 panels will be using
the same 360W panels that the
original group had specified or
provide a new spec for the new
group.
17085-Building Permit Change Order 1 REMP Calc-041619.pdf (1)
Subject: PlanCheck
Page Label: PL1.0_PROJECT SITE PLAN & NOTES
Author: justinh
File Name: 7_SPA_R_17085-Building Permit Change Order
1.2.pdf
Color:
Please complete the attached
APSP-15 compliance
information sheet to demonstrate
compliance with the 2015 IECC
energy code requirements for
residential pools and spas.
7_SPA_R_17085-Building Permit Change Order 1.2.pdf (1)
All the elevations and sections should be revised and included
in this change order to show the change in floor elevation and
removal of exterior decks. The floor elevation change would
affect every elevation and section. Currently several are
missing from the change order set.
Parcel ID #:
CollectorAspect,Degress fromTrue South
Collector Tilt,Degrees FromHorizontal
SolarOrientationAdjustmentFactor DC side capacity(kW)Inverter capacity(kW)kW forcredit kW MitigationCredit
Collector Group 1 0 0 87.00%9.3 9.3 9.3 8.09 kWCollector Group 2 87.00%0 0.00 kWCollector Group 3 87.00%0 0.00 kWCollector Group 4 87.00%0 0.00 kWCollector Group 5 87.00%0 0.00 kWCollector Group 6 87.00%0 0.00 kWCollector Group 7 87.00%0 0.00 kWCollector Group 8 87.00%0 0.00 kWCollector Group 9 87.00%0 0.00 kWCollector Group 10 87.00%0 0.00 kWCollector Group 11 87.00%0 0.00 kWCollector Group 12 87.00%0 0.00 kWCollector Group 13 87.00%0 0.00 kWCollector Group 14 87.00%0 0.00 kWCollector Group 15 87.00%0 0.00 kWCollector Group 16 87.00%0 0.00 kWCollector Group 17 87.00%0 0.00 kWCollector Group 18 87.00%0 0.00 kWCollector Group 19 87.00%0 0.00 kWCollector Group 20 87.00%0 0.00 kWTotal:8.09 kW$ Mitigation Credit:55,547.30$
Instructions:1)
2)
3)DC side capacity is the total labled panel output kW in a group.4)Inverter capacity is the recommended input power in kW of your inverter(s).5)6)7)8)
PREPARED BY:Date:4/16/2019
Enter the aspect and tilt for each group. The solar orientation adjustment factor is automaticallycalculated.
PROJECT ADDRESS:
The mitigation credit will be automatically entered into your RREMP or CREMP form. If your project has both RREMP andCREMP, it will automatically divide the credits up, with priority given to mitigating the CREMP payment.
Determine how many collector groups you have. Groups are used to differentiate between collectors(panels) with different tilts, aspects, sizing, or inverters. If all your collectors are installed similarily, youmight have just one group.
905 Chatfield Rd. Aspen, CO 81611
The kW mitigation credit is totalled and multiplied by $6865.32/kW to get the $ Mitigation Credit
You will be given credit for the lesser of the labeled panel output or the inverter.The kW for credit is multiplied by the solar orientation adjustment factor to get kW mitigation credit.
PV WORKSHEET
City of Aspen Version 11.3 Updated December 13, 2017
Permit Number:0273502402004
The PV worksheet is filled out incorrectly. The
original group is at 165 degrees from true south per
the plan (roof slopes to the north) and the new 6
panel group is at 180 degrees from true south.
Unless a new inverter is being proposed the inverter
capacity should be 10kW per the originally
submitted spec. Please revise the form to
accurately depict the solar system being proposed.
Please also confirm that the new group of 6 panels
will be using the same 360W panels that the
original group had specified or provide a new spec
for the new group.
Please complete the attached APSP-15
compliance information sheet to
demonstrate compliance with the 2015
IECC energy code requirements for
residential pools and spas.