HomeMy WebLinkAboutFile Documents.45 Callahan Ct.0014.2017 (9).ACBKCity of Aspen - Asbestos Checklist
Project Address: 845 Meadows Road
Txr fnv a Asvru
Parcel ID #: 2735-121-29-008
Asbestos is a known human carcinogen and is an airborne hasard. Once airborne, asbestos fibers can stay suspended in the air
for days, weeks or even months before settling out ofthe air, only to become airborne again from some minor disturbance, such as
turning on an air conditioner. Uncontrolled asbestos abatement projecd or renovation projects that disturb asbestos may cause
latent asbestos hazards that could expose people to asbestos in the future, long after the renovation activity occurred. The
airborne asbestos fiber concentrations resulting from disturbances may result in a significant esposure to the current andfuture
occupants ofthe home.
The 1989 "Ban" on asbestos -containing materials is commonly misunderstood. In fact, in 1991 the
U.S. Fifth Circuit Court of appeals vacated much of the so-called "Asbestos Ban and Phaseout
Rule" and remanded it to the EPA Thus, much of the original 1989 EPA ban on the U.S.
manufacturing, importation, processing, or distribution in commerce of many asbestos -containing
product categories was set aside and DID NOT TAKE EFFECT. Therefore, ALL demolition, remodel
or renovation projects must determine H disturbed material above the trigger levels contains
asbestos.
1. Residential: Will you be removing more than 32 sq It, 50 linear feet (e.g., pipe insulation), or the volume
equivalent of a 55-gallon drum of any material besides concrete, wood, bricks or steel — examples are
drywall, linoleum, ceiling tiles, roofing materials, etc.? 0 NO Q YES
2. Commercial: Will you be removing more than 160 sq ft, 260 linear feet (e.g., pipe insulation), or the
volume equivalent of a 55-gallon drum of any material besides concrete, wood, bricks or steel —
examples are drywall, linoleum, carpet, carpet adhesives, ceiling tiles, roofing materials, etc.?
0 NO [WYES
3. Will you be completely demolishing the building? m NO Q YES
If the answer is YES to any of the above, you will need an asbestos test before you can receive a
building and/or demolition permit. A state certified asbestos inspector must do this test and the test
report must be submitted with the building permit application. If the building has asbestos, a state certified
asbestos abatement firm must remove it. After removal, the abatement firm must provide a letter to the
Building Division staling that all the asbestos has been removed and that the air is clean. This letter must
be received BEFORE a permit will be issued. (See the local or statewide Yellow Pages, DexOnLine, or
htto://www.cdphe.state.co.us/ao/asbestos/index.htm] for certified asbestos inspectors and abatement companies.
ALWAYS ask for proof of current state cerfification.)
If YES to question # 3, you must submit a demolition permit app with the CDPHE in addition to the Aspen
permit app. This form may be found at hdos://www.colora(io.aov/pacifdcdohe/asbestos-forms NOTE: A copy
of this demolition permit app must be submitted with the Initial building permit application. When the CDPHE
approves the app, their issued permit must be given to the Aspen Building Dept before we Issue our permit.
I hereby certify that the above information is true and complete.
Owner /�tja^-d Phone # q -7 o - 5-q 4 - -] 9 a 5
Applicant (print name) ,�LJi o-) Phone #
Vpplicant Signature t.(a e,e.ce_. / -LJ" Date
Please call the City of Aspen Environmental Health Department at 920-5039 at any time ifyou have questions
about asbestos, Interpreting your test results, or other matters.
Webpage: hUp://www.aspenpitkin.mm/pdfs/depts/41/asbestosquestionnaire.pdf Rev. 04-15