HomeMy WebLinkAboutFile Documents.614 North St.0248.2017 (47).ARBK1      Drainage Report 614 W. NORTH STREET ASPEN, CO 81611 September 6th, 2017 Updated February 15th, 2018 Updated April 30th , 2018 Prepared by Richard Goulding, P.E. Roaring Fork Engineering 592 Highway 82 Carbondale, CO 81623 5/4/2018 Reviewed by Engineering 05/16/2018 12:04:02 PM "It should be known that this review shall not relieve the applicant of their responsibility to comply with the requirements of the City of Aspen. The review and approval by the City is offered only to assist the applicant's understanding of the applicable Engineering requirements." The issuance of a permit based on construction documents and other data shall not prevent the City of Aspen from requiring the correction of errors in the construction documents and other data. 2      Drainage Report 614 W. NORTH STREET ASPEN, CO 81611 I HEREBY AFFIRM THAT THIS REPORT FOR THE IMPROVEMENTS AT 614 W. NORTH STREET, ASPEN, CO WAS PREPARED BY ME FOR THE OWNERS THEREOF IN ACCORDANCE WITH THE PROVISIONS OF THE CITY OF ASPEN URBAN RUNOFF MANAGEMENT PLAN AND APPROVED VARIANCES AND EXCEPTIONS LISTED THERETO. I UNDERSTAND THAT IT IS THE POLICY OF THE CITY OF ASPEN THAT THE CITY OF ASPEN DOES NOT AND WILL NOT ASSUME LIABILITY FOR DRAINAGE FACILITIES DESIGNED BY OTHERS. RICHARD GOULDING, P.E. RFE Project # 2017-33 5/4/2018 3      Table of Contents 1.0 General .................................................................................................................................................... 4  1.1 Existing Site ......................................................................................................................................... 4  1.2 Proposed Conditions ........................................................................................................................... 4  1.3 Previous Drainage Studies .................................................................................................................. 5  1.4 Offsite Drainage & Constraints ........................................................................................................... 5  2.0 Drainage Basins and Sub‐basins .............................................................................................................. 5  2.1 Drainage Basins ................................................................................................................................... 5  2.2 Peak Discharge Calculations ................................................................................................................ 5  3.0 Low Impact Site Design ........................................................................................................................... 7  3.1 Principles ............................................................................................................................................. 7  4.0 Hydrological Criteria ............................................................................................................................... 8  4.1 Storm Recurrence and Rainfall ........................................................................................................... 8  4.2 Peak Runoff Methodology .................................................................................................................. 8  5.0 Hydraulic Criteria .................................................................................................................................... 8  5.1 Inlets .................................................................................................................................................... 9  5.2 Pipes .................................................................................................................................................... 9  6.0 Proposed Facilities ................................................................................................................................ 12  6.1 Drywell .............................................................................................................................................. 12  6.2.1 Infiltration .................................................................................................................................. 12  7.0 Operation and Maintenance ................................................................................................................. 12  7.1 Drywell .............................................................................................................................................. 12  7.2 Pervious Paver Area .......................................................................................................................... 13  8.0 Appendices ............................................................................................................................................ 13  Drawings 11x17 ....................................................................................................................................... 13      5/4/2018 4      1.0 General 1.1 Existing Site This report is an evaluation of a developed site located to the north of W. North Street, in the middle of  the block between North 5th and North 6th Street in the City of Aspen, Colorado. The property address is  614 W. North Street, and is located between two residential homes. To the north is the alley Right‐of‐ Way, and to the south is the North Street Right‐of‐Way. The lot is 4,064 square feet (sf.) and consists of a  3,800 sf. single‐family residence with a concrete driveway and flagstone patios. Large mature trees are  scattered along the southern half of the property and Right‐of‐Way, and large mature trees located near  the northeast property corner. No sidewalk or curb and gutter is installed in front of the residence on  North Street. All utilities are located in the alley, excluding the water line, which is located in North Street.     View of the site from North Street  A Geotechnical Report was produced on August 21, 2017. One exploratory bore was limited to 8 feet  below grade to perform the analysis due to auger refusal. The bore results are described as 0.5 feet of  organic, sandy clay and silt “topsoil”, over 6.5 feet of mixed clayey sand and gravel backfill material. The  final 1.5 feet of the boring consisted of gravel and cobbles where the practical auger refused at 8 feet  below the surface. No groundwater was encountered. A percolation test was conducted during this  analysis, with an average percolation rate of 4 minutes per inch, or 15 inches per hour.  1.2 Proposed Conditions This project is classified as a ‘Major Project’ per Table 1.1 of the URMP. This is because the proposed  development is over 1,000 square feet (sf) and disturbs an area of approximately 2,707 sf., which is over  67% of the site. The intent of this report is to demonstrate compliance with the requirements of the  5/4/2018 5      URMP. The Low Impact Design (LID) Principles in the introduction of the manual were used as a guide  throughout the design process. Onsite storm infrastructure has been sized for conveyance and full  detention storage of a 100 year event.   The proposed residence to be remodeled is 4,369 square feet (sf). Patios will be located on the south  and east sides of the structure. An existing two car garage will be accessed from the alley. For drainage,  one drywell will capture all runoff from roofs and hardscape and is sized to have capacity for full  detention.    Existing utilities servicing the residence will remain and will be used to service the remodeled residence.  1.3 Previous Drainage Studies The City of Aspen updated their URMP in 2014 and the property is within the boundaries of the study.  The study indicates that the property is not within a Mudflow Area.  1.4 Offsite Drainage & Constraints No offsite basins effect the site; no analysis was required.  2.0 Drainage Basins and Sub‐basins   The site was designed as one major drainage basin, which was then subdivided into smaller sub‐basins. A  Drainage Exhibit in the appendices illustrates the basin and sub‐basin delineations.  It lists Impervious  Areas, Runoff Coefficients, and Peak Flows.     The sub‐basins were created to calculate the concentrated flow from each impervious area, including  patios, decks and roofs. These sub‐basin peak flows were then used to size the proposed infrastructure.  2.1 Drainage Basins Basin 1 is 2,293 square feet (sf), 100% impervious, and consists of roof and deck areas, patios, and the  existing concrete driveway. Runoff from this basin is collected and conveyed to the drywell through a  series of downspouts, inlets, and trench drains. This drywell has capacity for full detention for the entire  basin.   2.2 Peak Discharge Calculations The peak flows were calculated for each Major Basin for the 5 and 100 year storm events. Rainfall  intensity was calculated using a Time of Concentration (Td) of 5 minutes.  Actual time of concentration  on the site is significantly less than 5 minutes, but according to the City of Aspen URMP, equations used  to calculate rainfall intensity are only valid for a Time of Concentration of greater than 5 minutes. So the  smallest valid Time of Concentration value was used.  The 1 hour Rainfall depth (P1), given in Table 2.2 as  0.64 inches for the 5‐year event and 1.23 inches for the 100‐year event. Equation 2.1 was referenced  when solving for the Rainfall Intensity.   I = 88.8P1/(10+Td )1.052  5/4/2018 6      Runoff Coefficients (C), a function of the Soil Group (in this case B) and the percentage of impervious  area within each basin were developed using Figure 3.2. The Runoff Coefficient (C) was then multiplied  by the Rainfall Intensity (I) and the acreage of each Major Basin (A) to determine the peak discharge for  each Major Basin. Q allowable was calculated the same way except each basin was treated as  undeveloped or 100% pervious. The Peak Discharge (Qp) is given by equation 3.1.    Qp= CIA  Qp= Peak Discharge (cfs)  C= Runoff Coefficient (Unitless)   I= Rainfall intensity (inches per hour)  A= Area (Acres)     Peak flow values were used to calculate the size of the proposed detention and conveyance structures,  such as drywells, inlets and piping. The tables below contain the peak flows for developed and  undeveloped conditions for 5 and 100 year storm events.                5 Year Peak Discharge Developed Calculations  1 Hour(P1)0.64 Return Period 5 Basin ID Total Area Imp. Area  Impervious C Value Time of CIntensityQ Max See(D1) (ft 2)(ft2)(%)From Table  (Td) I=88.8P1/(10+Td)1.052 (ft3/sec) 1 2292.89 2292.89 100.00% 0.896 5 3.29 0.16 5 Year Peak Discharge Pre Development Calculations  1 Hour(P1)0.64 Return Period 5 Basin ID Total Area Imp. Area  Impervious C Value Time of CIntensityQ Max See(D1) (ft 2)(ft2)(%)From Table  (Td) I=88.8P1/(10+Td)1.052 (ft3/sec) 1 2292.89 0.00 0.00% 0.080 5 3.29 0.01 100 Year Peak Discharge Developed Calculations  1 Hour(P1)1.23 Return Period 100 Basin ID Total Area Imp. Area  Impervious C Value Time of CIntensityQ Max See(D1) (ft 2)(ft2)(%)From Table  (Td) I=88.8P1/(10+Td)1.052 (ft3/sec) 1 2292.89 2292.89 100.00% 0.950 5 6.33 0.32 100 Year Peak Discharge Pre Development Calculations  1 Hour(P1)1.23 Return Period 100 Basin ID Total Area Imp. Area  Impervious C Value Time of CIntensityQ Max See(D1) (ft 2)(ft2)(%)From Table  (Td) I=88.8P1/(10+Td)1.052 (ft3/sec) 1 2292.89 0.00 0.00% 0.350 5 6.33 0.12 5/4/2018 7      3.0 Low Impact Site Design   Low Impact Development (LID) aims to mimic the natural pre‐development hydrologic pattern. The goal  is to manage storm water as close to its source as is possible. This entire developed site is approximately  57% impervious. The treatment train approach is used on all runoff to increase water quality and  percolation.  3.1 Principles Principle 1: Consider storm water quality needs early in the design process.  The Grading and Drainage design was coordinated with the architect during the design phase. Due to  the lack of space for the project, coordination in the design process was key.  Principle 2: Use the entire site when planning for storm water quality treatment.  Because of the size and limitations of the parcel, it was necessary in the design process to use the site  efficiently. Grading away from the residence for the project was difficult to achieve with the flat site.   Principle 3: Avoid unnecessary impervious area.  Pervious paver patios are being implemented, which will reduce the impervious area of the site.  Principle 4: Reduce runoff rates and volumes to more closely match natural conditions.  The runoff will all be infiltrated into the ground, as the drywells are sized for full detention. There will be  no runoff leaving the site.     Principle 5: Integrate storm water quality management and flood control.  The Drywells are being used for water quality, which in itself increases flood control. The drywells will  eliminate the peak flow as there is no runoff leaving the site.  Principle 6: Develop storm water quality facilities that enhance the site, the community and the  environment.  The proposed design encourages replenishing groundwater, and does not introduce any runoff into the  city infrastructure. This reduces the flows being introduced to the Roaring Fork River.   Principle 7: Use treatment train approach.  The emergency overflow from the drywell will release into a grass field, which will treat the water  before entering the city storm system.  Principle 8: Design sustainable facilities that can be safely maintained.   5/4/2018 8      Screens will be placed over downspouts to provide a barrier against vermin and debris. Drainage  systems were simply designed so maintenance is minimized. Infrastructure will be just below grade  providing little labor for maintenance. The Owner will sign a maintenance agreement as part of their  Certificate of Occupancy.  Principle 9: Design and maintain facilities with public safety in mind.  Proper drainage and grading of the driveway and walkways reduces ice buildup and dangerous icy  conditions. All grading was done with safety as the priority.   4.0 Hydrological Criteria 4.1 Storm Recurrence and Rainfall The property is not in the commercial core and is not served by any city curb and gutter so this property  classifies as a “Sub‐urban area not analyzed or served by public storm sewer”. The 5 and 100‐year events  were analyzed for this designation.   4.2 Peak Runoff Methodology Since the site is not serviced by public storm infrastructure, full detention is necessary. To determine these  capacities, the rainfall from a 100 year storm that is collected on all impervious areas must be detained.  No detention is required for pervious areas. Below is a summary of the required storage.     5.0 Hydraulic Criteria Sub‐basins were delineated per the design points of concentrations created by roof drains and inlets.  Pipe networks were then created connecting the sub‐basins and conveying the flows to the overall point  of concentration for the basin. The 100‐year peak flow for each sub‐basin was calculated.  Full Detention Storage Basin Total Area Impervious Area Impervious Full Detention Depth Factor of Safety Required Storage BMP (ft2)(ft2) (%) (in) F.O.S. (ft 3) 1 2292.89 2292.89 100.00% 1.23 1 235 Drywell 5/4/2018 9        5.1 Inlets The 100 year peak flows were used in the sizing of inlets. Equations 4‐17 to 4‐20 from the URMP were  used in the analysis. They incorporate a 50% clogging factor and 40% opening in the grates.  A water  depth of 0.04’ was assumed and all the inlets were treated as sumps as they will be set a minimum of  .04‘(½ Inch) below the flow lines. Below is a summary of each square inlet being tested for capacity  against their tributary basin.     5.2 Pipes The pipes were analyzed by calculating the flow from the sub basins entering them. Below is table which  groups what sub basins are conveyed in each pipe. The TOC is below 5 minutes for all sub‐basins, so a  reduction was not taken for the intensity.  They were tested for hydraulic capacity at 80% of pipe  diameter. Depth of flow was also calculated in the tables below. The pipes are all SDR 35 PVC with a  Manning’s coefficient of 0.01.    Design Q design / Q full charts were downloaded from FHWA. The equations in Section 4.8.4 was used as  the basis for these calculations.   100 Year Sub Basin Peak Discharge Developed Calculations  1 Hour(P1)1.23 Return Period 100 Sub Basin Total Area Imp. Area  Impervious C Value Time of CIntensitySub Basin Flow Rate (Name) At (ft2)Ai (ft2)Ai/At (%) From Table  (Td) I=88.8P1/(10+Td)01.052 Qsub (ft3/sec) 1.1 494.32 494.32 100.00% 0.950 5 6.33 0.07 1.2 180.27 180.27 100.00% 0.950 5 6.33 0.02 1.3 155.56 155.56 100.00% 0.950 5 6.33 0.02 1.4 465.98 465.98 100.00% 0.950 5 6.33 0.06 1.5 232.55 232.55 100.00% 0.950 5 6.33 0.03 1.6 397.08 397.08 100.00% 0.950 5 6.33 0.05 1.7 49.84 49.84 100.00% 0.950 5 6.33 0.01 1.8 317.29 317.29 100.00% 0.950 5 6.33 0.04 Sub Basin and Rectangular Inlet Calculations  1 Hour(P1)1.23 m=40% Ys=.04 (Depress inlet by 0.04') Return Period 100 Cg=50% Co=0.65 Inlet ID Basin ID Total Area Imp. Area  Impervious C Value Time of Concentration Intensity Q Max Inlet Type Inlet Width Inlet Length Effective Open Area (EQ. 4‐20) Inlet Capacity   (EQ 4‐19) Has Capacity See(D1) (ft 2)(ft2)(%)(From Table) (Td) I=88.8P1/(10+Td)1.052 (ft3/sec) Rectangular Wo (inches) Lo (inches) Ae=(1‐Cg)mWoLo Q=CoAe√2gYs (Yes/No) A5‐TRENCH DRAIN 1.3 155.56 155.56 100.00% 0.950 5 6.33 0.021 6" x 11.5' 6 138 1.150 1.154 Yes A16‐TRENCH DRAIN 1.7 49.84 49.84 100.00% 0.950 5 6.33 0.007 6" x 4' 6 48 0.400 0.401 Yes 5/4/2018 10          Storm System Pipes Pipe System Pipe Contibuting Sub‐Basins Design Flow Rate Qdes A1 1.1 0.07 A2 1.1 0.07 A3 1.1 0.07 A4 1.1, 1.2 0.09 A5 1.1‐1.3 0.11 A6 1.1‐1.3 0.11 A7 1.4 0.06 A8 1.1‐1.4 0.18 A9 1.5 0.03 A10 1.1‐1.5 0.21 A11 1.1‐1.5 0.21 A12 1.1‐1.5 0.21 A13 1.1‐1.6 0.27 A14 1.1‐1.6 0.27 A15 1.1‐1.6 0.27 A16 1.7 0.01 A17 1.7 0.01 A18 1.7 0.01 A19 1.1‐1.7 0.27 A20 1.8 0.04 A K=0.462 Pipe Design Flow  Rate Proposed  Slope Manning  Coefficient Required Pipe Diameter  Equation 4‐31 Required Pipe  Diameter  Proposed Pipe  Diameter Qdes (ft3/sec) S (%) n  d (ft) = {nQdes/K√S}3/8 Dreq (in) Dpro (in) A1 0.07 2.00% 0.01 0.18 2.17 4.0 A2 0.07 2.00% 0.01 0.18 2.17 4.0 A3 0.07 2.00% 0.01 0.18 2.17 4.0 A4 0.09 2.00% 0.01 0.20 2.44 4.0 A5 0.11 2.00% 0.01 0.22 2.63 4.0 A6 0.11 2.00% 0.01 0.22 2.63 4.0 A7 0.06 2.00% 0.01 0.18 2.12 4.0 A8 0.18 2.00% 0.01 0.26 3.11 4.0 A9 0.03 2.00% 0.01 0.14 1.63 4.0 A10 0.21 2.00% 0.01 0.28 3.31 4.0 A11 0.21 2.00% 0.01 0.28 3.31 4.0 A12 0.21 2.00% 0.01 0.28 3.31 4.0 A13 0.27 2.00% 0.01 0.30 3.61 4.0 A14 0.27 2.00% 0.01 0.30 3.61 4.0 A15 0.27 2.00% 0.01 0.30 3.61 4.0 A16 0.01 2.00% 0.01 0.08 0.92 4.0 A17 0.01 2.00% 0.01 0.08 0.92 4.0 A18 0.01 2.00% 0.01 0.08 0.92 4.0 A19 0.27 2.00% 0.01 0.30 3.65 4.0 A20 0.04 2.00% 0.01 0.15 1.84 4.0 Pipe Sizing 5/4/2018 11            Pipe Design Flow  Rate Proposed Pipe  Diameter Slope 80% of Proposed  Pipe Diameter Manning  Coefficient Full Pipe Cross  Sectional Area Full Pipe Flow Rate Q Design /  Q Full d/D Hydraulic Grade Line (Depth of Flow) Depth of Flow Less Than  80% of Pipe Diameter Qdes (ft3/sec) Dpro(in) S (%) Dpro*.8 (in) n A (ft) = π (Dpro/2)2 Qfull (ft3/s) = A(1.49/n)((Dpro/48)2/3)S1/2 Qdes/Qfull (from Chart) d (in) = (d/D)*Dpro (Yes/No) A1 0.07 4.0 2.00% 3.2 0.01 0.087 0.351 0.19 0.34 1.34 Yes A2 0.07 4.0 2.00% 3.2 0.01 0.087 0.351 0.19 0.34 1.34 Yes A3 0.07 4.0 2.00% 3.2 0.01 0.087 0.351 0.19 0.34 1.34 Yes A4 0.09 4.0 2.00% 3.2 0.01 0.087 0.351 0.27 0.38 1.52 Yes A5 0.11 4.0 2.00% 3.2 0.01 0.087 0.351 0.33 0.45 1.80 Yes A6 0.11 4.0 2.00% 3.2 0.01 0.087 0.351 0.33 0.45 1.80 Yes A7 0.06 4.0 2.00% 3.2 0.01 0.087 0.351 0.18 0.33 1.30 Yes A8 0.18 4.0 2.00% 3.2 0.01 0.087 0.351 0.51 0.57 2.28 Yes A9 0.03 4.0 2.00% 3.2 0.01 0.087 0.351 0.09 0.24 0.94 Yes A10 0.21 4.0 2.00% 3.2 0.01 0.087 0.351 0.60 0.63 2.52 Yes A11 0.21 4.0 2.00% 3.2 0.01 0.087 0.351 0.60 0.63 2.52 Yes A12 0.21 4.0 2.00% 3.2 0.01 0.087 0.351 0.60 0.63 2.52 Yes A13 0.27 4.0 2.00% 3.2 0.01 0.087 0.351 0.76 0.73 2.90 Yes A14 0.27 4.0 2.00% 3.2 0.01 0.087 0.351 0.76 0.73 2.90 Yes A15 0.27 4.0 2.00% 3.2 0.01 0.087 0.351 0.76 0.73 2.90 Yes A16 0.01 4.0 2.00% 3.2 0.01 0.087 0.351 0.02 0.08 0.32 Yes A17 0.01 4.0 2.00% 3.2 0.01 0.087 0.351 0.02 0.08 0.32 Yes A18 0.01 4.0 2.00% 3.2 0.01 0.087 0.351 0.02 0.08 0.32 Yes A19 0.27 4.0 2.00% 3.2 0.01 0.087 0.351 0.78 0.74 2.95 Yes A20 0.04 4.0 2.00% 3.2 0.01 0.087 0.351 0.12 0.26 1.05 Yes Hydraulic Grade Line and Pipe Capacity Pipe Design Flow  Rate Proposed Pipe  Diameter Slope d/D Manning  Coefficient Rh/D Hydraulic Radius Exit Velocity  (ID)Qdes (ft3/sec) Dpro(in) (%) (from Chart) n (from Chart) Rh (ft) = (Rh/D) Dpro V (ft/sec) = [1.49/n] Rh 2/3 √S  A1 0.068 4.0 2.00% 0.34 0.01 0.18 0.18 6.84 A2 0.068 4.0 2.00% 0.34 0.01 0.18 0.18 6.84 A3 0.068 4.0 2.00% 0.34 0.01 0.18 0.18 6.84 A4 0.093 4.0 2.00% 0.38 0.01 0.21 0.21 7.35 A5 0.115 4.0 2.00% 0.45 0.01 0.23 0.23 7.98 A6 0.115 4.0 2.00% 0.45 0.01 0.23 0.23 7.98 A7 0.064 4.0 2.00% 0.33 0.01 0.18 0.18 6.72 A8 0.179 4.0 2.00% 0.57 0.01 0.27 0.27 8.81 A9 0.032 4.0 2.00% 0.24 0.01 0.14 0.14 5.58 A10 0.211 4.0 2.00% 0.63 0.01 0.28 0.28 9.10 A11 0.211 4.0 2.00% 0.63 0.01 0.28 0.28 9.10 A12 0.211 4.0 2.00% 0.63 0.01 0.28 0.28 9.10 A13 0.266 4.0 2.00% 0.73 0.01 0.30 0.30 9.41 A14 0.266 4.0 2.00% 0.73 0.01 0.30 0.30 9.41 A15 0.266 4.0 2.00% 0.73 0.01 0.30 0.30 9.41 A16 0.007 4.0 2.00% 0.08 0.01 0.05 0.05 2.91 A17 0.007 4.0 2.00% 0.08 0.01 0.05 0.05 2.91 A18 0.007 4.0 2.00% 0.08 0.01 0.05 0.05 2.91 A19 0.273 4.0 2.00% 0.74 0.01 0.30 0.30 9.43 A20 0.044 4.0 2.00% 0.26 0.01 0.15 0.15 5.99 Exit Velocities 5/4/2018 12      6.0 Proposed Facilities 6.1 Drywell The proposed drywell collects all runoff from the site and is designed to have capacity for full detention.  Five feet of perforations are proposed for the drywell, rather than the standard 4 feet. The drywell is 5  feet in diameter and 16 feet deep, with 10 feet of storage capacity. It is 3.4 feet away from a structural  column and 2.9 feet from the property line that borders the Waters Avenue ROW. An impermeable liner  is proposed on half of the outside of the drywell that faces the residence to allow infiltration only  towards the ROW so that it will not affect the structure. If the system were to backup during a storm  event, the additional 6 feet of drywell capacity will allow it to not overflow. Below is a summary of the  drywell storage capacity.    6.2.1 Infiltration Part of the analysis is to ensure that the drainage structures can completely drain within 24 hours. The  minimum depth of perforation a drywell must have is 4 feet, however 5 feet of perforations is proposed  for this specific drywell. Below is a calculation showing that there is enough perforation area for the  drywell to drain within 24 hours using the percolation rate determined from H‐P Kumar’s Subsoil Study.  The determined percolation rate of 15 inches per hour for the entire site.  Section 8.5.4.2 was  referenced for these calculations. The perforated area was reduced by half due to the impermeable liner  being proposed on the outer half of the drywell facing the structure.    7.0 Operation and Maintenance 7.1 Drywell Drywells must be inspected and maintained quarterly to remove sediment and debris that has washed  into them. A maintenance plan shall be submitted to the City in the Drainage Report describing the  maintenance schedule that will be undertaken by the owners of the new residence or building. Minimum  inspection and maintenance requirements include the following:   Inspect drywells at least four times a year and after every storm exceeding 0.5 inches.   Dispose of sediment, debris/trash, and any other waste material removed from a drywell at   suitable  disposal  sites  and  in  compliance  with  local,  State,  and  Federal  waste regulations.   Routinely evaluate the drain‐down time of the drywell to ensure the maximum time of 24 hours is  not being exceeded. If drain‐down times are exceeding the maximum, drain the drywell via  Drywell Storage Drywell Basins Diameter Storage Depth Internal Volume External (18" of Screened Rock) Volume Total Capacity Required Capacity (Name) (#) D (ft) H (ft)π*H*(D/2)2) (ft3)0.3*π*5*((D/2)+1.5)2 ‐ (D/2)2) (ft3)(ft3)(ft3) Drywell 1 5 10 196 46 242 235 Drywell Infiltration Name Diameter Perforation Height Perforated Area Total Capacity Infiltration Rate Infiltration Time Volume Infiltrated in 24 Hours (Name) D (ft) H (ft)A (ft2) = (3.14*D*H)/2 V (ft3)I (in/hr) T (hr) = V/(A*I/12) Vtotal (ft3) = V*T Drywell 5 5 39.27 242.30 15 4.936 1195.97 5/4/2018 13      pumping and clean out the percolation area (the percolation barrel may be jetted to remove  sediment accumulated in perforations. If slow drainage persists, the system may need to be  replaced.  7.2 Pervious Paver Area As per section 8.5.3.1 of the URMP, the following schedule will be undertaken by the owners of the  property to achieve long term performance of the BMP’s.     8.0 Appendices Drawings 11x17 5/4/2018