HomeMy WebLinkAboutFile Documents.330 Gillespie St.0003.2018 (22).ARBK CONSTRUCTION MANAGEMENT PLAN
Project name: Gillespie Remodel
330 Gillespie St. Aspen CO.
APPROVED
Prepared by I.A.Sedgwick Inc. DATE
Dec. 25, 2017
Permit#Pending BY
1.0 General
A Construction Management Plan is being submitted. The project is located inside the City of
Aspen and within the County of Pitkin Colorado, and will be disturbing+/- 32 cubic yards of
soil. This project will consist of the renovation of a bathroom suite in an existing home and a
basement renovation to that existing home.
TABLE OF CONTENTS
2.0 PROJECT INTRODUCTION
2.1 DISTURBANCE AREA
2.2 LOCATION
2.3 DESCRIPTION
3.0 PROJECT DOCUMENTATION
3.1 PERMITS/OTHER DOCUMENTS
3.2 PUBLIC NOTIFICATION
3.3 PROJECT SIGN
3.4 CONTACT DESIGNATION
4.0 PROJECT IMPLEMENATION
4.1 DATES OF CONSTRUCTION
4.2 HOURS OF CONSTRUCTION
4.3 SEQUENCE(PHASING)OF CONSTRUCTION
4.4 ADJOINING PROPERTY OWNERS
4.5 PROJECT FENCING
4.6 PUBLIC HEALTH AND WELFARE
4.7 NATURAL ENVIRONMENT
5.0 PARKING MANAGEMENT
5.1 PARKING MANGEMENT FORM
5.2 EMERGENCY VEHICLE ACCESS AND ORDINANCE 35
5.3 CONSTRUCTION PARKING DETAILS
5.4 STAGING AREAS
5.5 CONSTRUCTION TRAILER,MATERIALS STORAGE,AND WASTE MANAGEMENT
6.0 TRAFFIC CONTROL
6.1 GENERAL
6.2 HAUL ROUTES
6.3 ONSITE VEHICLE LIMITATIONS
6.4 DELIVERY REQUIREMENTS
6.5 TRAFFIC CONTROL PLAN
7.0 PEDESTRIAN PROTECTION
7.1 GENERAL
8.0 SEDIMENT AND EROSION CONTROL
8.1 REQUIREMENTS
8.2 SMUGGLER MOUNTAIN RESTRICTONS
9.0 FUGITIVE DUST CONTROL
9.1 FUGITIVE DUST CONTROL PLAN
9.2 REQUIREMENTS
10.0 EMISSIONS
10.1 GENERAL
10.2 EMISSIONS FROM DIESEL POWERED ENGINES
11.0 NOISE SUPRESSION
11.1 GENERAL
11.2 NOISE SUPPRESSION PLAN
11.3 REQUIREMENTS
11.4 SPECIFIC RESTRICTIONS RELATED TO MANUFACTURING ON SITE
APPENDICES
A—Required Project Sign
C—Haul Route Map
D—Noise Suppression Plan,Techniques and Equipment
F—Ordinance 35
G—Site Plan Sketch
2.0 Project Introduction
This project consists of the renovation of an existing home located at 330 Gillespie St.,
Aspen, Pitkin County, Colorado. The renovation shall be contained to the master bathroom
suite and include the master bathroom, master closet. The scope also includes that
renovation of a basement level media and closet area of the house and will require
excavation and a new concrete lightwell area as well as backfill and clean up. Upgraded
Utilities and repairs of all systems in these two areas of the house will also be included in
the scope of this project.
2.1 Total Disturbance Area
(1). The addition of a light well to the basement will require new concrete foundation and
concrete slab, and excavation will be required. Total disturbance of soil for this area shall not
exceed 33 cubic yards of soil removal. Total square footage of area impacted by excavation not
to exceed 110 sf.
(2). The renovation of the existing building will take place within the existing structure and
within the existing footprint of the current home. Please see the site plan for areas of disturbance
and re vegetation. No exterior renovation elements will be included in the scope at this time for
the master bathroom suite.
Vicinity Map
Driving Directions: From Highway 82, Drive into Aspen and turn Left (East) on 3rd
Street. Travel seven blocks and the project is located on Gillespie St.
2.3 DESCRIPTION
This project is an overall remodel of the master bathroom suite of an existing home and the
renovation of a basement level media and closet area. We are adding a bathroom to the lower
level media room and changing the closet into a bedroom with a light well for egress. There will
be excavation work to the east side of the existing home in order to add this light well area.
Demolition shall for the most part be done by hand and haul off shall be in both dump trailers
and in commercial dumpsters.
Parcel ID#-273 512131002
The existing home is zoned as R-6
Building Use is—Residential
Site Area—6429 SF
3.0 PROJECT DOCUMENTATION
3.1 PERMITS
The plans will be submitted to City of Aspen Community Development Department for a
building permit. Permit number is pending. Upon issuance, copies of all applicable local, state
and federal licenses and permits will be maintained at the project site office. Applicable permits
will be listed and described in this CMP, and copies of the documents will be attached hereto.
All associated and applicable Electrical, Plumbing, Mechanical, Roofing, to follow,pending
approvals.
3.2 PUBLIC NOTIFICATION
This property is located on a city lot and shares a boundary with a neighbor on both sides. Those
neighboring owners shall receive notice of construction via written letter and via email
correspondence. There shall be no traffic delays due to the renovation and construction of this
home, as the residence has private driveway from the Street. Normal construction traffic will
access the property via Gillespie street and Highway 82. Large loads will have proper signal
crews to aid access to and from the site.
3.3 PROJECT SIGN
A project sign shall be constructed and posted as required. The sign shall be posted in a location
where it is readable from the street or driveway and shall meet criteria in City Municipal Code
26.510.030B4.
(See attached Appendix A)
3.4 CONTACT DESIGNATION
Owner: Cynthia Chase/Noah Shore 970-544-9265
Contractor: I.A.Sedgwick Inc. 970-948-1890
Site supervisor; Ben Allen 970-948-1890
Traffic Officer If Required/Ben A. 970-948-1890
City of Aspen Building Dept. General 970-920-5090
Fire department Emergency 911 970-925-5532
Aspen Police Department Emergency 911 970-920-5400
Utility company Aspen Electric CO. 970-920-5148
Water Dept. Aspen Water Dept. 970-920-5110
Source Gas Black Hills Energy 970-563-0012
Hospital contact Emergency 911 970-925-1120
Emergency call 911 call 911
4.0 PROJECT IMPLEMENTATION
4.1 DATES OF CONSTRUCTION
Construction is tentative to start in early March 2018 (pending permit procurement) and run
continually for 4 months following the start date. Expected completion is June 30, 2018.
4.2 HOURS OF CONSTRUCTION
Off-season construction hours shall be limited to 7:30am—5:30pm Monday through Friday and
9am—5pm on Saturday. No construction is permitted on Sundays or federally designated
holidays.
All activity that generates noise in excess of 80 decibels requires a noise
suppression plan and is restricted to operating between the hours of 9am and 5pm
Monday through Friday.
4.3 SEQUENCE (PHASING) OF CONSTRUCTION
A construction schedule including all project phasing,with item details, and specific
item completion dates is available should it be required. General schedule of events shall be as
follows:
05/01/18 General Demolition,protection, excavation
05/10/18 General Demolition, concrete light well, interior scope
05/15/18 Backfill, general framing, interior scope
06/01/18 Interior scope
07/01/18 Interior scope
RECEIVED
01/09/2018
ASPEN
BUILDING DEPARTMENT
0807/31/18 Interior scope, exterior clean up and finish project by 07/31/18
4.4 ADJOINING PROPERTIES
Adjoining private property and public right-of way will be supported and protected from any
damage that might result from construction operations. The construction process will be
sensitive to the adjoining properties and protect the property from any damage that might result
from construction operations.
4.5 PROJECT FENCING
Site Fencing will not be required along any side of the property for this project.
Tree fencing will not be required at the drip line of all trees as there are no trees within the scope
area of construction. Please see the attached CMP Site Plan for details and location of the light
well and its immediate access from the driveway.
4.6 NATURAL ENVIRONMENT
This project will require no trees be removed in order to complete the overall remodel submitted
for review.
5.0 PARKING MANAGEMENT
5.1 CONSTRUCTION PARKING DETAILS
All workers will be encouraged to use public transportation and to carpool. On site parking will
be allowed for subs and vendors with required tools and materials that need to be unloaded and
used on a daily basis and required to be in the existing parking area and driveway. All overflow
parking shall be done by permit parking only on City of Aspen Streets along 3nd street and West
Hopkins Ave.No construction Parking will be allowed within the free two-hour residential
parking areas without a valid parking permit.
5.3 EMERGENCY VEHICLE ACCESS
The contractor shall maintain continuous emergency vehicle access, on and around site,
Including but not limited to police, fire, and ambulance services. This includes projects
in, and along the driveway. This project will be compliant with the sections listed in Ordinance
35 (see attached Ordinance 35 Appendix F)
5.4a STAGING AREAS
Staging for this project shall be done in the existing garage location, inside the existing house
floor area and in the existing driveway area closest to the garage. These combined areas will give
the project some 500sf of area to stage materials, tools and product for on site use.
See the CMP plan for construction staging area locations.
5.4b-5.4c CONSTRUCTION TRAILER, MATERIALS STORAGE
RECEIVED
01/09/2018
ASPEN
BUILDING DEPARTMENT
A Construction trailer/office will not be required for this project as it is a remodel with areas that
are heated and weather proof and a temporary construction office will be located within the
residence. And all materials shall be stored in the garage and directly in front of the garage when
required. There is also no required portable restroom for this project as we have working
facilities on site for the duration of construction.
5.4d-5.4e WASTE MANAGEMENT
Trash dumpsters and recycling container locations.
A trash dumpster or trash trailer will be located along the side of the driveway at all times during
the project. A dumpster will only be required during the demolition phase of the project and will
be switched out to a small tow behind 12 yard dump trailer immediately thereafter.
There will be recycling receptacles for cans and bottles and cardboard and other recyclable
packaging materials, located with in the garage.
Per Aspen City Code, any dumpster or other trash receptacle that is used for food
refuse must be compliant with the City of Aspen Wildlife Protection Ordinance and any such
receptacle shall be constructed in a such a manner as to render it Bear Proof. All
construction waste containers shall be adequately covered at all times until transferred
to the landfill. The applicant shall prevent any accumulated debris, litter, or trash on
any construction site to blow or scatter onto adjoining properties.
6.0 TRAFFIC CONTROL
6.1 GENERAL
All traffic control operations shall be managed by the designated traffic control
Supervisor should it be required. Traffic control personnel shall wear clothing designating them
as traffic control and shall be able to successfully converse with the public.
6.2 HAUL ROUTES
The hauling of materials will not go into the city of Aspen's Core. Trucks will move from the
site location onto Gillespie Street and 3rd Street and then join state highway 82, and finally
progress through the round a bout and travel down valley to their finish destination. Access back
to the site for deliveries shall come up valley from Highway 82 and travel back to Gillespie St.
and 3rd St.
6.3 ONSITE VEHICLE LIMITATIONS
All construction related vehicle activities shall be defined. Maximum vehicle weights
and sizes shall be specified and be in compliance with the Pitkin County Asset
Management Plan sections 1.53.03.
6.4 DELIVERY REQUIREMENTS
Delivery vehicles may be onsite throughout the renovation between 7:30 am and 3 pm and will
be coordinated by the site supervisor and shall occur while site supervisor is on site.
RECEIVED
01/09/2018
ASPEN
BUILDING DEPARTMENT
Delivery vehicles and all other onsite vehicles are not allowed to idle for more than five
(5) Minutes, with the exception of generators or PTO type operations.
Deliveries for the Project shall be estimated according,but not limited to the following:
Delivery and construction vehicle staging. (types and numbers)
Demolition Dumpsters/Standard Dumpsters
Number of Deliveries 3
1 month for hand demolition
Dates start and stop: 05/01/18-06/01/18
Excavation
Number of trucks: 3 units, alternating on route during soils import
Dates start and stop: 05/15/18-05/20/18
Foundation Concrete and Pumping
Number of trucks: units, alternating on route during pour date
Dates start and stop 06/01/18-06/05/18
Framing
Number of deliveries: 1
Dates start and stop: 06/01/18
Drywall
Number of deliveries: 1
Dates start and stop: 06/15/18
6.5 TRAFFIC CONTROL PLAN
A traffic control Plan is not anticipated due to the small scope of this project at this time.
There is currently no need to close any roads for any construction related activities.
8.0 SEDIMENT AND EROSION CONTROL
8.1
Site Exporting shall be done on a very limited basis and site importing will also be done on a
very limited basis due to the small area of excavation.
Any exporting of materials off site will be done while traveling on a paved driveway. Should the
site become muddy, a tire wash shall be set up on site to contain any soils before they can be
tracked onto City roadways.
All concrete trucks will be required to wash into a location offsite where, after drying, the
concrete and debris can be loaded into a dumpster either by machine or by hand.
9.0 FUGITIVE DUST CONTROL
For the purposes of this project all excavation is expected to be through organic soils, and dust
control during excavation shall consist of watering with a water truck a minimum of 3 times per
day and watering by hand as required. The driveway access is currently concrete . Blowing dust
will be mitigated with sprayed water, including a water truck if necessary. Construction dust
from cutting and or grinding will be done with wet cutting at all times. Site cleanliness will be of
the utmost importance in order to reduce overall dust. There is no expected sandblasting
RECEIVED
01/09/2018
ASPEN
BUILDING DEPARTMENT
scheduled for this project. The primary means for controlling dust will be to wet down the dust
emitting source as required or as directed by the Construction Management Officer.
24 Hour Contact for Dust Control is Ben Allen/970-948-1890
10.0 EMISSIONS
10.1 GENERAL
All vehicles and equipment used on site will be properly maintained such that the
engines will function within manufacture's standards or parameters.
10.2 EMISSIONS FROM DIESEL POWERED ENGINES
Emissions from diesel engines operated within the UGB shall be of a shade or density
no darker than 40% opacity, except for starting motion no longer than 10 seconds or for
stationary operation not exceeding 10 seconds.
11.0 NOISE SUPRESSION
11.1 GENERAL
The noise limit for construction is 80 decibels measured at the property line of the construction
site. All construction equipment shall be adequately muffled and maintained to minimize project
noise. The installation of noise barriers is the minimum technique to suppress noise, especially
when jack hammering of concrete occurs, but at this time is not expected to be required.
11.2 NOISE SUPPRESSION PLAN
All activity that generates noise in excess of 80 decibels requires a noise suppression plan and is
restricted to operating between the hours of 9am and 5pm Monday through Friday.
(See attached Noise Suppression Plan—Appendix D)
RECEIVED
01/09/2018
ASPEN
BUILDING DEPARTMENT
Gillespie
Renovation
330 Gillespie St .
BUILDING PERMIT #
Pending
I .A. Sedgwick Inc .
Contact - Ben Allen
Contact Phone # 970-948-1890
Emergency Phone # 911
24 Hour Emergency Contact #
970-948- 1890
Appendix A RErEWED
01/09/2018
ASPEN
BUILDING DEPARTMENT
ATTACHMENTS:
The following items shall be included as attachments:
❑ Vicinity Map SEE SITE MAP SHEET
❑ Project Sign APPENDIX A
❑ Contact List ATTACHED ABOVE
❑ Site Plan(s) Showing: SEE SITE MAP SHEET
1. Disturbance Area: SEE SITE MAP SHEET
2. Revegetation Plan: NA
3. Construction Fencing:NA
4. Emergency Vehicle Access: SEE SITE MAP SHEET
S. Construction Parking: SEE SITE MAP SHEET
6. Staging Areas: SEE SITE MAP SHEET
7. Trailers, material storage, waste management, etc.
❑ Sequencing Schedule
❑ Traffic Control and Emergency Access Plan
❑ Fugitive Dust Control Plan