HomeMy WebLinkAboutFile Documents.743 Cemetery Ln.0011.2018 (40).ARBK CONSTRUCTION MANAGEMENT
PLAN
FOR
743-745 CEMETERY LANE
ASPEN, CO. 81611
LOTS 1 & 2 SAM'S CONDOMINIUMS
743 CEMETERY LANE PARCEL ID# 2735-126-122-001
745 CEMETERY LANE PARCEL ID# 2735-126-122-002
JANUARY 4, 2018
Prepared by: GRETCHEN GREENWOOD
ARCHITECT
TABLE OF CONTENTS
2.0 Project Introduction
2.1 Project Description
2.2 Project Disturbance Area
2.3 Project Vicinity Map
3.0 Project Documentation
3.1 Permitting
3.2 Public Notification
3.3 Project Sign
3.4 Contact List
4.0 Project Implementation
4.1 Dates of Construction
4.2 Hours of Construction
4.3 Construction Schedule
4.5 Project Fencing
4.6 Tree Protection
4.7 Parks
5.0 Project Management
5.1 Parking Management
5.2 Emergency Access and Ordinance 35
5.4 Staging Areas
6.0 Traffic Control
6.2 Haul Routes
6.3 Weight and Size Limitations of Vehicles
6.4 Delivery Requirements
6.5 Traffic Control Plan
8.0 Sediment and Erosion Control
8.1 Storm Water Pollution Prevention Plan
8.2 BMPs for Stormwater Pollution Prevention
8.3 Final Stabilization and Long-Term Stormwater Quality
8.4 Inspection and Maintenance Procedures
9.0 Fugitive Dust Control
9.1 Dust Control Plan
RECEIVED
01/11/2018
- 2 - ASPEN
BUILDING DEPARTMENT
10.0 Emissions
10.1 Maintenance
10.2 Opacity
11.0 Noise Suppression
11.0 General
11.1 Noise Suppression Plan
11.2 Equipment and Method
APPENDICES
A— Required Project Sign
B — Parking Management Form
C— Haul Route Map
D — Noise Suppression Plan, Techniques and Equipment
E — Construction Schedule
F — CMP Site Plan
G — Ordinance No. 35
H — Engine Idling
RECEIVED
O1/11/2018
_ 3 _ ASPEN
BUILDING DEPARTMENT
2.0 PROJECT INTRODUCTION
2.1 Project Descripti• .
Construction of a -w 4, 3 sf single family residence on a 5 5 sf lot located at the
south of 3rd Street. Ac ess for the residence is off the Alley. The new residence will have a
basement and two sto es above grade. There is o existing structures on
where the ew house will be constructed. The project also includes various site
improvements includin., grading, drainage, driveway, walkways, patio and landscapin•.
2.2 Project Disturbance Area
The area of disturbance is 4,000 square feet. Fill in blanks here.
2.3 Project Vicinity Map
See attached Appendix C — Project Vicinity and Haul Route Map
3.0 PROJECT DOCUMENTATION
3.1 Permitting
Fix dates for current
This CMP is being submitted as part of the application for a building permit. project.
3.2 Public Notification
Public notification will take place a minimum of 10 days prior to commencement of work and
will be distributed directly to neighbors within a 300 foot radius of the project. It will include an
invitation to a pre-construction meeting, a proposed schedule and description of impacts to the
neighborhood.
A preconstruction meeting summarii g this CMP will be held five days after the
aforementioned public notification (five . ys prior to breaking ground).
Work on the infrastructure is tentati - y scheduled to begin 07/15/14. The pre-construction
meeting is therefore tentatively schedul_d for 07/05/14 at 11:00am. Sam Barney, HCI Project
Manager, will act as the project represe tative and will notify all parties listed above.
3.3 Project Sign
743-745 PROJECT SIGN —APPEN► ,
RECEIVED
01/11/2018
- 4 - ASPEN
BUILDING DEPARTMENT
Who is the
3.4 Contact List contractor? There
are multiple
Owner: 743 C T contractors
O 745 C 777 C C mentioned in the
Contractor: TO E ETER IONE CMP
Site Supervisor: T
Safety Officer: T
Traffic Control Officer: Erosion Control T
Representative: T
City of Aspen Community Development— 970.920.5090
Pitkin County— 970.920.5200
Aspen Police Department— 970.920.5400
RFTA— 970.925.8484
School District— 970.925.3760
Water Department— 970.920.5110
Aspen Consolidated Waste— 970.925.3601
Holy Cross Electric: 970.945.5491 Fill in these blanks as
Aspen Valley Hospital —970.925.1120 well as others
Emergency Services - 911 throughout the CMP
4.0 PROJECT IMPLEMENTATION
4.1 Dates of Construction
The current project start is scheduled for 7/ 4/1 The estimated project duration is
months putting the projected completion date at around /1 . Any work within the City of
Aspen Right of Way will not commence prior to obtaining the appropriate permits from the City
of Aspen Engineering Department.
4.2 Hours of Construction
Construction hours will be limited to 7:30am — 5:30pm Monday through Friday and
9:00am-5:00pm on Saturday. All activities generating noise in excess of 70 decibels will require
a noise suppression plan and be restricted to operating between 9:00am — 5:00pm Monday
through Friday. Additional prohibited construction days are as follows:
• Sundays
• 4th of July (Day and any associated weekend)
• Memorial Day Weekend
• Labor Day Weekend
• Thanksgiving Day
• Christmas Day
RECEIVED
01/11/2018
- 5 - ASPEN
BUILDING DEPARTMENT
• New Years Day Fill in blanks
• Pro Challenge Bike Race
4.3 Construction Schedule
Please see attached —Appendix E
4.5 Project Fencing
The perimeter of the lot will be fenced with a tern orary tall
as indicated on the attached CMP site plan.
4.6 Tree Protection
The CMP Site Plan —Appendix F, shows the existing trees that are to be preserved and
where tree protection fencing will be installed. The fencing will be installed outside the drip
line of the trees and will be constructed of metal tee posts and orange plastic safety fence.
S T R P P What does this
mean?
5.1 Parking Management
See Parking Management Form - APPENDIX B
5.2 Emergency Access and Ordinance 35
HCI will maintain continuous emergency vehicle access to the site, including but not limited
to police, fire, and ambulance services.
See Ordinance 35 —APPENDIX G
5.4 Staging Areas
All material handling and equipment staging will be accommodated on site. Under no
circumstances will job materials be stored in the ROW. HCI will keep trash containers and
portable restrooms within the limits of the projects property.
RECEIVED
01/11/2018
- 6 - ASPEN
BUILDING DEPARTMENT
6.0 TRAFFIC CONTROL
6.2 Haul Routes
See Haul Route Map—APPENDIX C
6.3 Weight and Size Limitations of Vehicles
• Dump Trucks — 54,000 GVW
• Excavator— 54,000 GVW
• Boom Truck—45,000 GVW
6.4 Construction Vehicle Activity
There will be approximately 250 truck trips required. This will equate to approximately one
truck trip per day over the 16 month duration of the project. The expected numbers of truck
trips are as follows:
35 Loads of Demolition Debris
1 Load of Fencing and Tree Protection Materials
2 Loads of Pipe and Manholes for Drainage and Infrastructure
2 Construction Trailer Mobilization and Demobilization Trips.
1 Load of Drilling Equipment for Excavation Shoring
2 Excavation Equipment Mobilization
70 Dump Truck Loads of Excavated Soils Leaving Site
50 Dump Truck Loads of Backfill and Gravel Delivered to Site
15 Loads of Premixed Concrete
3 Concrete Pump Truck Trips
2 Loads of Stone Paving Materials
2 Loads of Structural Steel, Steel Stairs and Railings
1 Crane and Boom Truck Trip for Structural Steel
10 Loads of Framing and Exterior Trim Materials
2 Loads of Cabinets and Interior Trim Materials
1 Trip by Foam Insulation Truck
1 Load of Roofing Materials
1 Load of Windows and Exterior Doors
2 Loads of Drywall
1 Load of Appliances
1 Load of Heating and Air Conditioning Equipment
1 Load of Light Fixtures
2 Loads of Plant Materials
2 Loads of Other Landscaping Materials
20 Trash Truck Trips
20 Temp. Toilet CleaningTrips RECEIVED
01/11/2018
_ 7 _ ASPEN
BUILDING DEPARTMENT
Pickup and deliveries times will be coordinated so that only one large truck will be on site at
any given time. Delivery vehicles and all other on-site vehicles will not be allowed to idle for
more than five (5) minutes, with the exception of generators or PTO type operations. Project
subcontractor and suppliers will be provided with written notification of Aspen's vehicle idling
regulations.
See Section 13.08.110 Engine Idling —APPENDIX H.
6.5 Traffic Control Plan
Garvik does not anticipate that there will be any need to interfere with traffic on any public
right-of-way. If some unforeseen need arises, a Traffic Control Plan (TCP) will be prepared by
a State Certified Traffic Control Supervisor. The plan will conform to the most current edition of
the Manual of Uniform Traffic Control Devices for Streets and Highways (MUTCD) and be
submitted to the City of Aspen Department of Engineering for approval/permitting.
8.0 SEDIMENT AND EROSION CONTROL
8.1 Storm Water Pollution Prevention Plan
All necessary Best Management Practices (BMP's) will be in place and maintained in order
to minimize dirt entering the streets. Primary strategies are as follows:
• Avoid unnecessary site disturbance.
• Maintain grading; install silt fences and sediment traps prior to any soil disturbance.
• The installation of a tracking pad will be impractical due to the limited space
available. Hansen will make sure that the short ramp into the excavation is kept as
mud free as possible by use of screened rock over geo-textile fabric and not using
the ramp in wet conditions.
• The washout of concrete chutes will have to be done back into the concrete trucks
due to the lack of space on site. Hansen will do everything they can to make sure
that the concrete trucks do not wash out illegally offsite.
• Hard plastic kiddie pools will be used to protect the ground below the concrete pump
transfer points. Spills captured will be allowed to dry and will be placed in the site
trash receptacle.
• Pathways around the house will be stabilized primarily through the use of screened
rock over geo-textile fabric.
RECEIVED
01/11/2018
- 8 - ASPEN
BUILDING DEPARTMENT
8.2 BMPs for Stormwater Pollution Prevention
Best Management Practices (BMPs) will be employed for stormwater management as
indicated in the following sections. The construction sequence as indicated in 4.3 above will
help minimize the total area of disturbance at any particular point in time.
a) Structural Practices:
a. Silt fences will be installed on the downhill sides of all areas of disturbance as
shown on the civil engineers drainage and erosion control plans.
b. All open excavations will include the temporary development of a low point
with a sump/pump for the removal of stormwater. The sump inlet will be
protected with straw bales or a Dandy Bag type sediment filtration measure.
Clear sump effluent will be discharged where it will not cause further erosion
(to be determined based on construction phasing and available outlet areas
at that time).
c. Temporary diversion ditches and swales will direct runoff from other site
areas through straw wattle and hay bale filtration prior to discharge off the
site. The exact location and alignment of these structures will be determined
in the field based on project phasing and the space needed for construction
staging.
d. Fugitive dust control will be achieved using a hose and spray nozzle.
e. Surface roughening will be conducted in newly excavated areas to provide
temporary stabilization when other temporary stabilization measures are not
feasible (such as gravel or temporary vegetation) or will not be provided
immediately.
f. If for any reason construction is delayed for a period of time exceeding 30
days, more permanent stabilization will be put into place including backfilling
open excavations and reestablishing vegetation with seed and mulch.
b) Non-Structural Practices: Pollution prevention will be stressed among all employees
and sub-contractors, including adequate training of personnel and frequent
monitoring of activities.
a. Proper facilities and procedures will be used for on-site waste storage and
disposal. Daily inspection and maintenance of waste disposal areas will be
conducted. Where possible, waste containers will be covered, and waste
storage areas will be fenced.
b. The contractor will ensure that good housekeeping will be employed during
construction, with all work, materials storage and waste storage areas kept in
a neat and orderly condition.
c. Existing trees and mature vegetation that are not to be removed will be
protected during construction to limit unnecessary disturbance of site soils
and maintain natural erosion control.
c) Materials Handling:
a. All potentially hazardous materials will be stored off site. In the event that
any such materials are stored on site, toxic materials and petroleum products
01/11/2018
- 9 - ASPEN
BUILDING DEPARTMENT
will be enclosed and contained in an impervious elevated basin sized large
enough to hold the volume of the hazardous materials being contained.
b. Any spill or discharge or construction related materials will be cleaned up
immediately and disposed of accordingly.
c. Any spill not properly contained and cleaned-up will be reported to the proper
authorities.
i. Aspen Fire Department, Fire Marshal: 925-2690
ii. Colorado Department of Public Health and Environment, Emergency
Response: 303-756-4455.
iii. City of Aspen Engineering Department: 920-5080
iv. City of Aspen Environmental Health Department: 920-5039.
v. National Response Center: 800-424-8802
8.3 Final Stabilization and Long-Term Stormwater Quality
All temporary BMPs will remain in place until construction is complete and revegetation has
been verified to have taken hold. Final stabilization and long term stormwater quality are
addressed by the civil and landscape drawings submitted as part of the building permit submittal
package.
8.4 Inspection and Maintenance Procedures
a) A thorough inspection of the stormwater management system will be performed at
least every 14 days, and after any precipitation event that causes run off. The
inspection will include the observation of the construction site perimeter and
discharge points, all disturbed areas, and material storage areas exposed to
precipitation. All erosion and sediment control measures will be inspected for
integrity and functionality (e.g., sediment fences, hay bales, straw wattles, temporary
swales and ditches).
b) Damaged or ineffective BMPs will be fixed and/or replaced. Removed sediment will
be placed where it will not become an additional pollution source.
c) When necessary, BMPs will be added, removed or replaced with more effective
measures. All such actions will be documented and the SWMP will be updated to
reflect those changes.
9.0 FUGITIVE DUST CONTROL
9.1 Dust Control Plan
The project's Dust Prevention and Control Plan are as follows:
• Avoid unnecessary site disturbance.
• During construction a hose and spray nozzle will be used on exposed soils as necessary
to mitigate air born dust. RECEIVED
01/11/2018
- 10 - ASPEN
BUILDING DEPARTMENT
• Exported soils and other debris will be hauled off via covered dump trucks. All areas
directly surrounding the site will be maintained daily with thorough cleanings taking place
every Friday afternoon.
• 24 Hour Contact: T
10.0 EMISSIONS
10.1 Maintenance
All vehicles and equipment used on site will be properly maintained such that the engines
will function within the manufacture's standards or parameters.
10.2 Opacity
Emissions from diesel engines operated within the City of Aspen shall be of a shade or
density no darker than 40% opacity, except for starting motion no longer than 10 seconds or for
stationary operation not exceeding 10 seconds.
the noise limit at this
location is 70 db in
11 .0 NOISE SUPPRESSION the summer on
season (6/1-Labor
11.0 General Day), 80 db the rest
of the year.
The noise limit for construction is 80 decibels measured at the property line of the
construction site. All construction equipment shall be adequately muffled and maintained to
minimize project noise. The installation of noise barriers is the minimum technique to suppress
noise, especially when jack hammering of concrete occurs.
11.1 Noise Suppression Plan
All activity that generates noise in excess of 80 decibels requires a noise suppression plan
and is restricted to operating between the hours of 9am and 5pm Monday through Friday.
See Signed Noise Suppression Plan —APPENDIX D
11.2 Equipment and Methods
In addition to the standard practices agreed to within the signed Noise Suppression Plan,
the table below from the City of Aspen's complete packet has been included for quick
contractor/subcontractor reference.
RECEIVED
01/11/2018
- 11 - ASPEN
BUILDING DEPARTMENT
Noise Controls for Construction Equipment (Schneider et al., 1995)
Equipment Noise Controls
Pile Driver Enclosure, muffler
Stone saw cutting Noise control pad with water
Handheld impact drills Reduction of reflected sound
Circular saw blades 115°tooth angle, new tooth configuration, slotted saw blades,
viscoelastic damping
Pneumatic tools Muffler
Pavement breaker/ Muffler, enclosure of cylinder case and front head, moil damping
Rock drill
Portable air Muffler, acoustic enclosures
compressor
Bulldozer Bulldozer Cab-liner material, enclosure, sound absorption in
canopy, sealing of all openings
wheeled loader 'Absorption of sound cooling air route
RECEIVED
01/11/2018
- 12 - ASPEN
BUILDING DEPARTMENT
LL fak
This area is City trail 0\
and cannot be used
for staging or
deliveries. ilk
There are no trees on
tis site plan. Are
there any t ees on
site?
�1 I
CITY OF ASPEN
PERMIT SUBMISSION
743 CEMETERY LANE
PROPERTY LINE ID#2735-122-26-001
745 CEMETERY LANE
ID#2735-122-26-002
Aspen, Colorado 81611
\ 13- -
Lot 2 West Aspen Subdivision
L _kb I ARCHITECT
Gretchen Greenwood Architect
210 South Galena Street Suite 30
••• Aspen,CO.81611
•••
L.
0:970-925-4502 M:970-948-2081
\ 4 PARKING SPAdES WASTE MANAGEMENT 10 YARD ILUMPSTER ggreenwood@ggaaspen.com
1 AND 5 YD.REYCLING SURVEY WASTEENGINEER
HIGH COUNTRY ENGINEERING
210 South Galena Street
Aspen,CO.81611
b � 1-1 0:970-26-3816
�
H
aspen surveyors@gmail.com
it
I CIVIL ENGINEER
I I I 1 Mountain Cross Engineering
826 z Grand Ave.
w _" I I Glenwood Springs,CO.81601
z II 0:970-945-5544 F:970-945-5558
J -
Chris@mountaincross-eng.com
STRUCTURAL ENGINEEER
a I I� i I I Landon Anderson P.E.
0 I�' . d ---- MATERIAL STORAGE AREA 2)8'GATES FOR ACCESS I Anderson Structural Engineering
a L____T i I 1 448 Elk Run Road
/ I I New Castle,CO.81647
II 0:970-984-0320 M:970-355-4062
I 1 landon@anderson-engineering.com
ill
III MECHANICAL ENGINEER
M.Blaine Buck.
Bighorn Consulting Engineers
569 S.Westgate Dr.Suite#1
II
Grand Junction,CO.81505
II I I PORT A-POTTY 0:970-241-8709 F:970-241-9514
blaine@bighorneng.com
P -Li I I I LANDSCAPE ARCHITECT
`-. ,711
RCLA
Richard Camp Landscape Architecture B
tilliPO Box 958
/'
21 O 3 PARKING SPACES w O:970-963-7123
.�� I� L
0 Z JOB MANAGEMENT(AKA TRAI ER) richard.rcla@gmail.com
0_ Carbondale,CO.81625
a
OD COPY RIGHT:Gretchen Greenwood&Assoc,Inc.
ISSUE DATES
NORT1
PERMIT 1/10/2018 BLDG.PERMIT SUBMISSION
PROPERTY LINE /
NOISE MITIGATION LAYOUT
I
502 LINEAR FEET OF AT LEAST 12 FEET HIGH ACOUSTICAL BARRIER PANELS WITH A SOUND TRANSMISSION CLASS(STC)
RATING ON THE WEST,SOUTH,EAST ANDNORTH SIDES OF THE PROPOSED SITE WITH NO OPENINGS OR GAPS IN THE WALL.
If this project has soil WITH THE IMPLEMENTATION OF THE MITIGATION MEASURES OUTLINED HERE,THE NOISE LEVELS WILL COMPLY WITH THE LIMIT OF 70 d5A.
stabilization,a noise
suppression plan MITIGATION NOTES AND RECOMMENDATIONS REVISION DATES
prepared by a sound
engineer and a soil I.ALL EQUIPMENT SHOULD BE SWITCHED Oft WHEN NOT IN USE.
stabilization plan will
have to provided. 2.ALL EQUIPMENT SHOULD BE KEPT IN GOOD REPAIR WITH ALL WORN
LOOSE AND UNBALANCED MACHINE PARTS TO BE REPLACED.
3.EQUIPMENT SHOULD BE PLACED TO MAXIMIZE THE DISTANCE
BETWEEN THE NOISY EQUIPMENT AND THGE NEIGHBORING HOUSES.
4.'RESIDENTIAL"GRADE MUFFLERS SHOULD BE FITTED TO THE
EXHAUST OUTLETS OF ALL COMBUSTIBLE ENGINES.
5.WHERE POSSIBLE BROADBAND WHITE NOISE REVERSING ALARMS SHOULD BE
USED IN PLACE OF TONAL REVERSING ALARMS ON TRUCKS WITHIN THE CONSTRUCTION SITE.
G.CONSTRUCTION OPERATIONS ARE LIMITED TO THE HOURS OF 7:30 AM TO 5:30 PM SHEET TITLE
MONDAY THROUGH FRIDAY AND 9:00 AM TO 5:00 PM ON SATURDAY. CONSTGRUCION ON SUNDAY IS PROHIBITED.
WORK IS NOT ALLOWED ON HOLIDAYS.VERIFY WITH THE CITY OF ASPEN,
THE PRE HOLIDAY,hOLIDAY AND POST HOLIDAY WORKING RESTRICTIONS, CONS 0— CT ION MANAGEMENT SITE PLAN C MP S I Tf�ECEIVED
SHEET ID
Ca le: ,/811 = ,I-mII CMP PUN
NP 018
N
SHEET 1 OF MANY BUILDING DEPARTMENT
Appendix A
743 -745 DUPLEX
743-745 CEMETERY LANE
ASPEN, COLORADO 81611
BUILDING PERMIT #
CONSTRUCTION CONTACT:
TO BE DETERMINED
EMERGENCY PHONE #
24 HOUR EMERGENCY
CONTACT
TO BE DETERMINED
RECEIVED
01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 I Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W S IMF T SWS IMF T S
0 EP+ 20180710 273 days Mon Wed 1-
Preliminary 7/24/18 8/8/18
1 mi.
+ Site Work 12 days Mon 7/24/18 Tue 8/8/1: I-I
2 ® E; Clear and grub 5 days Mon Fri 7/28/18 Site excavation contractor
lot 7/24/18
3 EP; Install 2 days Mon Tue 8/1/19 Electric company
temporary 7/31/18
power service
4 EP4 Install 5 days Wed 8/2/19 Tue 8/8/18 " Electric contractor,Plumbing contractor
underground
utilities
5 EP4 Foundation 67 days Wed 8/9/18Thu 11/9/18 I I
6 Excavate for 10 days Wed 8/9/18 Tue I " Site excavation contractor
foundations 8/22/18
7 EP, Micropile 20 days Wed 8/9/18 Tue 9/5/18 -►
Shoring
8 EP+ Form 13 days Wed 9/6/18 Fri 9/22/18 " Concrete contractor
basement
9 EP, Place concrete 12 days Mon Tue " Concrete contractor
for 9/25/18 10/10/18
foundations &
10 Cure basement 7 days Wed Thu LI
walls for 7 10/11/18 10/19/18
11 •p•, Strip basement 2 days Fri Mon ig,C ncrete contra
wall forms 10/20/18 10/23/18
Task I= Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only L
Inactive Milestone Finish-only I RECEIVE[
Page 1 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W 1 S I T M F I T 1 S W S T M F T I S
12 EP} Waterproof/ins 4 days Tue Fri '_,Concrete coni
basement 10/24/18 10/27/18
13 EP-0 Perform 1 day Mon Mon Inspector
foundation 10/30/18 10/30/18
inspection
14 me; Backfill 8 days Tue Thu ' Site ex
foundation 10/31/18 11/9/18
15 fr Steel 20 days Fri 11/3/18 Thu
16 EP; Install Steel 15 days 11/30/18 Fri 11/10/18
17 fr Framing 60 days Thu 11/30/18 Fri r
18 EP, Install 1st floor 7 days Fri 12/1/18 Mon
joists 12/11/18
19 EP, Lay 1st floor 2 days Tue Wed
decking 12/12/18 12/13/18
20 EP+ Frame 1st floor 10 days Thu Wed
walls 12/14/18 12/27/18
21 EPy Frame 1st floor 3 days Thu Mon 1/1/18
corners 12/28/18
22 EPy Install 2nd 7 days Tue 1/2/19 Wed
floor joists 1/10/19
23 op
-• Frame 2nd 2 days Thu Fri 1/12/19
floor decking 1/11/19
24 Frame 2nd 10 days Mon Fri 1/26/19
floor walls 1/15/19
Task Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only L
Inactive Milestone Finish-only I RECEIVED
Page 2 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W I SIT M F I T IS WIS T , M F T S
25 EP4 Frame 2nd 3 days Mon Wed
floor corners 1/29/19 1/31/19
26 EP} Complete roof 10 days Thu 2/1/19 Wed
framing 2/14/19
27 or
+ Conduct 1 day Thu Thu
framing 2/15/19 2/15/19
28 X Dry In 38 days Fri 2/9/19 Tue 4/3/19
29 �4 Install 1st floor 4 days Fri 2/16/19 Wed
sheathing 2/21/19
30 me} Install 2nd 4 days Thu Tue
floor sheathing 2/22/19 2/27/19
31 NI.} Install roof 3 days Wed Fri 3/2/18
decking 2/28/19
32 me} Install felt, 10 days Mon 3/5/18 Fri 3/16/19
flashing and
shingles
33 or Hang 1st floor 4 days Mon Thu
exterior doors 3/19/19 3/22/19
34 N. Install 1st floor 4 days Fri 3/23/19 Wed
windows 3/28/19
35 NI.
+ Install 2nd 4 days Thu Tue 4/3/19
floor windows 3/29/19
36 NI.; Exterior Finishes 15 days Wed 4/4/19 Tue 4/24/19
37 NP+ Complete 15 days Wed 4/4/19 Tue +
exterior siding 4/24/19
Task Ili. Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only L Inactive Milestone Finish-only ] RECEIVE[
Page 3 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'17 Oct 22,'18 Nov
0 Mode W S T M F I T IS W S T , M F T S
38 Utility 41 days Wed Wed
Rough-B97Ins 3/28/19 5/23/18
and Complete
39 Mr
+ Rough-in 30 days Wed 4/4/19 Tue
plumbing 5/15/19
40 Ni•+ Conduct 1 day Wed Wed
rough-in 5/16/19 5/16/19
plumbing
inspection
41 mr. Place concrete 5 days Thu Wed
for basement 5/17/19 5/23/19
floor
42 # �4. Rough-in 30 days Wed Tue 5/8/19
electrical 3/28/19
43 �� Conduct 1 day Wed 5/9/18 Wed 5/9/19
rough-in
electrical
inspection
44 ® Oro Rough-in HVAC 25 days Wed 3/28/19 Tue 5/1/19
45 EPy Conduct 1 day Wed 5/2/19 Wed 5/2/19
rough-in HVAC
inspection
46 # EPy Rough-in 2 days Wed Thu
communicatior 3/28/19 3/29/19
-phone, cable,
computer,
Task UM Inactive Summary External Tasks
Split ,,,,,,,,,,,,,,111, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary 11 Manual Summary Rollup Progress
Project Summary Manual Summary ii Manual Progress
Inactive Task Start-only (_Inactive Milestone Finish-only I RECEIVE[
Page 4 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'17 Jul 30,'17 Aug 27,'17 Sep 24,'17 Oct 22,'17 Nov
0 Mode W 1 S I T M F I T 1 S W S T M F T S
47 EP4 Rough in fire 10 days Wed Tue
suppresion 3/28/19 4/10/19
48 lip} Interior Finishes 68 days Wed 4/25/1 Fri 7/27/18
49 * Insulation 11 days Thu 5/10/1EThu 5/24/1E
50 or. Place wall 1 day Thu Thu
insulation - 5/10/19 5/10/19
1st floor
51 •1-
4 Place wall 1 day Fri 5/11/19 Fri 5/11/19
insulation -
2nd floor
52 MP
4 Place ceiling 1 day Mon Mon
insulation - 5/14/19 5/14/19
2nd floor
53 or. Conduct 1 day Tue Tue
insulation 5/15/19 5/15/19
inspection
54 Drywall 28 days Wed 5/16/19 Fri 6/22/1•
55 or. Install 2 days Wed Thu
drywall - 1st 5/16/19 5/17/19
floor walls
56 EPy Install 2 days Fri 5/18/19 Mon
drywall - 1st 5/21/19
floor
Task UM Inactive Summary External Tasks
Split ,,,,,,,,,,,,,,, , Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only (_Inactive Milestone Finish-only I RECEIVE[
Page 5 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W I SIT M F I T IS WIS T , M F T S
57 9 EP4 Install 2 days Tue Wed
drywall 2nd 5/22/19 5/23/19
floor walls
58 9 EP+ Install 2 days Thu Fri 5/25/19
drywall 2nd 5/24/19
floor
59 9 Er, Tape and 4 days Tue Fri 5/25/19
float 1st 5/22/19
floor drywall
60 rA Er, Tape and 4 days Tue Fri 5/25/19
float 2nd 5/22/19
floor drywall
61 A' Paint and 15 days Mon Fri 6/15/19
Wallpaper 5/28/19
62 MP
4 Texture all - 5 days Mon Fri 6/1/19
1st floor 5/28/19
63 1110 MP
4 Paint all - 5 days Mon 6/4/19 Fri 6/8/19
1st floor
64 MP
4 Texture all - 5 days Mon 6/4/19 Fri 6/8/19
2nd floor
65 sr; Paint all - 5 days Mon Fri 6/15/19
2nd floor 6/11/19
66 Paint 5 days Wed Tue 5/1/19
exterior 4/25/19
siding &
67 Cabinets 22 days Tue 6/5/19 Thu 7/5/19
Task UM Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only (_Inactive Milestone Finish-only I RECEIVE[
Page 6 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W I SIT M F I T IS WIS T , M F T S
68 EP4 Install 1st 5 days Wed 6/6/19 Tue
floor- 6/12/19
kitchen
69 al EP+ Install 1st 4 days Mon Thu
4 floor- 6/11/19 6/14/19
master bath
and guest
cabinets
70 or. Install 2nd 4 days Fri 6/15/19 Wed
floor- hall 6/20/19
bath and
private bath
cabinets
71 or. Install chair 10 days Thu Wed 7/4/19
rails, crown 6/21/19
moldings,
trim
72 Finish Plumbin 10 days Mon 6/18/19 Fri 6/29/19
73 Complete 7 days Mon Tue
1st Floor 6/18/19 6/26/19
74 Complete 7 days Wed Thu 7/5/19
2nd Floor 6/27/19
75 EP, Complete 7 days Fri 7/6/19 Mon
Basement 7/16/19
Task UM Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only (_Inactive Milestone Finish-only I RECEIVE[
Page 7 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W I SIT M F I T IS WIS T , M F T S
76 Ir4 Conduct 1 day Tue Tue
finish 7/17/19 7/17/19
plumbing
inspection
77 * Finish Electrica 15 days Mon 6/18/19 Fri 7/6/19
78 Complete 4 days Tue Fri 7/20/19
1st floor 7/17/19
circuits to
service
79 or. Complete 4 days Mon Thu
2nd floor 7/23/19 7/26/19
circuits to
service
80 Er. Conduct 1 day Fri 7/27/19 Fri 7/27/19
finish
electrical
inspection
81 ® Er, Complete 2 days Mon Tue
communicati 6/18/19 6/19/19
wiring -
phone,
cable,
82 Finish HVAC 5 days Mon 6/18/19 Fri 6/22/19
83 ® Complete 2 days Mon Tue
1st floor- 6/18/19 6/19/19
zone 1
Task UM Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only (_Inactive Milestone Finish-only I RECEIVE[
Page 8 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 Jul 30,'18 Aug 27,'18 Sep 24,'18 Oct 22,'18 Nov
0 Mode W I SIT M F I T IS WIS T , M F T S
84 or.
4 Complete 2 days Wed Thu
2nd floor- 6/20/19 6/21/19
zone 2
85 INP.+ Conduct 1 day Fri 6/22/19 Fri 6/22/19
HVAC
inspection
86 Carpet,Tile 30 days Mon Fri 7/6/19
and 5/28/19
87 ni of, Tile entry, 25 days Mon Fri 6/29/19
kitchen and 5/28/19
baths
88 or. Carpet 1st 2 days Mon 7/2/19 Tue 7/3/19
floor
89 or
+ Carpet 2nd 2 days Wed 7/4/19 Thu 7/5/19
floor
90 or
+ Install 1 day Fri 7/6/19 Fri 7/6/19
appliances
91 Landscaping and 58 days Wed Fri 7/6/18
Grounds Work 4/18/19
92 ni Er, Pour concrete 4 days Wed Mon
driveway and 4/18/19 4/23/19
sidewalks
93 or. Install 4 days Tue Fri 4/27/19
backyard fence 4/24/19
Task UM Inactive Summary External Tasks
Split ,1,,1,,1,,1,1 1 1 1 1, Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date:10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only L Inactive Milestone Finish-only I RECEIVE[
Page 9 01/11/2018
ASPEN
BUILDING DEPARTMENT
ID Task Task Name Duration Start Finish Jul 2,'18 1 Jul 30,'18 l Aug 27, 18 Sep 24,'18 Oct 22,'18 1 Nov
0 Mode W S IMF T SWS TMF T S
94 n •e* Sod and 4 days Mon 5/7/19 Thu
complete 5/10/19
plantings-
front yard
95 or
+ Sod and 4 days Fri 5/11/19 Wed
complete 5/16/19
plantings-
backyard ,
96 EP4 Final Acceptance 8 days Mon 7/30/19 Wed 8/8/19
97 MP
4 Complete final 1 day Mon Mon
inspection for 7/30/19 7/30/19
certificate of
occupancy
98 or. Cleanup for 1 day Tue Tue
occupancy 7/31/19 7/31/18
99 EPy Perform final 1 day Wed 8/1/19 Wed 8/1/19
walk-through
inspection
100 Er. Complete 5 days Thu 8/2/19 Wed 8/8/19
punch list
Task UM Inactive Summary External Tasks
Split Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary 11 Manual Summary Rollup Progress
Project Summary Manual Summary li Manual Progress
Inactive Task Start-only Inactive Milestone Finish-only RECEIVE[
Page 10 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 1 Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 I Apr 8,'19 May 6,'19 I Jun 3,'19 Jul 1,'19 I Jul 29,'19 I Aug 26,'19
S W S 1 T M F T S W I S 1 T M I F T 15 W 1 5 I T I M I F I T I S W I S T I M F I T
i
ctor
contractor
Task NM Inactive Summary r —I External Tasks
Split ,.„.„.„.„.„„ Manual Task External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 11 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 Apr 8,'19 May 6,'19 Jun 3,'19 Jul 1,'19 I Jul 29,'19 Aug 26,'19
S W S T M F T S W S T M F T S WSITIMIFIT IS W I S T M F I T
e contractor
tor
ite excavation contractor
*-1—
i1
Framing contractor
1 Framing contractor
Framing contractor
Framing contractor
_ Framing contractor
Framing contractor
_Framing contractor
Task UM Inactive Summary External Tasks
Split , , Manual Task I I External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary ii Manual Progress
Inactive Task Start-only i_
Inactive Milestone Finish-only I RECEIVE[
Page 12 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 1 Dec 17,'18 Jan 14,'19 I Feb 11,'19 Mar 11,'19 I Apr 8,'19 May 6,'19 I Jun 3,'19 Jul 1,'19 I Jul 29,'18 I Aug 26,'19
S W S 1 T M I F T I 5 I W I S 1 T M I F T I 5 W 1 5 I T I M I F I T I S W I S T I M F I T
Framing contractor
Framing contractor
j Inspector
I
Framing contractor
Framing tor
ctor
Roofing contractor
Framing contractor
Framing contracto
LFramin. . I . . or
r 1
11._ Framing contractor
Task iiiiM Inactive Summary External Tasks
Split ,,,,,,,,,,,,,,,,,, Manual Task . Illi External Milestone
Milestone ♦ Duration-only Deadline ♦
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 13 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 I Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 IApr8,'19 May 6,'19 Jun3,'19 Jul1,'19 I Jul 29 '19 IAug26,'19 I
S W S I T M F T S W S I T M I F T I S W 1 S T M F T I S W I S ' T I M F I T
J
Trmiu Plumbing contractor
Inspector
, - - I .
Electric contractor
j Inspector
Keating and AC contractor
Inspector
j Electric contractor
Task llllllM Inactive Summary External Tasks
Split ,,,,,,,,,,,,,,,,,, Manual Task External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 14 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 I Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 I Apr 8,'19 May 6,'19 Jun 3,'19 Jul 1,'19 I Jul 29,'19 I Aug 26,'19 I
S W S I T M F T S W S I T M I F T 15 W I S T M F I T I S W I S T I M F I T I
I
W-
T Insulation contractor
rInsulation contractor
F Insulation contractor
j Incpec+or
—I
1 Drywall contractor
Drywall contractor
Task NM Inactive Summary External Tasks
Split ,.„.„.„.„.„„ Manual Task External Milestone
Milestone ♦ Duration-only Deadline ♦
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary —1 Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 15 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 I Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 IApr8,'19 May 6,'1 1IJun3,'19 Jul 1,'19 IJul29,'19 IAug26,'19 I
S W SIT M F T S W SIT M I F T I S W I 5 TIMIF IT I S W I S T I M F IT
Drywall co tractor
r. Drywall c ntractor
Drywall c ntractor
a Drywall c ntractor
■ ` 1
Painti g contractor
ii Painting contract r
"Painting contract r
T. Painting cont actor
i Painting contractor
I
Task 1 NM Inactive Summary r —I External Tasks
Split ,,„,„,„,„,„„ Manual Task External Milestone
Milestone ♦ Duration-only Deadline f
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [ r
Inactive Milestone Finish-only ] RECEIVED
Page 16 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 I Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 I Apr 8,'19 May 6,'19 I Jun 3,'19 Jul 1,'19 I Jul 29,'19 I Aug 26,'19 I
S W S I T M F T S W S I T M I F T I s W I S T I M I F I T I S W I S T I M F I T
_Finish carpentry contractor
• Finish carpentry contractor
i Finish carpentry contractor
imm Finish carppnt contractor
I-'
" Plumbing contract r
" Pluribing contractor
Toni Plumbing contractor
Task NM Inactive Summary r —I External Tasks
Split ..,,,,,,,,,,,,,,,, Manual Task External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [ r
Inactive Milestone Finish-only ] RECEIVED
Page 17 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 1 Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 IApr8,'19 May 6,'19 IJun3,'19 Jul 1,'19 IJul29,'19 IAug26,'19
S W S 1 T M F T S W S 1 T M I F T 15 W 1 5 I T I M I F I T I S 1 W I S T I M F I T
Inspector
1
Electric contractor
Electric contractor
T Inspector
Electric contractor
Heating and AC contractor
Task NM Inactive Summary r —I External Tasks
Split ,.„.„.„.„.„„ Manual Task External Milestone
Milestone ♦ Duration-only Deadline t
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 18 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 1 Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 I Apr 8,'19 May 6,'19 I Jun 3,'19 Jul 1,'198 I Jul 29,'19 I Aug 26,'19
S W S 1 T M F T S W S 1 T M I F T 15 W 1 5 I T I M I F I T I S W I S T I M F I T
11 Heating and AC contractor
1 Inspector
Flooring contractor
Flooring contractor
1 Flooring contractor
j Applianrp_contractor
Concrete contractor
rI_Fencing contractor
Task NM Inactive Summary -I External Tasks MP
Split ,,„,„,„,„,„„ Manual Task External Milestone e
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 19 01/11/2018
ASPEN
BUILDING DEPARTMENT
Nov 19,'18 1 Dec 17,'18 Jan 14,'19 Feb 11,'19 Mar 11,'19 I Apr 8,'19 May 6,'19 I Jun 3,'19 Jul 1,'19 I Jul 29,'19 I Aug 26,'19
S W S 1 T M F T S W S 1 T M I F T 15 W I S I T I M I F I T I S W I S T I M F I T
TEir
Landscape contractor
Landscape contractor
Inspector
"Maid service
1 Owner
General contractor
Task NM Inactive Summary r —I External Tasks
Split ,.„.„.„.„.„„ Manual Task External Milestone
Milestone ♦ Duration-only Deadline
Project: 20180710 Preliminary
Date: 10/10/17 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only [Inactive Milestone Finish-only ] RECEIVED
Page 20 01/11/2018
ASPEN
BUILDING DEPARTMENT
•
•
ORRDNANCE NO..35 `
(SERIES OF 2002)
AN EMERGENCY ORDINANCE OF int MY COUNCIL Ole rat CITY OF
ASPEN,COLORADO,TO AMEND SECTION 1 L04 OF TIE'MUNICI PAL CODE
• OF THE CITY OF,ASPEN--14RE PREVENTION AND PROTECTION.AND TO -
AMEND SECTION 24.16'OF THE MU] ICC1'AL CODE 0 'THE CITY OF
ASPEN—RESIDENTIAL MIMING NG PERMIT S 'STEM'FOR THE PURPOSE OF
IMPLEMENTING NEW REGULATIONS ENSU}UNG THE SAFETY OF
CONSTRUCTION SITES.
WHEREAS;'the City Council of the City of Aspen directed the Community
Development Director and the Chief Building Official of the Community Development.
• Department to propose arnendrnents to the Municipal Code to improve fire protection for
construction sites and improve emergency access and parking for construction sites;and,
WHEREAS, the amendments requested relate to SeetiO '11'.04.030, Fire
Prevention and Protection - Amendments, and to Section-24.16, Residential Parking
. • Permit System,of the Aspen Municipal Code;arid,
WHEREAS, pursuant to Section 1.04.060,-amendments to the Municipal Code
• • may be approved by City Council by adoption of an Ordinance;and,
'WHEREAS,.the Chief Building Official,'the Community Development Director,
• • . and the Aspen Fire Marshal recommend adoption of the amendments,as described herein,
• to the afore mentioned sections for the purpose of protecting'tlre public health, welfare,
•and safety;and, •
WHEREAS, City Council review.ed and considered the recommendations of the Chief •
Building_Official, the Community Development'Director; the Aspen Fire Marshal, and
members ofthe public duringa duly noticed public hearing;and, •
WHEREAS, the City Council finds that the amendments, as hereinafter described,
meet or exceed all applicable standards and that the approval is consistent with the goals and -
e_lenxents of the Aspen Area.Community Plnri;and;
WHEREAS,the City Council finds that this Ordinance furthers and is necessary for
the promotion of public health, safety, and welfare and•should be adopted as an Emergency '
• • - Ordinance pursuant to Section 4.11 ofthe City Charter.
NOW, THEREFORE BE rr ORDAINED BY THE.CITY COUNCIL OF THE QV:
OF ASPEN,COLORADO,THAT: '
Section 1: •
Section 24.16 of the Municipal Code of the City of Aspen, Colorado, which section - -
defines, describes, authorizes;and`regulates the on-street parking permit program within •
the City of Aspen shall hereby be amended by adding a section related to requirements fox
construction staging areas, construction parking areas, and emergency access areas for
construction sites within the City of Aspen which said-section shall read as follows:
•
•
• • Ordinance No.35, Series of 2002 • -
. Page l' .
• 01/11/2018
•
ASPEN
BUILDING DEPARTMENT
•
24./6.240 Construction Staging Area, Parking, and Emergency Vehicle
Access Management Plan
To ensure proper public health, welfare, and safety, the City of Aspen requires
approval of job site plans describing construction staging area(s), locators and
• numberr of construction-related vehicles, and ensuring proper emergency venic'le
arress for construction projects within the City of Aspen. These plans are required
for all residential construction or remodeiing-of 1,500 square feet,or more, for any
construction or remodeling involving multi-family buildings (three Or more writs),
or for any construction or remodeling involving commercial buildings. All other
construction activity shall be considered exempt from these provisions.
The construction project shall be issued street parking permits for the expected
duration of the project for a fee. Parking permits issued, Pursuant to an approved
Construction Staging Area, Parking, and Emergency Vehicle Access Management
Plan, shall permit the all-day on-street parking of construction related vehicles
within the specified construction parking area for the duration. f the construction
project. Construction vehicles parked outside of the approved area or after the
spec-illed construction duration shall,be considered in violation.
The Chef Building Official shall require submission of a Construction Staging
Area, Parking,and Emergency Vehicle Access Management Plan with submission
of building permit documents. A building permit shall not be issued until such plan
has been reviewed and approved by the Chief Budding-Official,
All construction staging and construction parking shall be cortfined to the areas-
de;ned in the approved plan for the job site_ Workers shall, be encouraged to
carpool. Emergency access, as described•in the approved plan for the job site,
shall at no time be blocked. A stop work order may be issued upon non •
-
compliance. .
Section 2:
Section 11.04.030 of the Municipal Code of the City of Aspen, Colorado, which
• Section defines, describes,'and authorizes the regulations for fire prevention and
protection within the City of Aspen shall hereby-be amended'by adding a Seddon
related to requirements for construction projects within the City of Aspen and the
use of temporary heating systems which said section shall rear].as follows:
(ii) The following shall be added to Section 8263.2.1.2:
To ensure proper public health,welfare, and safety,the City of Aspen.requires any•
construction site using fuels to generate temporary heat for the purpose of •
conditioning space during the process of construction shall be equipped with:
I.. Signaling devices capable of detecting dangerous levels of heat andfor
smoke and capable of notifying a qualified party with responsibility to
monitor the site and respond to the alarm and take appropriate actions;
RECEIVED
Ordinance No. 35, Series o12002
Paget 01/1.1/2018
ASPEN
BUILDING DEPARTMENT
2. As an alternate, an approved fire Watch plan and schedule may be
substituted for the alarm requirement;
3. Associated supply lines shall be protected from flame or heat
ixnpingernent resulting in failure of the appliance or supply hoses
resulting in free flow of volatile fuel into the atmosphere and/or fire
situation;
4. A free flow shut-off value shall be required on all propane tanks
supplying temporary heat systems;or,
5. Any other plan acceptable to the Fire Marshal.
Prior to the installation of any temporary heating device(s), the system equipment
. check list, prepared and maintained by the Fire Marshal, shall be submitted and
approved by the Fire Marshal's Office. It shall be the responsibility of the
contractor to notify the Fire Marshal prior to the activation of any temporary
heating device.
The principal contractor, or home owner-builder shall submit a statement
acknowledging and agreeing to the terms of this section with submission of
building permit documents. A stop work order may be issued upon non-
compliance with provisions of this section.
(jj) Section 16 of the Appendix II-A of the Uniform'Fire Code is amended as
follows:
•
Section 3:
This Ordinance is adopted as an emergency ordinance,pursuant to Section 4.11of the
City Charter, and shall be effective November 1, 2002 and apply to all currently
permitted and active construction projects-within the City of Aspen thereafter.
$ectiog 4:
This Ordinance shall not affect any existing litigation and shall not operate as an
abatement of any action Or proceeding' now pending under or by virtue of the
ordinances repealed or anzehded as herein provided, and the same shall be conducted
and concluded under such prior ordinances. -
Section 5:
If any section, subsection, sentence,clause, phrase, or portion of this Ordinance is for
any reason held invalid or unconstitu#ozFal in a court of competent jurisdiction, such
• portion shall be deemed a separate, distinct and'lade-Pendent provision and shall not
affect the validity of the remaining portions thereof
Section 6:
A public hearing on the Ordinance shall be held on the 15th day of October,2002,at .
5:00 p.m.in the City Council Chambers,Aspen City Hall, Aspen'Colorado,fifteen(15)
days prior to which hearing a public notice of the same was published in a newspaper of
general circulation within the City of Aspen.
Ordinance No. 35, Series of 2002 RECEIVED
Page3
01/11/2018
•
ASPEN
•
BUILDING DEPARTMENT
INTRODUCED,READ AND OR,,DERED PUI3LISI1ED as provided.by law,
by the City Council ofthe City of Aspen on the 23r`1 day of Septem ,2002,
Attest:
. • r ,
Kathryn S oeh, ivy Clerk elan K.Klan d, or
FrV1ALLY,adopted,passed and approved this-15"day of'T) 124(2002_
Attest;
. Kathryn ` oeh,City Clerk Helen K.K
Approved as to form
tty ftornegy
•
•
•
•
•
•
•
a • RECEIVED
rdinance No 35,Series of 2002 •
•
'age4 •
01/11/2018
•
ASPEN
BUILDING DEPARTMENT
APPENDIX H SECTION 13.08.110 ENGINE IDLING
(a) Except as hereinafter provided, shall be unlawful for any person to idle or permit
the idling of the motor of any stationary motor vehicle for a prolonged or
unreasonable period of time determined herein to be five (5) minutes or more
within any one(1) hour period of time.
(b) This section shall not apply when an engine must be operated in the idle mode for
safety reasons including, but not limited to, the operation of cranes and fork lifts
used in the construction industry.
(c) The time required by a diesel powered motor vehicle with a gross weight rating of
ten thousand (10,000) pounds or more while operating in a stationary position to
achieve a temperature of one hundred twenty(120) degrees Fahrenheit and an air
pressure of one hundred (100) pounds per square inch, shall not be included in
the computation of the five (5) minutes determined herein to be a prolonged or
unreasonable period of time. The temperature and air pressure as indicated on the
vehicle's gauges may be used for determining the diesel engine's temperature and
air pressure.
(d) The time during which transportation vehicles are actively loading or discharging
passengers shall not be included in the computation of the five (5) minutes
determined herein to be a prolonged or unreasonable period of time. A
transportation vehicle shall be defined for purposes of this section to mean motor
vehicles designed to transport a minimum of sixteen (16) persons. (Ord. No 74-
1992, § 1: Code 1971, § 11-2.70)
RECEIVED
01/11/2018
ASPEN
BUILDING DEPARTMENT
Ci y of Aspen
Construction Noise Suppression dean
As the General Contractor for this construction project, I/1't Ala/7e hereby agree
to the follo restrictions and will provide the necessary noise suppression (outlined below),
such th "it wil lesson the impact to the properties within 300 feet of the project located at
7 ` 7 CCAvF - . I understand that if any construction activities exceed
80 cibels an are covered by this document I will contact the City of Aspen Environmental
F19,alth Dep en o design a specific noise suppression plan for th se activities.,
e
Signature C, Print name
On-site Contact Phone# -t D 30 ?33
Many activities on construction sites are noisy. Although some noise may be unavoidable, it can
often be controlled using improved work practices. Builders should make all reasonable efforts
to minimize noise. Noise Suppression plans are required for all construction projects where
activities will generate noise that exceeds 80 decibels. Section 18.04.050(A)(2)(d)
Hours of operation
All construction activity is limited to the following days and times:
Monday thru Friday Saturday Sunday
7:30 am to 5:30 pm 9:00 am to 5:00 pm No construction work is allowed
Constructions activities producing noise greater than 80 decibels are limited to the following
days and times:
Monday thru Friday
9:00 am to 5:00 pm
Work that is over 80 decibels which by law requires a noise suppression plan will not be allowed
for Saturday work that includes but not limited to the use of compressors, generators,
jackhammers, power equipment, nail guns, drilling machinery, earth moving equipment and
similar loud construction activities. This does not restrict quiet work inside and outside that does
not require a power source, including a battery, on Saturday.
Construction activity is not allowed during all federal holidays.
Due to the congestion in Aspen when town is completely full, noise suppression plans will not
be approved for the following dates: Christmas Week (December 25 through Jan. 1), Food
and Wine Week in June (Friday thru Sunday), 4th of.holy day and/or weekend if it falls on
a Friday or Monday, and Labor Day weekend.
RECEIVED
Revised 01/09/2013 01/11/2 018
ASPEN
BUILDING DEPARTMENT
Specific noise suppression requirements for all activities exceeding
80 decibels at a construction site include:
1. Notify neighbors within two hundred fifty (300)feet of the project informing them of
the kinds of equipment, expected noise levels and durations of loud work. Including
the variation of noise levels during a typical construction days may be helpful. Such
notification must be in writing and be done seven (7) days prior to the starting time of
the project. Communication with neighbors can prevent complaints from arising, and
resolve concerns before there is a problem. Provide a phone number where the
foreman can be reached prior to the start of the job.
2. Operate equipment in accordance with manufacturer's specifications and with all
standard manufacturers' mufflers and noise-reducing equipment in use and in
properly operating condition.
3. Post notices to inform workers, including sub-contractors, about the basic noise
requirements, as well as specific noise restrictions, to the project.
4. Install noise barriers around all equipment/activities specified in
Table 1: TYPICAL CONSTRUCTION EQUIPMENT REQUIRING NOISE
SUPPRESSION. Noise barriers not only significantly reduce construction noise, but
they also provide an extra benefit of"hiding" the noise producing sources, thus
increasing a neighbor's tolerance. (See also the attached list of noise blocking
methods for details on approved noise barriers.)
5. Move portable loud equipment including generators, compressors, and cement
mixers to different sides of the property to reduce impacts on individual neighbors.
What can you do about construction noise?
• The use of radios on the site before 8:00 am are not allowed: remind laborers and sub-
contractors.
• Noise suppression plans will not allow noisy machines such as brick cutters or
jackhammers to be operated before 9.00 am.
• Noisy equipment such as cement mixers should be placed on the site to maximize the
distance from neighboring houses and/or rotate location so as to not impact just one
neighbor. Noise levels drop quickly with distance from the source.
• All equipment should be properly maintained, with special attention to mufflers and other
noise control devices.
• Between work periods, builders are required by city ordinance to shut down machines
such as backhoes, bobcats, loaders and generators.
• When dropping materials from a height—for example, into or out of a truck, or when
loading or unloading scaffolding, noise suppression plans require a chute or side baffles.
• All vehicular movements to and from the site must only be made during the scheduled
normal working hours. This includes off-site noise that is associated with a specific
project such as staging of concrete trucks.
RECEIVED
Revised 01/09/2013 01/11/2 018
ASPEN
BUILDING DEPARTMENT
TABLE 1: NOISE CONSTRUCTION EQUIPMENT REQUIRING NOISE
SUPPRESSION PLANS
Equipment Category
Auger Drill Rig
Backhoe
Chain Saw
Clam Shovel
Compressor(air)
Concrete Mixer
Concrete Pump
Concrete Saw
Crane (mobile or stationary)
Dozer
Drill Rig
Excavator
Front End Loader
Generator(more than 25 KVA)
Gradall
Grader
Horizontal Hydraulic Boring Jack
Impact Pile Driver(diesel or drop)
Impact Wrench
Jackhammer*
Mounted Impact Hammer(hoe ram)
Paver
Pneumatic Tools
Rock Drill
Scraper
Scarifier
Slurry Machine
Vibratory Pile Driver
RECEIVED
Revised O1/09/2013 01/11/2 018
ASPEN
BUILDING DEPARTMENT
Noise Blocking Methods
Contractors shall require all subcontractors and vendors to use:
• Quieter vs. Louder equipment
• "Residential" grade combustion engine exhaust silencers
• Electrical vs. pneumatic hand power tools: All pneumatic tools operated in the City of
Aspen must be fitted with an effective silencer on their air exhaust port.
• Hydraulic vs. air powered rock drills
• "Silenced"pile drivers vs. Diesel pile drivers
In general, noise reduction equipment and materials may include, but not be limited to:
1. Shields, shrouds, or intake and exhaust mufflers.
2. Noise-deadening material to line hoppers, conveyor transfer points, storage bins,
or chutes.
3. Noise barriers using materials consistent with the Temporary Noise Barrier
Materials Section.
4. Noise curtains
5. Plywood with concrete blankets at the height of the equipment and that it
surrounds the activity such that it directs noise up more than out from the
property.
6. Portable three sided enclosures made out of plywood to move with the activity
such as jack hammering.
7. Internal combustion engines are to be fitted with a suitable muffler in good repair.
Specific Equipment:
Generators: The local power grid shall be used wherever feasible to limit generator noise. No
generators larger than 25 KVA shall be used and, where a generator is necessary, it
shall have maximum noise muffling capability.
Backup Alarms: All equipment with backup alarms operated by the Contractor, vendors,
suppliers, and subcontractors on the construction site shall be equipped with
either audible self-adjusting ambient-sensitive backup alarms or manually-
adjustable alarms. The ambient-sensitive alarms shall automatically adjust to a
maximum of 5 dBA over the surrounding background noise levels. The
manually-adjustable alarms shall be set at the lowest setting required to be
audible above the surrounding noise. Installation and use of the alarms shall be
consistent with the performance requirements of the current revisions of Society
of Automotive Engineering (SAE)J994, J1446, and OSHA regulations.
Compressors: The unit with the lowest noise rating which meets the requirements of the job
should be used where work is conducted in the City of Aspen, installed with
mufflers and/or enclosed in a noise barrier.
RECEIVED
Revised O 1/09/2013 O 1/11/2 O 18
ASPEN
BUILDING DEPARTMENT
Jackhammer: All jackhammers and pavement breakers used on the construction site shall have
exhaust systems and mufflers that have been recommended by the manufacturer
as having the lowest associated noise and shall be enclosed with shields or
acoustical barrier enclosures.
Concrete crushers or pavement saws: Pre-augur pile holes to reduce the duration of impact or
vibratory pile driving and tie to local power grid to
reduce the use of generators and shall be enclosed with
shields or acoustical barrier enclosures.
Pneumatic hand power tools: All pneumatic tools operated in the City of Aspen must be fitted
with an effective silencer on their air exhaust port.
Temporary Noise Barrier Materials:
Temporary barriers shall be constructed of 3/4-inch Medium Density Overlay(MDO)plywood
sheeting, or other material of equivalent utility and appearance having a surface weight of 2
pounds per square foot or greater. The temporary barriers shall be lined on one side with glass
fiber, mineral wool, or other similar noise curtain type noise-absorbing material at least 2-inches.
The materials used for temporary barriers shall be sufficient to last through the duration of the
construction project, and shall be maintained in good repair. Prefabricated acoustic barriers are
available from various vendors. An equivalent barrier design can be submitted in lieu of the
plywood barrier described above.
Impact Equipment:
Impact noise is noise produced from impact or devices with discernible separation in sound
pressure maxima. Examples for impact equipment include,but are not limited to; blasting, chisel
drops, mounted impact hammers (hoe ram), and impact pile drivers.
Impact equipment is the loudest and most intrusive to the neighboring property. The City of
Aspen requires that this type activity have the strictest mitigation requirements and
requires a customized noise suppression plan specific to the site. General contractors must
contact the City of Aspen Environmental Health Department for an application at 970-920-5039.
Noise Control
• Replace worn, loose, or unbalanced machine parts that cause vibration.
• Keep machine parts well lubricated to reduce friction.
• Acoustical enclosures and barriers around generators
• Sound absorbing material and vibration isolation systems on hand tools
• Quiet work practices -use rubber mallets to erect and dismantle formwork.
RECEIVED
Revised O1/09/2013 01/11/2 018
ASPEN
BUILDING DEPARTMENT
Noise Controls for Construction Equipment (Schneider et al., 1995)
'Equipment 'Noise Controls
'Pile Driver 'Enclosure, muffler
Stone saw cutting Noise control pad with water
'Handheld impact drills Reduction of reflected sound
Circular saw blades 15°tooth angle, new tooth configuration, slotted saw blades,
iscoelastic damping _
'Pneumatic tools Muffler
avement breaker/Rock Muffler, enclosure of cylinder case and front head,moil damping
drill
'Portable air compressor Muffler, acoustic enclosures
Bulldozer Bulldozer Cab-liner material, enclosure, sound absorption in canopy,
sealing of all openings
Wheeled loader 'Absorption of sound cooling air route
Vibratory roller 'Flexible mounting for pump compartment
Joint Cutter Anti-vibration mounting fixtures
RECEIVED
Revised O 1/09/2013 O 1/11/2 O 18
ASPEN
BUILDING DEPARTMENT