Loading...
HomeMy WebLinkAboutFile Documents.201 W Francis St.0029-2022-BROF (3) Or /101 CITY OF ASPEN Construction Mitigation Plan for Medium Projects Full Construction Management Plan (CMP) requirements can be found in the Construction Management Plan Requirements Manual available here. The following document can be utilized for interior remodels and/or soil disturbance greater than 1,000 SF and less than 2,000 SF or roofing permits within the CRA or roofing permits on multifamily dwellings regardless of location.The "Construction Mitigation Plan for Minor Projects" document can be utilized for interior remodels and/or soil disturbance less than 1,000 sf. For large projects or at the discretion of the CMP reviewer a full CMP written by the project contractor is required. The purpose of this form is for medium projects to provide the required information for construction management and to acknowledge the applicant is aware of all CMP requirements and will abide by all requirements. 1.0 General The project contractor has completed the City of Aspen online CMP certification class.The online training course is available at cmpaspen.com.A copy of the CMP certificate is provided with this submission. 2.0 Project Location Project Address: 201 W Francis St, Aspen, CO 81611 Project Disturbance Area: No soil disturbance Project Description: See attached, page 5 Contact Information: Name: Phil Dunn Phone: 609-330-5045 Email: phil@stormkingroof.com 3.0 Project Documentation List all Permits Related to this Project (MEP, tree removal permit, UTWC, encroachments, etc.): N/A February 2021 1 Appendix A-Project Sign CITY OF ASPEN PROJECT NAME — PROJECT ADDRESS PERMIT NUMBER G.C.NAME&CONTACT NUMBER(S) Indicate Project Public Notification: EMERGENCY NAME d CONTACT NUMBER(S) Project Sign Will Be Posted at Site—Required information is provided to the right. Project Description Project Partner Project Partner — 4.0 Project Implementation ect Partner Listing)Agent/Agency WebsitelContact — Dates of Project Construction: As soon as permit is issued Hours of Construction: Construction hours shall be limited to 7:30am—5:30pm Monday through Friday and 9:00am—5:00pm on Saturday. No construction is permitted on Sundays or holidays as identified by the CMP Manual.Will construction fencing be provided? Yes d/ ot required for the project scope The fence shall be six feet (6') in height and constructed out of chain-link fence with mesh windscreens (visual barriers). If fencing is required show the location of the construction fencing on the site plan. Are there trees within the work area? Yes No (Fencing not required) If trees are within the work area provide a site plan showing exact tree protection fence location and accurate tree driplines 5.0 Site and Right of Way Management A Site plan is attached which shows all construction staging areas. see attached, page 6 Construction trailer,job materials storage, waste management and recycling container locations, and portable restrooms shall be clearly designated on the project site plan. Loose job material storage is not allowed in ROW under any circumstance. Show any use of the ROW or show there is adequate space onsite. Will the project use any portion of the Public Right of Way for construction purposes?The project shall submit a temporary encroachment permit for Yes ,X o use of the ROW. Will the Project maintain continuous emergency vehicle access, on and around site, including but not limited to police,fire, and ambulance services? Yes No February 2021 2 Or /101 CITY OF ASPEN Does the project require leasing public parking spaces for construction purposes? Yes VNo All parking must be leased through the COA Parking Department as a separate process. Does the project propose earth retention? If the project proposes earth retention a plan shall be submitted Yes VNo that depicts the extent of excavation and details any method of stabilization employed.The plan shall also depict any non- surcharge areas associated with the stabilization plan. The City of Aspen requires recycling of materials, both conventional and construction related. Does the project have a recycling plan in place on site? Yes No See section 5.7 of the CMP Manual for full recycling details. 6.0 Traffic Control Does the project require a traffic control plan? Yes VNo If so, attach the traffic control plan to this application. Does the project require any special circumstances for deliveries? Yes VNo Traffic control required for deliveries must be fully coordinated with the City of Aspen Engineering Department. Roads will not be closed under any circumstances, unless granted permission from the City of Aspen Engineering Department. 7.0 Pedestrian Protection Does the Project maintain pedestrian walkways including all ADA requirements? VYes No If temporary ramps are needed please show the location on the CMP site plan. 8.0 Sediment and Erosion Control Attach a site plan to this application which identifies all Best Management Practices which will prevent any erosion and sediment transport offsite. N/A Is the project located in the Smuggler Mountain Superfund Site? Yes VNo If so, attach the Superfund Site soil Removal Permit. 9.0 FUGITIVE DUST CONTROL A Fugitive Dust Control Plan is in place. Yes Not Applicable 10.0 EMISSIONS February 2021 3 OI tIli/ CITY OF ASPEN All vehicles and equipment used on site will be properly maintained such that the engines will function within manufacture's standards or parameters. V Yes No 11.0 NOISE SUPPRESSION A noise suppression plan is in place. Yes with minimum 14' noise fencing Not Applicable The minimum requirements for a non-modeled plan are a 14-foot tall fence of noise dampening material completely surrounding the construction site. Provide a Noise Suppression Plan. Provide a drawing showing the location of the sound fence. Include the property line, where the earth retention will be,the extent of excavation, any trees that are to be left throughout the construction, and location of gate. Also include a detail of how the fence will be supported and the noise dampening material used. Projects are limited to 70 decibels (dB) at the property line during the summer on season. Projects located on the Mall will be limited to 70 decibels (dB)at the property line during the winter on season.All other times projects will be limited to 80 decibels (80dB) at the property line. 12.0 ENFORCEMENT A City Construction Mitigation Officer will complete random site visits to determine if the project is following approved Plan and City requirements. SIGNATURE I acknowledge that all information provided is accurate.The Project will comply with all COA Construction Management Plan Requirements as Outlined in the CMP Manual. Contractor acknowledges that failure to abide by this affidavit will result in red tags on the project and loss of participation in the program Signature: /" z7u Printed Name: Phil Dunn Date: 05/02/22 February 2021 4 STORM KING ROOFING SHEET METAL 201 W FRANCIS ROOF REPLACEMENT CONSTRUCTION MANAGEMENT PLAN Site location: 201 W Francis St Aspen, CO 81611 Property Owner: Heather Vicenzi Scope of Work: 2,889 SF Malarkey Asphalt Shingle on Main House • Remove and properly dispose of the existing asphalt and cedar shingles • Fabricate and install 24 ga. "Aged Bronze" pre-finished flashing per manufacturers specifications. • Furnish and install full coverage High Temp Ice&Water Shield per local building code requirements. • Furnish and install Malarkey"Heather"Asphalt Shingles and associated accessories per the manufacturer's specifications. • Furnish and install all roof penetration flashing to ensure a neat appearing and watertight assembly. • Clean up and properly dispose of all roofing debris. Scope#2— 973 SF Malarkey Asphalt Shingle on ADU • Remove and properly dispose of the existing Cedar Shingles • Fabricate and install 24 ga. "Aged Bronze" pre-finished flashing per manufacturers specifications. • Furnish and install full coverage High Temp Ice &Water Shield per local building code requirements. • Furnish and install Malarkey"Heather"Asphalt Shingles and associated accessories per the manufacturer's specifications. • Furnish and install all roof penetration flashing to ensure a neat appearing and watertight assembly. • Clean up and properly dispose of all roofing debris. Scope#4— 200 Pre-finished TRA Apex Snow Guards • Install 200 TRA Apex Snow Guards per roof plan and manufacturers specifications. • Clean up and properly dispose of all roofing debris. Scope#5—Pre-finished Seamless K-Style Gutters& Downspouts • Remove and properly dispose of existing gutters and downspouts. • Install 26' of Seamless Pre-finished 5" K-Style Gutters per roof plan and manufacturers specifications. • Install 30' of Pre-finished 2"x 3" Rectangular Downspouts per roof plan and manufacturers specifications. Field Supervision Contact: Aaron James (603) 730-7444. • Clean up and properly dispose of all roofing debris. Waste Management: Roofing waste will be hauled of site with a trash trailer provided by Storm King Roofing LLC to Pitkin County Landfill. Dump trailer and toilet will be located per the included site plan. Portable toilet will be on- site at the start of work and will remain on-site for the duration of project. Parking: These re-roofs are on a property with ample parking that will not interfere with any city business, thoroughfare or right of way. Duration of Work: Expected duration of project is 5 to 8 weeks depending on weather. •' • . •♦ . 'nkis St J a ►�. wF I ` / �,' • . rands .% • . i r. • : PS r J 4` y vcs. 41160. 1. •' 201 W,rancisSt, w+ _ i s• Aspen,CC,;•8161%• i • /1 o•• _"'• 1 n'• .6* .1 4 , / ,.• , N) /1...7.4 .: ''.: .. 1 ' 1 iii, i,.. • • , , ........ , .. ..,...., , 1 7 ' . • •J • rg • 1 lir Ir ��� �I 1 • .‘ lit.4.._ !lilt • 4% 4 i •a` V , • Art-, .. - • iti' . 01 . • . ,• . r:lik• , • . '•to, ,A1• -0 e‘, 110, 14414 ••,,, • Y• 1 • lir "1.111pia% I ,.4 • ; +5 , i . • i , I ni ‘ .096 • no ...ikt §Y . Dump Trailer Parking & Toilet Extent of Work Field Supervision Contact: Aaron James (603) 730-7444.