HomeMy WebLinkAboutFile Documents.303 Oak Ln.0027-2022-BROF (9) APPROVED Carl Kishbaugh 4/25/2022 STORM KING ROOFING SHEET METAL 303 OAK LANE ROOF REPLACEMENT CONSTRUCTION MANAGEMENT PLAN Site location: 303 Oak Lane, Aspen, CO 81611 Property Owner: Sally Maxwell Scope of Work: 1,922 SF Building Malarkey Highlander Asphalt Shingle • Remove and properly dispose of the existing asphalt shingles • Fabricate and install 24 ga. pre-finished flashing per manufacturers specifications. • Furnish and install full coverage High Temp Ice &Water Shield per local building code requirements. • Furnish and install Malarkey Highlander Asphalt Shingles and associated accessories per the manufacturer's specifications. • Furnish and install all roof penetration flashing to ensure a neat appearing and watertight assembly. • Clean up and properly dispose of all roofing debris. 470'Heat Tape • Furnish and install approx. 470 L.F. of 220-volt heat tape on eave and in gutters and downspouts per manufactures specifications. • Clean up and properly dispose of all heat tape debris. Waste Management: Roofing waste will be hauled of site with a trash trailer provided by Storm King Roofing LLC to Pitkin County Landfill. Dump trailer and toilet will be located per the included site plan. Portable toilet will be on- site at the start of work and will remain on-site for the duration of project. Parking: These re-roofs are on a property with ample parking that will not interfere with any city business, thoroughfare or right of way. Duration of Work: Expected duration of project is 2 to 4 weeks depending on weather. RECEIVED Field Supervision Contact: Aaron James (603) 730-7444. 04/14/2022 ASPEN BUILDING DEPARTMENT STORM KING ROOFING SHEET METAL 303 OAK LANE ROOF REPLACEMENT CONSTRUCTION MANAGEMENT PLAN Site location: 303 Oak Lane, Aspen, CO 81611 Property Owner: Sally Maxwell Scope of Work: 1,922 SF Building Malarkey Highlander Asphalt Shingle • Remove and properly dispose of the existing asphalt shingles • Fabricate and install 24 ga. pre-finished flashing per manufacturers specifications. • Furnish and install full coverage High Temp Ice &Water Shield per local building code requirements. • Furnish and install Malarkey Highlander Asphalt Shingles and associated accessories per the manufacturer's specifications. • Furnish and install all roof penetration flashing to ensure a neat appearing and watertight assembly. • Clean up and properly dispose of all roofing debris. 470'Heat Tape • Furnish and install approx. 470 L.F. of 220-volt heat tape on eave and in gutters and downspouts per manufactures specifications. • Clean up and properly dispose of all heat tape debris. Waste Management: Roofing waste will be hauled of site with a trash trailer provided by Storm King Roofing LLC to Pitkin County Landfill. Dump trailer and toilet will be located per the included site plan. Portable toilet will be on- site at the start of work and will remain on-site for the duration of project. Parking: These re-roofs are on a property with ample parking that will not interfere with any city business, thoroughfare or right of way. Duration of Work: Expected duration of project is 2 to 4 weeks depending on weather. RECEIVED Field Supervision Contact: Aaron James (603) 730-7444. 04/14/2022 ASPEN BUILDING DEPARTMENT