303 OAK LANE ROOF REPLACEMENT
CONSTRUCTION MANAGEMENT PLAN
Site location:
303 Oak Lane, Aspen, CO 81611
Property Owner:
Sally Maxwell
Scope of Work:
1,922 SF Building Malarkey Highlander Asphalt Shingle
• Remove and properly dispose of the existing asphalt shingles
• Fabricate and install 24 ga. pre-finished flashing per manufacturers specifications.
• Furnish and install full coverage High Temp Ice &Water Shield per local building code
requirements.
• Furnish and install Malarkey Highlander Asphalt Shingles and associated accessories per the
manufacturer's specifications.
• Furnish and install all roof penetration flashing to ensure a neat appearing and watertight
assembly.
• Clean up and properly dispose of all roofing debris.
470'Heat Tape
• Furnish and install approx. 470 L.F. of 220-volt heat tape on eave and in gutters and
downspouts per manufactures specifications.
• Clean up and properly dispose of all heat tape debris.
Waste Management:
Roofing waste will be hauled of site with a trash trailer provided by Storm King Roofing LLC to Pitkin
County Landfill. Dump trailer and toilet will be located per the included site plan. Portable toilet will be on-
site at the start of work and will remain on-site for the duration of project.
Parking:
These re-roofs are on a property with ample parking that will not interfere with any city business,
thoroughfare or right of way.
Duration of Work:
Expected duration of project is 2 to 4 weeks depending on weather.
RECEIVED
Field Supervision Contact: Aaron James (603) 730-7444. 04/14/2022
ASPEN
BUILDING DEPARTMENT
STORM KING
ROOFING
SHEET METAL
303 OAK LANE ROOF REPLACEMENT
CONSTRUCTION MANAGEMENT PLAN
Site location:
303 Oak Lane, Aspen, CO 81611
Property Owner:
Sally Maxwell
Scope of Work:
1,922 SF Building Malarkey Highlander Asphalt Shingle
• Remove and properly dispose of the existing asphalt shingles
• Fabricate and install 24 ga. pre-finished flashing per manufacturers specifications.
• Furnish and install full coverage High Temp Ice &Water Shield per local building code
requirements.
• Furnish and install Malarkey Highlander Asphalt Shingles and associated accessories per the
manufacturer's specifications.
• Furnish and install all roof penetration flashing to ensure a neat appearing and watertight
assembly.
• Clean up and properly dispose of all roofing debris.
470'Heat Tape
• Furnish and install approx. 470 L.F. of 220-volt heat tape on eave and in gutters and
downspouts per manufactures specifications.
• Clean up and properly dispose of all heat tape debris.
Waste Management:
Roofing waste will be hauled of site with a trash trailer provided by Storm King Roofing LLC to Pitkin
County Landfill. Dump trailer and toilet will be located per the included site plan. Portable toilet will be on-
site at the start of work and will remain on-site for the duration of project.
Parking:
These re-roofs are on a property with ample parking that will not interfere with any city business,
thoroughfare or right of way.
Duration of Work:
Expected duration of project is 2 to 4 weeks depending on weather.
RECEIVED
Field Supervision Contact: Aaron James (603) 730-7444. 04/14/2022