HomeMy WebLinkAboutFile Documents.100 Dean St.0056-2021-BCHO (9) APPROVED
CK 1/17/2021
Construction Management Plan
Timber Ridge Condominiums
100 E Dean Street
2.1
The scope of work is removal and replacement of the exterior finishes.All work is to be within the site fencing along the property lines.
There will be minimal soil disturbance of approx.400 sf for concrete supports and slab on grade.
2.2
Site map is attached
2.3
The work will consist of removal and replacement of the exterior finishes including but not limited to: Removal and of existing wood
stairs,decks,balconies,and replace with steel/concrete elements.Removal of existing mansard and gable roofs and replace with vertical
metal siding along with new roof membrane on flat roof.Exterior siding,stone etc.to be replaced with Hardie Aspyre siding,and
new stone veneer.There will also be stucco elements in place of some of the wood siding.Excavation will be minimal along immediate
exterior foundation walls
3.0
This document is attached to the application for the applicable building permit 10 Days Prior to start
3.2 of construction
Public notification will be distributed to neighbors located within 300 feet of the project p operty.Updates will be made as required.
The site Superintendents number will be posted on the Job sign to allow for direct communication and will also be included in the public
notification.
3.3
Jobsite Sign will be posted as required.It will be 18"X 24"in size and will be legible from street or driveway
3.4
Owner:Timber Ridge Corporation
Contractor:Janckila Construction Inc.
Site Supervisor:TBD
Safety Officer:Sarah Janckila
Traffic Control:Al Traffic control
Erosion Control Representative—Not Applicable
City of Aspen Community Development Department—(970)920-5090
City of Aspen Fire Department—(970)925-5532
City of Aspen Police Department—(970)920-5400
Emergency Fire&Police—911
Aspen Valley Hospital—(970)925-1120
Roaring Fork Transit Authority(RFTA)—(970)925-8484
Aspen School District—(970)925-3760
Holy Cross Energy(Electrical)—(970)945-5491
Black Hills Energy(Gas)—(800)895-2999
Century Link Telephone—(800)603-6000
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
4.2
Dates of construction:Spring of 2021 to late fall of 2021
Hours of construction to be per COA
4.3
Construction schedule attached
4.4
Adjoining properties should not be impacted due to work.
4.5
Chain link fence shall be six feet(6')in height and constructed out of chain-link fence with mesh windscreens(visual barriers)to surround
the project at the property lines.
5.1
No work is anticipated in the ROW
5.2
Emergency vehicle access will be maintained
5.3
Construction parking will be as shown on the site management plan.Construction parking will be as dictated by the Covid 19 requirements
at the time the project is started.Adequate on-site parking for workers is anticipated.
5.4
Staging areas will be within site fence and material deliveries will be made out of the ROW
5.5
No ROW encroachment is anticipated
5.6
The construction trailer,job materials storage,portable restrooms,waste management and recycling container locations shall be clearly
designated on the project site plan within the project site.
Extent of excavation is shown on the plans.No stabilization required.
5.7
There will be a recycling container next to dumpster.
Concrete materials to be hauled specifically by excavator.Wood products will not be salvageable.
There will be a bear proof container for food refuse on site
6.1
No traffic control is anticipated
6.2
Haul routes will be oriented to minimize traffic congestion and maximize pedestrian safety
6.3
No traffic control requirements are anticipated.Roads are to remain open.The maximum number of delivery vehicles is to be three(3).
Only concrete trucks delivering concrete will be allowed to idle in excess of 5 minutes.
6.4
Traffic control plan is not anticipated to be necessary
7.0
Pedestrian impacts are not anticipated as all existing sidewalks are on opposite sides of the street from project.
8.0
Due to limited scope of soil disturbance a Storm Water Management plan should not be required.In the event of any fugitive
sediment waddles or other measures will be provided.
8.2
RECEIVED
O1/11/2021
ASPEN
BUILDING DEPARTMENT
Project is not within the Smuggle Mountain Super Fund Zone
9.0
Due to limited scope of dirt work fugitive dust is not anticipated.
10.0
All equipment will be within manufacturers specifications regarding emissions
11.0
Construction equipment will be adequately muffled and maintained to minimize noise
No radios will be allowed to operate on site in excess of noise limitations
Sound blankets are not anticipated to be required at this time.
Appendix A Project Sign
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
JANcKITAA
CONSTRUCTION INC.
970.927.6714
100 E Dean Street, Aspen CO 81611
Permit # TBD
Emergency Contact: 970.379.0313
Appendix B Haul Route Map
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
i �♦� -aur� �� ��,
OFFICIAL HEAVY HAUL ROUTE MAP
��` - Appendix B - Haul Route Map Legend i
�\ ) 1 j, �li•I[ Designated Heavy Haul Raute W Y,F.
W ! ••.l '� 1, • 'w -Roads v*ill *tit-
� . 1`,• �' ,IS f =1 �.' ❑ ` QParcels AM M NSPRuOEa! 600�
t t/1 / \' t irk% � d 1111 �.__i City Boundary u feet
�I 1►� I4d� ! ❑❑ w
•�t ��Ii� �� �iut is�i } a arnA•Nv Fnn A ,s'an ..n •
--Al :, ,)14„
NM
xvir
AAA �t — 11 , rj•-lusii old * ��.1 **� lii1 if fli- 1 1r t 1� I �
it Nity_,Niiiiit�r �nt�4447 '�.��/, o ``7 �• i Imo ` \= C
Si*4/- .'484/1:'lir 4.188 '• // ''ller# e;ft V/
alai ,--A111410*. ---- '.. I ON iiii:'N, '' 41-•`' it- V '''''14.
__ ...„,_,,,oliciir 414014,01)74 "1""41
474111 stl---,---3",(_:ain - it f*-4 at WO cwil-aAlr .1" 7 7#0.4 ' ‘ ,Z
iff
tilt.411:4*[ill! 1.1-*iI4I&''IV I - *iii--4---\
Irr
I V 'IP
;tt-tir'''
11/l� lal 1'.7 ftl 11 1
Irr► ill Ills ki-- 1li11; ♦ ♦ i� ��
�1 �Ir1 I1 n„/I �I/L1/1 � 1`
li —�Q £ lT•r1 1/III ri
•�I r ; • It �l r' 1lt..� �a
) IF
a �� 1 l Jet �11i '�1l uQ1 DI j 4 4 1 �
- ♦ ; J ilk lint: '*
la
//Ilk „
/ l Ili `alltr *lir
\I��jir, 11--/ .1,-- 4$ _611 .
-.. 1 r ,
... \ ,
)4_.. . \ i
f ,, ,,
i,
REC EED
01/11/2IV021
ASPEN
BUILDING DEPARTMENT
Appendix C -
Noise Suppression Plan, Techniques and Equipment
Noise Blocking Methods
Contractors shall require all subcontractors and vendors to use:
• "Residential" grade combustion engine exhaust silencers
•Electrical vs. pneumatic hand power tools
•Hydraulic vs. air powered rock drills
• "Silenced"pile drivers vs. Diesel pile drivers
Temporary Noise Barrier Materials:
Temporary barriers shall be constructed of 3/4-inch Medium Density Overlay(MDO)plywood
sheeting, or other material of equivalent utility and appearance having a surface weight of 2
pounds per square foot or greater. The temporary barriers shall be lined on one side with glass
fiber,mineral wool, or other similar noise curtain type noise-absorbing material at least 2-
inches. The materials used for temporary barriers shall be sufficient to last through the
duration of the construction project and shall be maintained in good repair. Prefabricated
acoustic barriers are available from various vendors. An equivalent barrier design can be
submitted in lieu of the plywood barrier described above.
Noise Control:
•Replace worn, loose, or unbalanced machine parts that cause vibration.
•Keep machine parts well lubricated to reduce friction.
•Acoustical enclosures and barriers around generators
• Sound absorbing material and vibration isolation systems on hand tools
• Shields, shrouds, or intake and exhaust mufflers.
•Noise-deadening material to line hoppers, conveyor transfer points, storage bins, or
chutes.
•Noise barriers using materials consistent with the Temporary Noise Barrier
Materials Section.
•Noise curtains
•Plywood with concrete blankets at the height of the equipment and that it surrounds
the activity such that it directs noise up more than out from the property.
•Portable three-sided enclosures made from plywood to move with the activity such
as jack hammering.
•Internal combustion engines are to be fitted with a suitable muffler in good repair.
•Noisy equipment such as cement mixers should be placed on the site to maximize
the distance from neighboring houses and/or rotate location so as to not impact just
one neighbor. Noise levels drop quickly with distance from the source. RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
• All equipment should be properly maintained, with special attention to mufflers
and
other noise control devices.
Revised 11/17/09
•Between work periods, builders are required by city ordinance to shut down
machines such as backhoes, bobcats, loaders and generators.
•All vehicular movements to and from the site must only be made during the
scheduled normal working hours. This includes off-site noise that is associated with
a specific project such as staging of concrete trucks.
Equipment/ Noise Controls
Activity
Pile Driver Enclosure, muffler
Stone Saw Cutting (Noise control pad with water
Handheld Impact Reduction of reflected sound
Drills
Circular Saw Blades 15°tooth angle, new tooth configuration, slotted saw blades,viscoelastic
damping
Pneumatic Tools Muffler
Pavement Breaker/ Muffler, enclosure of cylinder case and front head, moil damping
Rock Drill
Portable Air Muffler, acoustic enclosures
Compressor
Bulldozer Bulldozer Cab-liner material, enclosure, sound absorption in canopy,
sealing of all openings
Wheeled Loader Absorption of sound cooling air route
Vibratory Roller Flexible mounting for pump compartment
Joint Cutter Anti-vibration mounting fixtures
Dropping from When dropping materials from a height—for example, into or out of a
Height truck, or when loading or unloading scaffolding, noise suppression plans
(Re-Roofing) require a chute or side baffles.
Generators Acoustical enclosures and barriers surrounding equipment
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Generators25 KVA: The local power grid shall be used wherever feasible to limit generator
noise. No generators larger than 25 KVA shall be used and, where a
generator is necessary, it shall have maximum noise muffling capability.
Hand Tools Sound absorbing material and vibration isolation systems on hand tools
Dismantling 1 use rubber mallets to erect and dismantle formwork
Formwork
Backup Alarms All equipment with backup alarms operated by the Contractor, vendors,
suppliers, and subcontractors on the construction site shall be equipped
with either audible self-adjusting ambient-sensitive backup alarms or
manually-adjustable alarms. The ambient-sensitive alarms shall
automatically adjust to a maximum of 5 dBA over the surrounding
background noise levels. The manually-adjustable alarms shall be set at
the lowest setting required to be audible above the surrounding noise.
Installation and use of the alarms shall be consistent with the performance
requirements of the current revisions of Society of Automotive
'Engineering (SAE) J994, J1446, and OSHA regulations.
Compressors The unit with the lowest noise rating which meets the requirements of the
job should be used where work is conducted in the City of Aspen,
installed with mufflers and/or enclosed in a noise barrier.
Jackhammer All jackhammers and pavement breakers used on the construction site
shall have exhaust systems and mufflers that have been recommended by
the manufacturer as having the lowest associated noise and shall be
enclosed with shields or acoustical barrier enclosures.
Concrete Crushers or Pre-augur pile holes to reduce the duration of impact or vibratory pile
Pavement Saws driving and tie to local power grid to reduce the use of generators and
shall be enclosed with shields or acoustical barrier enclosures.
Pneumatic Hand All pneumatic tools operated in the City of Aspen must be fitted with an
Power Tools effective silencer on their air exhaust port.
RECEIVED
O1/11/2021
ASPEN
BUILDING DEPARTMENT
Revised 11/17/09
TABLE 1
NOISE CONSTRUCTION EQUIPMENT REQUIRING NOISE
SUPPRESSION PLANS
Equipment Category
Auger Drill Rig
Backhoe
Chain Saw
Clam Shovel
Compressor(air)
Concrete Mixer
Concrete Pump
Concrete Saw
Crane (mobile or stationary)
Dozer RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Drill Rig
Excavator
Front End Loader
Generator(more than 25 KVA)
Gradall
Grader
Horizontal Hydraulic Boring Jack
Impact Pile Driver(diesel or drop)
Impact Wrench
Jackhammer*
Mounted Impact Hammer(hoe ram)
Paver
Pneumatic Tools
Rock Drill
Scraper
Scarifier
Slurry Machine
Vibratory Pile Driver
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Appendix E - Central Resort Area and Commercial
Core Area Map
-v v s� 2
se W 4,1 r, / 0>r m
Zco?�r 3 \
�i,f T r q�M ��
7 d mTJ 1414.2 1*.�.ii ' _ , Central Resort Area , 4 4g' 44'
W wil ila 2 % .i* QF A T
Dikriii/� o ��; �I� R�� eft hII
J • °FA '�I `,., -1
ti i' �1 ��/� I7��f Ma,vsi 1 gigV1,?/
\
vz WhIIlr. �®�_ 1I ``,/ o 44 i Commercial Core Area
- liff '''illir ll *CU l '' ' I Eli Tary"-Qt11 ...- _ - '"•621Fir.1111 *
�+, � whir 14gir 0—or iriW.:80. 1''�*�
y y� n� J6�` y•0-`� 6, ii r
_ / /y�,��q}/[��/, (/�/�( +mot ^/C
twit
Will -�tly�q `y,`��:I 4I_ 'P1414 _.!:I�Ia1I�� ; iN AVF D Q
'T'� v y '�"' --r 2
' r- 0,... 1.1.'Ckap '4 Ariwtoowilirpt 5�; e63.1i G , ',2 wliArt ip 0
�
•
. 4': siff 1 trizt,i84,1,1 c, ? iii,:c_
%.%_1,# "it I 1,41!.. - ',-N k.'te• % 'tpllitallia:
,7 4 "-at*'-.''' it. i... 17, ,, I ' •01-
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Appendix F - Encroachment Zone Map
,,i - / ��// �� -
'CMP Encroachment Zone Map ,
� ' + RED-Encroachments lig
rt241IJii/� \ -.
•
,/' ami�f_ ; ORANGE-Encroachments
i IilZ77j
YELLO -
Main Street ____
71 /---- -------- ---; .... ,
. r pi .,, ,
, „,, /
MOPbns Ave Prf117 itifoi Lid
"�f /� tar/
i ...y il/ - /��
llymsn Ave Vie
�,__� N°�t/ • �:r�/ Iril •q1 ••• ,Y,
..,..,....1...47 Lie; II,,,,,,,,,,,,, !I nor P:s0
Cooper Ave + • f, A�/ ,,__, �_`iO
il
1
1 r hat -wJ1 ..
'f l� Ilr ,_ �m�I r /itif •��
:_ l ��,� '��` r` I �`Iiir .... .111=7. ! `II�1 •
ri - _` 9 �JI Str..t • krir , rp♦ �•PVT r
i____,7
�: / Ail
::'. '
7 ---_,- „,ii ,,,,,, ___,Iiii . , __ st.,_______7,i,,,,..i
1
..7 :
.....,.
/�' P.d..0lan / A .•• I �',.• ::�••I r1
4 ~` will Mau. ..'7!i:i!!....ii
.. .......................................
:.�• :/,
ask
Mg
e: F:,::::::.k. arlionter Street /
StIlllll4 �Sti Il% rI%l:�•Ijr ���•
1114 WO 11 r____, ZZ-am ! or40 - ii,,--- ea% Ps" A, . .,..,.,...... :4:1 1111.? (/f?-------- ---
oz.- . —itt . %is telt ir .t----- I fifieif .
�8 l'R..49 / .� in ���� eal
;7.....i 4111, mor :Pi s'.:... :17-.' SI Ar iii
• r �4111147 as.'�,'� \,, ``\( 111‘-birDZ3 _ ., ',•\ III
•� 1�R� j��1
I\Iii, to
�.. ita le
•
NI
fly [I] Ns
r
,E1 D
01/11/2021
ASPEN
BUILDING DEPARTMENT
Appendix H — Construction Waste Management Plan
CONSTRUCTION WASTE MANAGEMENT PLAN
Contact
Person:
Company Name: Janckila Construction Inc James
Zielinski
Address: 50 Sunset Dr. ste 3 Telephone
#:
970.379.03
Project Location: 100 E Dean Street Aspen Co
Contractor: Janckila Construction Inc.
Contact Person: James Zielinski
Telephone #: 970.379.0313
Recycling
Coordinators:
Contact Person: James Zielinski
Telephone #: 970.379.0313
RECEIVED
O1/11/2021
ASPEN
BUILDING DEPARTMENT
Project
Description:
The work will consist of removal and replacement of the exterior finishes including but not limited to:Removal
and of existing wood stairs,decks,balconies,and replace with steel/concrete elements.Removal of existing
mansard and gable roofs and replace with vertical metal siding along with new roof membrane on flat roof.
Exterior siding,stone etc. to be replaced with Hardie Aspyre siding,and new stone veneer.There will also be
stucco elements in place of some of the wood siding.Excavation will be minimal along immediate exterior
foundation walls
1. Salvage Yes I No
Do you plan to salvage materials from this project prior to X
demolition or construction?
If YES, list the materials that will be salvaged (e.g., doors, Facility or pany Receipt attached Y/N?
I windows, casing, toilets, sinks, fixtures, wood siding, tiles, Salvage co !ceiving
etc.) material
1.
2.
3.
4.
5.
2. Source Separation Yes No
X
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Do you plan to source separate any materials for delivery to a recycling
facility (e.g. separation of material such as wood, concrete, metal into
separate bins)
Materials Hauler Facility
Concrete E&L Excavation Landfill
Wood Waste Management Landfill
3. On-Site Use Yes No X
Do you plan any on-site reuse activities for this project (e.g. reuse of wood forms for X
concrete, on-site crushing of concrete for on-site use, use of reusable containers or
pallets for material deliveries, etc.)? (please provide photos of locations these items were
reused)
If yes, please describe:
4. Disposal at landfill
Will any materials be disposed of (not recycled or salvaged) at the landfill? Yes No
X
RECEIVED
O1/11/2021
ASPEN
BUILDING DEPARTMENT
Estimate the number of tons of material to be taken to the landfill for disposal: 15
Construction & Demolition Summary Report (CDSR) CITY OF ASPEN
This form must be completed for the following types of projects:
• All New Construction
• All Demolition, (excluding single family& duplex)
• Addition/Alteration with construction valuation exceeding$50,000 (excluding
single family& duplex residential)
Completed Summary Reports must be submitted prior to sign off at Final Inspection and
issuance of certificate of occupancy or temporary certificate of occupancy. A separate
Summary Report is required for each permit issued.
Deliver completed CDSR to Building Inspector. Call(XXX)XXX-XXXX or email with
inquiries regarding this form.
DO NOT ATTACH ADDITIONAL ITEMS
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Permit#: TBD
Project Address: (include floor, suite, etc.): 100 E Dean Street Aspen Co 81611
Contact Name:
James Zieilinski
Title: Project Manager Company: Janckila Construction Inc
Contact Mailing Address: 75 Buckskin dr. City Carbondale State CO
ZIP 81623
Phone: 970.927.6714Fax: 970.963.7239 Email: jimz@janckilaconstruction.com
For lines 1,2&3 please check only 1 item for each
1) Project Type: New Construction X Addition/Alteration Demolition
2) Building Type: Non-residential Single Family/Duplex
XApartment/Multifamily Sewer/Storm Drain Streets, Sidewalks, Traffic
Bridge Landscape,Parks, Open Space
3) Tenant Improvement(check one): Yes No X
4) Size of Project 12,171 sq. ft. Project Valuation$ 2,000,000.00
5) Completion Date 10 /28 / 21
6) Describe any difficulties you encountered in complying with your waste management
plan and tell us how to remedy the problem in the future.
For City Use Only:App Filed / / CDSR Submitted / / Received / /
Counter Staff
Diversion Goal Approved Good Cause Non-Attainment Conditional Approval
Not Approved,reason
Permit #: Address:
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
REQUIREMENT:
Recycle % of Asphalt& Concrete materials and no less than % of all other debris
(measured in tons).
Instructions: Using receipts and invoices list the tonnage of materials recycled during construction or
demolition. See the Conversion Worksheet to change all materials to tons. Complete the chart below
and make sure your column totals are correct. Include destinations for all materials.
Use Materials Conversion Worksheet to convert from cubic yards, square feet,board feet,
etc.to tons Column A—Tons of scrap or debris for each material type.
Columns B,C,D—quantities of A to be salvaged or reused,recycled, or disposed. See worksheet for
definitions.
Column E—list vendors or facilities used for salvage or reuse,recycling,or disposal.
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Material Type A B C D E
(circle all that apply) Total TONS Salvage Recycling* Disposal* Actual Facility Used
Discarded or
Reuse*
Asphalt/Concrete
DO NOT INCLUDE ASPHALT/CONCRETE IN TOTAL OR CALCULATION BELOW
Brick.Masonry.Tile 40 40 Masons yard
Cabinets,Fixtures.Doors.
Windows_ Equipment
Carpet
Carpet Padding
Cardboard
Ceiling Tile(acoustic)
Drywall(used or painted)
Drywall(unpainted scrap or
111111
sheets)
Landscape Debris (brush,
chips.trees.stumps.etc.)
Scrap Metal(all types) IPli
Wood,Pallets,&Lumber
(clean&unpainted,no
pressure treated wood)
Non-Recyclable Debris,ACM,
LBP(indi"'*.1 _
Other(in( Painted Lumber 10 i n
Recyclable Mixed Debris 6
Column Totals > A B C D Confine Totals Are Correct
*See instructions for definitions 0 See C&D Recycling Options for details
7. Fill in the blanks below to calculate your recycling rate. 1
Column Totals `� 40 - C ) = 40 T A 50 = 8 X 100 = 80
10.Is the percentage shown in#7 greater than or equal to 65%? X YES NO
If no.explain why and include documentation
Print Name: Signature: Date
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Monday Tuesday Wednesday Thursday Friday Saturday Sun(
Dec 2file Dec 22 Dec 23 Dec
Dec 25 Dec 26 Dec 27 Dec 28 Dec 29 Dec 30 ALI Dec
Look f�Jan 1Uuy ",uL J 2. .,` L., Jan 3v„ ,,,, �,lccurrent year that you are ding construction.
Years: onday023, 3.0ues8day Wednesday Thursday Friday Saturday Sung
ec 21 girl Dec 22 Dec
ec ec ec Dec 28 Dec 29 Dec
Pr M milli. Jan 2 lian 3
Years: 2018, 2029, 2035
Monday Tuesday Wednesday Thursday Friday Saturday Sun(
IllEc 20 111.1111111. Dec
Dec 23 Dec 24 Dec 25 6 Dec 27 Dec 28 Dec
Dec 30 Dec 31 Jan 1 Jan 2
Years. 2019, 2024, 2030
Monday Tuesday Wednesday Thursday Friday Saturday Sun(
Dec 19 Dec 20 Dec
Dec 22 Dec 23 Dec 24 Dec 25 Dec 26 Dec 27 Dec
Dec 29 Dec 30 Dec 31 Jan 1 Jan 2
Years: 2095, 9031 9036
Monday Tuesday Wednesday Thursday Friday Saturday Sung
Dec 19 Dec
ec 21 ec Dec sec 25 Dec 26 Dec
c 28 Dec 30 Dec 31 Jan 1 Jan 2
Years: 2090, 909R, 2037
Monday Tuesday Wednesday Thursday Friday Saturday Sun(
Dec 18 Dec
Inc 20 — ec Dec 22 ec 23 Dec 24 Dec 25 Dec
Derr? Dec 28 Dec 7 Impec 30 AL. Dec 31 ALJan 1
Years: 2021 , 2027 2032
Monday Tuesday Wednesday Thursday Friday Saturday Sun(
Dec
Dec 19 Dec 20, Dec 22 T Dec 23 Dec
Dec 26 Dec 27 Dec 28 Dec 29 Dec 30 iril i-L."EN
Years: 2016, 2022, 2033 01/11/2 021
ASPEN
BUILDING DEPARTMENT
VICINTY PLAN
r ��o,
c sr
iv i ra�is o�Pn
4 .S Srtuth 4. sz 5 4
to
r o IV,
Heb o
e { 2 erh Sr 04, Avg,
~' z. Vi oleetre, u
L.
N£ *Main s z i c John Denver Sanctuary e) e,
0 2 f Bteefr �' R'o �o
erg C ndePt 4i
W HoPk,Rs Ave �, Aspen P{o
tyN 0 4' cam' t Em .
y7n,,,Ave F g F H P2 ki�9
U F AZ Avp \e S7
PROJECT SITE ecoo eolve " ti
,e
0 0
f C Aspen MountainO Coo,,,
Ski Resort•Aspen:
Scn)n.•lit S ,M
4 m
d
a
•
•
•
. 1
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
Project Schedule
it + 1 a 1 i i i 1 1 a i i i i i i i i i a 1 t o f _i_{_ i i / I I
' 1 ii 1 1 ^'j�S{• I I
,t r 1 r i , r r r r - . , ; . r , I : I e I . ; r�
1
stiti"1"4
i1 i1
, ji , '. IL
, . .tit,
Hip i
r
II! ' i A
3
4111
1
,
RECEIVED
01/11/2021
ASPEN
BUILDING DEPARTMENT
•
rree�aecuow. rdlm
k a ra�ro o
r
T - ® 'sue I 4 II <>. -
•
o ,,
o 7 1
o
f i
e
I
wood
4` f— il
k Existing em
d
i I
b LNILO yo.,, ufLL4 LfuLQ 1.111RE utuLE IBILG 1 1
1
< �I
I � T
II\
_:I ,ia :
o __ __ 11 = O -+....l 11 .,
E 1 ` r __ v+wwuuxswcm.
__:1;_,
• T
® `.._.L , .umwr.M
u
n@
Y
o tiara
.u�caaru�siicwmuc �\
11A
SITE PLAN 1
RECEIVED
O1/11/2021
ASPEN
BUILDING DEPARTMENT