HomeMy WebLinkAboutresolution.council.107-14 RESOLUTION # 107
(Series of 2014)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN,
COLORADO, APPROVING THE MAIN STREET SIDEWALK WIDENING
PROJECT AS A CHANGE ORDER TO THE 2014 HOPKINS PEDESTRIAN
CONNECTIVITY IMPROVEMENTS PROJECT.
WHEREAS, Excavation Services, INC. is currently under contract to the
City to complete the 2014 Hopkins Pedestrian Connectivity Improvements Project.
WHEREAS, the City wants to change order Excavation Services, INC.
contract to complete the Main Street Sidewalk Widening Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO,
That the City Council of the City of Aspen hereby approves the change order
to Excavation Services, INC. contract with the City to complete the Main Street
Sidewalk Widening Project.
s'
INTRODUCED, READ AND ADOPTED by th 'C ty ounci of the ity of
Aspen on the 8th day of September, 2014.
teven Skadron, Mayor
1, Linda Manning, duly appointed and acting City Cler do certify that the
foregoing is a true and accurate copy of that resolution adopte by the City Council
of the City of Aspen, Colorado, at a meeting held, September 8, 2014.
Linda Manning, Cit Clerk
CHANGE ORDER
City of Aspen Engineering Department No. -01
PROJECT: Hopkins Pedestrian Connectivity Improvements
DATE OF ISSUANCE: 09/08/14
OWNER: City of Aspen
CONTRACTOR: Excavation Services,INC. OWNER's Project No. 2014-073
You are directed to make the following changes in the Contract Documents.
Description: Complete the construction of an 8 foot wide sidewalk,permeable pavers, and landscaping on
the south side of Main Street,between Mill Street and Monarch Street. (See Attachment B: Main Street
Construction Drawings and Technical Specifications for additional details)
Purpose of Change Order: Increase funding to complete the Main Street Sidewalk Widening Project scope
of work.
Attachments: Cost Breakdown; Main Street Construction Drawings; Additional Technical Specifications
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
Original Contract Price:.$76,166.00 Original Contract Time:08/25/14—11/01/14
Previous Change Order No. Net Change from previous
to No.(N/A) Change Orders:
$0.00(0 days)
Contract Price prior to Contract Time prior to
this Change Order: this Change Order:
$76.166.00 08/25/14—11/01/14
Net Increase(decrease) Net Increase(decrease)
of this Change Order: of this Change Order:
+$49,954.00 +0 days
Contract Price with all Contract Time with all
approved Change Orders: approved Change Orders:
$126.120.00 08/25/14—11/01/14
SUBMCCEPT D 01 REVIEWED APPWt BY: : BY: BY. ��
71 41—
DATE: �� !' DATE: / DATE: f
Troy Buster Garrett Sabourin,PE Trish Aragon,PE Steve Barwick
Excavation Services,INC City of Aspen City of Aspen City of Aspen
Owner Project Manager Department Head City Manager