HomeMy WebLinkAboutresolution.council.118-23RESOLUTION # 118
(Series of 2023)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN,
COLORADO, APPROVING A CHANGE ORDER BETWEEN THE CITY OF
ASPEN AND 3G CONSTRUCTION LLC. AUTHORIZING THE CITY
MANAGER TO EXECUTE SAID CHANGE ORDER ON BEHALF OF THE
CITY OF ASPEN, COLORADO.
WHEREAS, there has been submitted to the City Council a change order for
Water Place Roof Replacements, between the City of Aspen and 3G Construction
LLC., a true and accurate copy of which is attached hereto as Exhibit "B";
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO,
That the City Council of the City of Aspen hereby approves that change
order for $76,993.13, between the City of Aspen and 3G Construction LLC., a
copy of which is annexed hereto and incorporated herein and does hereby
authorize the City Manager to execute said agreement on behalf of the City of
Aspen.
INTRODUCED, READ, AND ADOPTED by the City Council of the City
of Aspen on the 8th day of August 2023.
Torre, Mayor
I, Nicole Henning, duly appointed and acting City Clerk do certify that the
foregoing is a true and accurate copy of that resolution adopted by the City Council
of the City of Aspen, Colorado, at a meeting held, August 8th, 2023.
luk6a-
Nicole fienning, City Clerk
i
L.
L.
DocuSign Envelope ID: A66D8A3C-39E7-4579-9165-76CFB251C216
30 CONSTRUCTION
ROOFING
ROOFING
. PAINTING
. 6WING
3G Construction & Roofing
835 E. Platte Ave. Suite 1
Colorado Springs, CO 80903
(719) 422-2027
3gconstruction@gmall.com
www.3GRoofs.com
CHANGE ORDER
ADDRESS CHANGE ORDER # E-68671
City of Aspen DATE 07/25/2023
427 Rio Grande Place
Aspen, CO 81611
ACTIVITY
Waterplace Roof Replacement Project. 2023 -150
CHANGE ORDER #1 SUMMARY 1 9,122.13
Original estimate included roofing materials that
have since increased in price by the
manufacturers and or suppliers due to the roof
industry price increases. I have attached letters
from the manufacturers and suppliers.
Change order to reflect difference between
original estimate and new requested changes per
provided percentage increases as follows:
BREAKDOWN
Original roof material cost $94723.69
New roof material price $103845.82
$9122.13
CHANGE ORDER #2 SUMMARY 67,871.00
Original estimate included 10 control modules,
de-icing cable system at all gutters and at roof
locations per original bid documents.
Change order to reflect difference between
original estimate and new requested changes per
red lined plans and provided documents as
follows:
BREAKDOWN
1. 10 qty - (Wi-Fi) hcm1002 modules CHANGE
to 22 qty.-aseds8c modules and 2 qty.-aseds9c
modules
9,122.13
67,871.00
DocuSign Envelope ID: A66D8A3C-39E7-4579-9165-76CFB251C216
2. 225 ft. of flat metal hot panel CHANGE to 800
ft.
3. 1800 ft. of heat cable CHANGE to 5000 ft.
4.175 ft. of hot valley metal CHANGE to 330 ft.
5. 44 pieces joint transitions CHANGE to 159
pieces.
6. 10 qty. power connection kits CHANGE to 27
qty.
7. 10 qty. splice tee kits CHANGE to 27 qty.
8. CHANGE, add necessary hardware to support
new system.
Total cost difference from original estimate =
$67,871.00
TOTAL $76,993.13
Docu3igned by:
Accepted By 52DW214EE1942B..
owx a, 0 Accepted Date 8/10/2023 1 3:31:54 PM PDT