311 Park Avenue Mon 9/17/18
New Beginnings
ID Task Name Duration Start Finish !gust 1 September 1 I October 1 I November 1 I December 1 I January 1 I February 1 March 1 April 1 May 1
0 8/12 18/26 I 9/9 19/23 110/7 110/21 111/4 111/18. 12/2 1 12/16 1 12/30 1 1/13 1 1/27 1 2/10 1 2/24 1 3/10 1 3/24 I 4/7 14/21 I 5/5 15/19 1
1 311 Park 138 days Mon 9/17/18 Fri 4/5/19 f I I I
•123 ` Submittals •
'
128 Windows 15 days Mon 9/17/18 Mon 10/8/18 µVindows ',,
124 Skylight 10 days Thu 9/27/18 Thu 10/11/18 1 m +SkyligM •
•
',
125 Structural Steel 15 days Mon 10/1/18 Mon 10/22/18 •tructural Steel ',, ',,
126 Stair Stringers 15 days Tue 10/9/18 Tue 10/30/18 fair Stringers ', ',
127 Tile 15 days Fri 11/2/18s�Tue 11/27/1E '.Ile ', ',,
,
2 Mon 101111iI •
', '
3 IN NTP 0 days Mon 10/1/18 Mon 10/1/18 .011 ',.
4 Temporary Office 1 day Mon 10/1/18 Mon 10/1/18 1�semporary•free ',• , ',,
5 Dumpster and PortaPot 1 day Tue 10/2/18 Tue 10/2/18 I4�umpster:nd PortaPot •
6 Floor and Finishes Protection 2 days Wed 10/3/18 Thu 10/4/18 1 loor and Finishes Protectio I, I, I,
7 Isolate and Drain Snowmelt and InFloor Heat 1 day Fri 10/5/18 Fri 10/5/18 .•ate a d Drain Snowmelt nd InFloor Heat ', •
', ',
8 •
13 Lower Level 38 days Fri 10I5118 Thu 11/29/18 •
14 LL Remove Bed 3 Finishes and Wall Board as indicated 1 day Fri 10/5/18 Fri 10/5/18 i Remo e Bed 3 Finishes a d Wall Board as indicated
15 LL Remove Wall Board as Indicated for MEP Demo 2 days Mon 10/8/16 Tue 10/9/18 �h Re ove Wall Board as ndicated for MEP Demo
16 LL Remove Remaining Finishes and Framing as indicated 3 days Mon 10/22/18 Wed 10/24/18 • I
L Remove Remai ing Finishes and Framing as indicated
17 LL Remove Stair 2 days Wed 11/28/18 Thu 11/29/16 i L Remove Stair •
9 Window Well 6 days Mon 10/8/18 Mon 10/15/18 •
10 WW Shore Slab 1 day Mon 10/8/18 Mon 10/8/18 � h•re Slab
11 WW Saw Cut Slab,Walls,Floor 1 day Tue 10/9/18 Tue 10/9/18 II" •a Cut Slab,Wal ,'loor
12 WW Demo Concrete and Fill 4 days Wed 10/10/18 Mon 10/15/18 • Demo Concret. .n••Fill •
18 Main Level 38 days Wed 10/10/18 Tue 1214118
20 ML Remove Wall Board as Indicated for MEP Demo 2 days Wed 10/10/18 Thu 10/11/18 •
r mope Wall Boa•a:Indicated for MEP Demo ,, ,, ,,
19 ML Remove Remaining Finishes and Framing as indicated 3 days Thu 10/25/18 Mon 10/29/18 •
L Remove-e aining Finishes and Framing as indicated
21 ML Remove Stair 3 days Fri 11/30/18 Tue 12/4/18 —kAL Remove Stair ',.
22 Upper Level 22 days Fri 10112118 Mon 11/12/18 •
24 UL Remove Finishes and Walls as Indicated for MEP Demo 2 days Fri 10/12/18 Mon 10/15/18 L"ere ove Finishe-a d Walls as Indicated for MEP Demo ',, ',, ',,
25 Reshape Ridge Beam 3 days Tue 10/16/18 Thu 10/18/18 fA .ha se Ridge B•am
23 UL Remove Remaining Finishes and Framing as indicated 3 days Tue 10/30/18 Thu 11/1/18 ie L Remov-R maining Finishes and Framing ae indicated
26 Remove Wood Truss Members 4 days Wed 11/7/18 Mon 11/12/18 ® -em•ve Wood Truss Members ,.
27 Exterior 18 days Tue 10/16/18 Thu 11/8/18
29 EX Remove Exterior Finishes as Indicated 2 days Tue 10/16/18 Wed 10/17/18 ove Exteri•r F Wishes as Indicated
30 EX Remove Railings 6 days Thu 10/18/18 Thu 10/25/18 lam Remove R ilinc s
28 EX Open Roof For New Stair and Steel 2 days Wed 11/7/18 Thu 11/8/18 EX Op W•oof For New Stair and Steel ',, ',, ',, ',,
129 •days Mon 1018/1 ,
134 Windows 50 days Mon 10/8/18 Wed 12/19/18 IN.1 ®—M indows
132 Skylight 50 days Thu 10/11/18 Wed 12/26/18 miin®—MI 4SkyLight
131 Structural Steel 15 days! Mon 10/22/18 Mon 11/12/18 = .!I Steel
130 Stair Stringers 15 days Tue 10/30/18 Tue 11/20/18 _Stringers
133 Tile 40 days Tue 11/27/18 Mon 1/28/19 I cite
3' 1 Tu
33 MEP Demo,Cut,Move as required for Framing 4 days Tue 10/16/18 Fri 10/19/18 EP❑emo Cut, on-as required for Framing
34 Rough Plumbing 5 days Thu 12/13/18 Wed 12/19/18 '. '. i�—lough Plumbing
35 Rough Mechanical and Fireplace 2 days Thu 12/20/18 Fri 12/21/18 4.32ough Mechanical asd Fireplace
36 Rough Electric 5 days Wed 12/26/18 Thu 1/3/19 ough Electric 'I,
32 AV,Low Voltage 3 days Fri 1/4/19 Tue 1/8/19 AV,Low Voltage
37 .. ..
38 Form Footing 1 day Tue 10/16/18 Tue 10/16/18 irm Footing '. '
39 Inspect Footing 1 day Wed 10/17/18 Wed 10/17/18 spect Fooling
40 Pour Footing 1 day! Thu 10/18/18 Thu 10/18/18 "our Footing '
41 Form Wall 2 days Fri 10/19/18 Mon 10/22/18 orm Wal
42 Inspect Wall 1 day Tue 10/23/18 Tue 10/23/18 sped Wall
43 Button up wall 2 days Wed 10/24/18 Thu 10/25/18 utton up wal •
44 Pour wall 1 day Fri 10/26/18 Fri 10/26/18 ';our waII
45 Strip Walls 1 day Mon 10/29/18 Mon 10/29/18 ',I trip b ails •
46 Waterproof Slab 4 days Tue 10/30/18 Fri 11/2/18 ate pro'rf SI,b ' '.
47 Pour back apron,window well slab,and slab at floor 3 days Mon 11/5/18 Wed 11/7/18 ',, Pour b Ick:pron,win w ell slab,and slab at floor ',•
87
93 Exterior Railings Field Measure 2 days Fri 10/26/18 Mon 10/29/18 xterior Raiding-Fi-Id Mea ur
96 Exterior Railing Install 10 days Tue 11/20/16 Wed 12/5/18 xterio Ra iing Install
Page 1
koruGrowth Harmony New Beginnings 311 Park Avenue Mon 9/17/18
ID Task Name Duration Start Finish /gust 1 September 1 October 1 1 November 1 December 1 1 January 1 February 1 I March 1 April 1 May 1
0 8/12 18/26 I 9/9 19/23 I 10/7 110/21 11/4 1 11/18 12/2 12/16 12/30 1 1/13 1 1/27 1 2/10 1 2/24 1 3/10 1 3/24 1 4/7 1 4/21 1 5/5 1 5/19 1
100 Stair Core Window Install 3 days Wed 12/19/18 Fri 12/21/18 I Core Window I stall ,.
88 Remove and Replace Windows as Indicated 4 days Wed 12/26/18 Wed 1/2/19 ��..' -emove and-enlace Windows as Indicated I ',
99 Sky Light Install 3 days Wed 12/26/18 Fri 12/28/18 �i`ky Light Install ',
•
90 Patch Roof 3 days Wed 1/2/19 Fri 1/4/19 r •�I atch Roof
98 Install Lift and Slide and Folding Door 4 days Thu 1/3/19 Tue 1/8/19 II stall Lift,nd Slide and Folding Door '
91 Remove and Replace Roofing 20 days Mon 1/7/19 Fri 2/1/19 rma -emove and Replace Roofing ',,
89 Patch Siding at Windows 5 days Wed 1/9/19 Tue 1/15/19 Patch iding at Windows '
95 Paint Exterior 10 days Mon 2/4/19 Fri 2/15/19 aint Exterior '',,
92 Gutters and Downspouts 5 days Tue 2/19/19 Mon 2/25/19 utters and Downspouts '
97 Faux and Grout Exterior Stone 7 days Tue 2/19/19 Wed 2/27/19 ,iiaux and Grout Exterior Stone '',,
94 Heat Trace and Hook up 3 days Tue 2/26/19 Thu 2/28/19 14..eat Trace and Hook up '
48
59 Frame Lower Level Walls and Prep for Steel 3 days Tue 10/30/18 Thu 11/1/18 rame Lo er eve Wills•nd•r•p for Steel
58 Frame Main Level Walls and Prep for Steel 3 days Fri 11/2/18 Tue 11/6/18 -Fra a ai Leva all and P ep for Steel ',,
57 Frame Upper Level Walls and Prep for Steel(Brace Ridge) 3 days Wed 1117/18 Fri 11/9/18 ame Up•er ev II .Its an•Prep for Stee(Brace Ridge)
56 Install Main Level Steel 2 days Mon 11/12/18 Tue 11/13/18 s II ain e 1.1-eel
55 Install Upper Level Steel 2 days Wed 11/14/18 Thu 11/15/18 s II pp,r lave Steel -
54 Install Roof Steel 2 days Fri 11/16/18 Mon 11/19/18 s II R•of ate=I
53 Install Stair Stringers 2 days Tue 11/20/18 Wed 11/21/18 s':II-al IStr nge s
52 Install Temp Treads 2 days Mon 11/26/18 Tue 11/27/16 s II m•Tre d•
51 Main Level Patch in old stair and Complete Framing 3 days Wed 12/5/18 Fri 12/7/18 I n evel Pa ch in old star and Complete Framing
50 Upper Level Patch in at old stair and Complete Framing 3 days Mon 12/10/18 Wed 12/12/18 i p•er L :I Patch in at o d stair and Corn•lete Framing
49 Roof Patch in and Complete Framing 4 days Thu 12/13/18 Tue 12/18/18 - oof•a ch in and Co plate Framing,,
65 76 days Wed 11/28/1: W, 4
84 Stair Tread Manufacuture 10 days Wed 11/28/18 Tue 12/11/18 Tre-d anufacuture ',. ',,
66 Insulate 2 days Wed 1/9/19 Thu 1/10/19 sulate ', '
67 Insulation Inspection? 1 day Fri 1/11/19 Fri 1/11/19 �sulatlo Inspection? ',.
68 Install Pocket Doors 1 day Fri 1/11/19 Fri 1/11/19 stall P• ket Doors
69 Hang and Finish 8 days Mon 1/14/19 Wed 1/23/19 a g and Finish ',,
70 Prime Walls 2 days Thu 1/24/19 Fri 1/25/19 •Ime Walls '
73 Install Floor Tile 3 days Mon 1/28/19 Wed 1/30/19 IF wilastall Floor Til:
71 Install Doors 3 days Thu 1/31/19 Mon 2/4/19 stall Doors
72 Install Bath Tile 4 days Thu 1/31/19 Tue 2/5/19 Wm" stall Bath ile
85 Stair Treads Install 2 days Thu 1/31/19 Fri 2/1/19 N.tair Treads In.tall '�,
83 Stair Stand-Off and Field Measure 1 day Mon 2/4/19 Mon 2/4/19 II fair Stand-•ff and Field Measure ,
75 Install Trim and Closets Shelves 4 days Tue 2/5/19 Fri 2/8/19 '. I - entail Tri: and Closets Shelves ',
76 Install Cabinets 2 days Wed 2/6/19 Thu 2/7/19 stall Cabiets
78 Final Paint 10 days Mon 2/11/19 Mon 2/25/19 t [al Paint ',
77 MEP Trim 5 days Tue 2/26/19 Mon 3/4/19 ', ,r EP Trim ,
■
82 Stair Glazing Install 3 days Wed 2/27/19 Fri 3/1/19 II al;tair Glazing Install
81 Stair Railing Field Measure 1 day Mon 3/4/19 Mon 3/4/19 ICI fair Railing Field Measure ',
74 Piece in Wood Floor and refinish 5 days Tue 3/5/19 Mon 3/11/19 1r,1� •iece in Wood Floor and refinish
86 Carpet 4 days Tue 3/5/19 Fri 3/8/19 r(!'a arpet
79 Touch up Paint 5 days Tue 3/12/19 Mon 3/18/19 ouch up Paint
80 Stair Railing Install 2 days Tue 3/19/19 Wed 3/20/19 "I tair Railing Install
60 TRough Inspections Illirdays ThITTOR1711
64 Plumbing 1 day Thu 12/20/18 Thu 12/20/18 62 Mechanical 1 day Wed 12/26/18 Wed 12/26/18 lhnganical •
63 Electrical 1 day Fri 1/4/19 Fri 1/4/19 II i Iectrlcal
61 Framing 1 day Mon 1/7/19 Mon 1/7/19 taming
101 Closeou I 4
102 Final Inspections 21 days Tue 3/5/19 Tue 4/2/19
105 Electrical Final 1 day' Tue 3/5/19 Tue 3/5/19 '� I - rical Final ':.
106 Plumbing Final 1 day Tue 3/5/19 Tue 3/5/19 ', �(�• •bing Final ',
107 Mechanical Final 1 day Tue 3/5/19 Tue 3/5/19 LI(l anical Final
108 Zoning? 1 day Tue 3/5/19 Tue 3/5/19 ', F(�•• ngT ',
109 Engineering? 1 day Tue 3/5/19 Tue 3/5/19 'I, �III t neering? 'I,
103 Life Safety Inspection?? 1 day Tue 3/19/19 Tue 3/19/19 ', ife Safety Inspection?? ',
104 Pre CO Inspection 1 day Thu 3/21/19 Thu 3/21/19 'I, �•re CO Inspection ',,
110 CO Final 1 day Fri 3/22/19 Fri 3/22/19 O Final
111 CO Processing 7 days Mon 3/25/19 Tue 4/2/19 0 Processing
112 Sub Contractor QAQC 14 days Tue 3/19/19 Fri 4/5/19
113 Final Clean/Exterior Power Wash/Windows 2 days Tue 3/19/19 Wed 3/20/19 Ina!Clean/Exterior Power Wash/Wlnd
114 Koru QAQC 2 days Thu 3/21/19 Fri 3/22/19 l f(o u QAQC
Page 2
koruGrowth Harmony New Beginnings 311 Park Avenue Mon 9/17/18
ID Task Name Duration Start Finish !gust 1 September 1 October 1 I November 1 December 1 I January 1 February 1 March 1 April 1 May 1
0 8/12 18/26 I 9/9 19/23 110/7 110/21 111/4 111/18] 12/2 1 12/16 1 12/30 1 1/13 1 1/27 1 2/10 1 2/24 1 3/10 1 3/24 I 4/7 14/21 I 5/5 15/19 1
115 Corrections 2 days Mon 3/25/19 Tue 3/26/19 orrections
116 Touch Up Clean 1 day Wed 3/27/19 Wed 3/27/19 ouch Up Clean ',,
117 Design Team Review 1 day Thu 3/28/19 Thu 3/28/19 •
fir esign Team Review '•
118 Corrections 2 days Fri 3/29/19 Mon 4/1/19 tea.orrections
119 Design Team Final Review 1 day Tue 4/2/19 Tue 4/2/19 r resign Team Final Review
120 Touch up Clean 1 day Wed 4/3/19 Wed 4/3/19 •
',, ilrTouch up Clean ,,
121 Owner Review 1 day Thu 4/4/19 Thu 4/4/19 ,►,Owner Review
•122 Building Turnover 1 day Fri 4/5/19 Fri 4/5/19 •
'I. Building Turnover