HomeMy WebLinkAboutFile Documents.520 S Original St.0144.2018 (4).ARBK G.F. WOODS CONSTRUCTIOIkj general contracting+construction management Construction Management Plan 550 S. Original St. Unit A 1. Project Introduction 1.1. This project is located on the top floor of the Arrowhead condominium building located at 520 S. Original St. The space is 2,300SF of floor area covering the entire 3rd level. 1.2. Vicinity Map: Condominiums la Office Ship Center 9 WF E Cooper Ave MAX Womens Clothing Aspen Bike Q Tours&Rentals 9 QStash 7O y Wg Eosin = y Grand Aspen EDeraar Ave A A EDerarn Wg y Are 3 ATM o EDaraar Are E Deans, '520 South Original Street Wg 9 9 '.npprr Q.. Glory Hole Park r Aspen Alps vP Condominiums gSifaeu6 3 O Wore,,,,,. s Ar 1.3. The apartment complex building is located on the SE corner of S. Original and E. Dean St. This project is currently in an indeterminate state of construction where major demolition and MEP rough in has been accomplished and put on hold. Minimal redesign of the existing space had been completed and GF Woods has been contracted to finish the remaining scope of this remodel consisting of interior finish work. Project duration is expected to be 7-8 months. 2. Project Documentation 2.1. Adjacent units will be notified of work and provided contact information via the posting of the project sign. All immediate neighbors and the HOA will be notified directly of this construction and informed on an as need basis of possible construction impacts. Because impacts beyond the licensed ROW area are not anticipated, specific notification and on-site meeting should not be necessary. 05/25/2018 ASPEN BUILDING DEPARTMENT 2.2. A project sign will be posted on the entry door of the building with the contractor's contact information. 2.3. Contact List: Owner: Shea Trust General Contractor: G.F.Woods Construction, Eric Wynne (970) 319-6938 Site Supervisor: Jeremy Nolan (970) 366-9959 Safety Officer: Jeremy Nolan (970) 366-9959 Traffic Officer: Jeremy Nolan (970) 366-9959 3. Project Implementation 3.1. Dates of Construction: Construction is expected to last approximately 8 months (March 1, 2018 — November 30, 2018) and will only occur on approved dates Monday through Saturday. 3.2. Hours of Construction: Construction activity will only occur during the allowed hours of 7:30AM and 5:30PM Mon - Friday and 9AM to 5PM on Saturdays. 3.3. Excavation will not occur or encroach within 5' of the property line. 3.4. Project is all interior scope so no job site fencing will be installed. 3.5. Project shall uphold utmost respect for public health and welfare. 4. Project Management 4.1. Parking for subcontractors and GF Woods Construction employees will be limited to street parking. Temporary material staging will be located within the garage in the basement of the structure and in the private street parking spaces allocated to the unit off Dean St. 4.2. Parking at the site is limited and is all metered, private or 2 hr. carpooling and public transit will be encouraged and utilized to the greatest extent practicable. 4.3. Map of Construction Management Plan is attached as Exhibit A. 5. Traffic Control 5.1. Traffic Control Supervisor will manage operations, if and when necessary. 5.2. Designated haul routes will be followed. Exhibit B 5.3. Maximum vehicle weight shall not exceed 10,0001bs. 5.4. Any traffic control required for deliveries will be coordinated with the City of Aspen Engineering Department. Deliveries will not be scheduled outside of the approved hours of construction. No more than one delivery truck can be accommodated at any time. Deliveries will be either from Dean St. or from S Original in early morning hours to cause the least disturbance. 5.5. A Traffic Control Plan is not included as road blockages or traffic stoppages are not scheduled or anticipated due to the limited scope and nature of the project. 6. Pedestrian Protection 6.1. Pedestrian safety will be maintained per City Code Section 21 .04.060, MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 7. Sediment and Erosion Control — NA 8. Fugitive Dust Control — N/A. 9. Emissions —All construction vehicles will be maintained and in good running order. 10. Noise Suppression 10.1. Construction noise will be limited to 80 decibels at the property line whenever possible. And are not expected to be a concern with all construction activity contained indoors. 10.2. Loud or obtrusive work will be completed during the approved hours of 9AM to 5PM (Monday through Friday only). Neighbors will be notified 3 days advance. 05/25/2018 ASPEN BUILDING DEPARTMENT Exhibit A .1t.0 ,,,„. ..,:...\:,k- :3 d .*.,,, /'. \ F j `Ali). ICA‘ r ' *41"® iilt OLE PARK D - . .: . -1 Iti 10t4 - - 111111111 �l { 1111.1111. � m �? I■= INEEMI .a riit.acce .via stair or,010". . Pe = &<29\n9 ü4jj (e�4 1,11 G . . . ..• . ,...•• . . .. . . .. .. . , .. ... ... .. . , . , . . , / OA . . . . . . .. . . . . ,,�° / r access viao .,:...>,.-\J.,i,i‘il•-\t,,,,,.,. . . . ,:.,,, ...,,.. . 2., • . . staircase/ ✓/ o- , Ga G\�PV , SO RECEIVED 05/25/2018 ASPEN BUILDING DEPARTMENT Exhibit B �.. �W°�,�E� ��I �� ( OFFICIAL HEAVY HAUL ROUTE MAP _� �, —GIL'L'ESP_IEAVE _ Legend N _ 0 9 �+ RL GT _< z pie' h. Designated Heavy Haul Route W- E wNCRTy •• h-V — gj �/• Roads (•'--iitS Parcels?ir �� N. ill ❑ b 0 300 600 •' CR.tMS,� p� b ■ i___:City Boundary I SMU O Feet ,.,DER s,� .� , diT�� Map prepared byEngineeringandGISDepartment •Ii O ,ICityofAspen,CO81611May4,2007N/ss, Ifee I•IIc 0 , PINFRO j , -114 �,��� z •III I �• •IIh �A ....... y: = �,es Aws � .� - � �-, �', 0le IMI ''`k= _...•� ! iit `l tom 4 , ��_ II EKF ■ a • 51 J e��i •�� we�E �i � gMST I11 -� � �Ir � .1. � hjl� •� � sT •III,_,_ ` o �.�-� 116) , a 4N�2 ••I// ,- /�� i� 2 aI oftk�''. •� II,,, o • /_/*ikv4-cc,v,-s. . T I. 2/ / iilv SOU7.H AVE1'V* • � lIkft . i ) o� 9G`� 9���'p Rat�y � Ally sr •2 2 kER sr •• �OwwW 4 gig v p ,�2i��,, Cp, , as------,.....,:o or ,a- t.:(1. et $111 444f c''. 14/1i0410 ' Iri 10 /4 / *ffi A et*, - rg AI ..v • KIySgVE • ti ,�,��' / • II IN , ' ,� II I � � � .,� L j wNv I '�;� �� I•�, ,• DER ; ' • are I• • NOPKINS II.k/ �� �� i '' ,,* /,444rt w* /*Mpeft "' 71m/4,-„Wri � N A kr* 71 �W�Co_ • ii,�Z�' ZQ gim, r��Q�• C�� i QUEEN�ST tr,u4,,,,, ::1,1 DR ��4 � " � _ _ 1/4 i_lli i � ii,"147,:ii-tokii ), 4 l � 7° .,3-ika *4 •— c,fift e4 ' �iA,`/ gN ` ` EIdifi, /. Q�m 4141 . 01,_ o rie .. LN G,11„,ir, 7 sr .ft � e II., ' , Qwilily' WI AIIIPA4 ,4�r) Alf 'r ` ° NsT �»> �g S� I *• MH O ' '�E M _..... ..,_ ailli ti illi psP 2, ,,,,741, CI 1 1 I T 1