CITY OF ASPEN ENGINEERING DEPARTMENT
T((F CITY OF ASPEN SUFFICIENCY REVIEW REQUIREMENTS
If the project will increase impervious area(this includes enlarging a driveway,adding hard surface
patios,increasing the footprint of the house, etc.), disturb>200SF of exterior area(this includes
grading, even if a structure or hard surface isn't added), or add or repair snowmelt then an
engineering review will be required as part of the Building Permit or Landscape and Grading Permit
Application review process. All permit applications that must receive an engineering review are
required to schedule and participate in a Pre-Application Meeting with the Development Engineer.
The sufficiency checklist below and any necessary supporting documents should be completed prior
to this meeting,as they will be reviewed during the meeting. The Development Engineer's
signature on this checklist is required in order to submit a Building Permit Application.
•
Project Address: •V P
Project Common Location/Common Name: VIi
PLIVer
Parcel ID Number: D7 37 1 6
Owner and Phone Number: 10 Q 0."1O to 0-1-1
Contact and Phone Number and e-mail address: t114 0
B U r rld, i? ,G°M
1. How much land will be disturbed? acres= WWI sq.ft.
If one acre or more is disturbed, a CDPHE Construction General Permit is required.
Yes,Notice of Coverage has been included in the CMP.
No,A statement that Notice of Coverage is not required has been included in the CMP. 1/4
2. How much impervious area will be disturbed? 11 sq.ft. Added? 70 sq.ft.
3. What is the estimated'total impervious area of the site(not just the addition)? sq.ft.
q-
. 4. What type of permit is being sought(Building or Landscape/Grading)? 'Ua Vbl 014,
5. What sub-basin(see Secion 1.5 of URMP)is the project located within?
6. What level of project is this—Minor or Major? M 1 N OW.
In general,the project is considered"Minor" if 200— 1000 sq ft of disturbance/work and"Major"
if > 1000 sq ft of disturbance/work.
•
Revised 1 I-30-I4
Received
2/27/17 •
The following information is required for the engineer's review. Please indicate if these documents
have been completed and are attached. If any of these documents are not applicable,please provide
an explanation in the space provided.
Included N/A
7. Minor Grading and Drainage PIan and Report •
❑
8. Major Grading and Drainage Plan and Report
9. Compliant City of Aspen Survey
10. Soils Report
11. Excavation Stabilization Plan -
12. Construction Management Plan(CMP)
13. Public Improvement Requirements
�✓� I c
}
14. Floodplain Development Requirements
15. Mudflow Analysis ❑
3'r
I hereby declare the engineering information submitted in this sufficiency review for this
project is sufficient for City of Aspen Building Permit Application submittal.