HomeMy WebLinkAboutFile Documents.550 S Alps Rd.0018.2017 (11).ARBK 550 Aspen Alps South Road Heirloom Residence
Aspen, Colorado 81611 0018.2017.ARBK
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
Division Project Summary Division totals %Cost
01 General Conditions $ 38,590 18.9%
02 Sitework $ 2,500 1.2%
03 Concrete $ - 0.0%
04 Masonry $ 33,714 16.5%
05 IV1`talc $ - 0.0%
06 Woods and Plastics $ 79,160 38.8%
07 ThermalIVbisture Protection $ 42,700 21.0%
08 Doors and Windows $ - 0.0%
09 Interior Finishes $ - 0.0%
10 Specialties $ - 0.0%
11 Equipment $ - 0.0%
12 Furnishings $ - 0.0%
13 Special Construction $ - 0.0%
14 Conveying $ - 0.0%
15 Plumbing/HVAC $ 4,600 2.3%
16 Electrical $ 2,500 1.2%
Project Cost Subtotal I $ - $ 203,764 100.0%
Project Contingency 5.0% $ 10,188.20
Subtotal $ 213,952
Overhead&Profit 10.00% $ 21,395
Subtotal $ 235,347
Project Total $ 235,347
City of Aspen
Received
n °aepartment Page 1 of 8
Buildi
Heirloom Residence \i\)0
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
01 Cost Codes Description of Work Quantity unit Cost Current Budget (Notes, Assumptions for Allowances I
CO GENERAL CONDITIONS $ 38,590_
1 1001 Mobilization 1 LS $350.00 $ 350.00
2 1002 Demobilization 1 LS $350.00 $ 350.00
3 1020 Mockups/Allowance 1 LS $0.00 $ -
4 1035 Temporary Protection 1 LS $1,500.00 $ 1,500.00 Protection of the window and door package
5 1036 Site Fire Protection 1 LS $0.00 $ -
6 1040 Professional Consultants LS - By owners or Change order.
9 1055 Working supervisor 360.00 HRS $60.00 $ 21,600.00 10 weeks of combined supervision and PM at 36 hours per week
10 1060 Project Management 0.00 HRS $90.00 $ - Combinded with above _
13 1070 Permits and Fees 1 LS $0.00 $ - By owners or Change order.
14 1076 Federal Express 1 LS $250.00 $ 250.00 Budget for document/item conveyence
15 1080 Blueprints 1 LS $250.00 $ 250.00 Budget for document printing
16 1500 Temp Facilities Porta Potty 3 MO $280.00 $ 840.00
19 1530 Temp. Const./Locks/Keys 1 LS $500.00 $ 500.00 Budget for temporary construction
21 1590 Equipment Rental 1 LS $1,000.00 $ 1,000.00 small tool rental
22 1600 Scaffold Rental 1 LS $ - No scaffolding included here (within siding install bid)
26 1605 Crane Allowance 1 LS $0.00 $ - Not included
25 1605 Forklift 3 MO $2,000.00 $ 6,000.00 Forklift for mobilization of materials on daily basis
23 1740 Waste Removal 1 LS $4,250.00 $ 4,250.00 Project Clean up and debris removal
24 1750 Wnter Protection 1 LS $500.00 $ 500.00 Winter protection allowance - plowing and snow removal. This may vary based on local winter conditions.
Includes temporary heat
27 1785 Final Clean 1 LS $1,200.00 $ 1,200.00 Construction Cleaning at end of project
City of Aspen
Received
Page 2 of 8
Building°aepartment
Heirloom Residence \i\)0
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
Scope I I Description of Work I Quantity I unit I Cost Current Budget Notes, Assumptions for Allowances
02 Sitework/Excavation $ 2,500
Landscape Repair 1 LS $2,500.00 $ 2,500.00 Repair of the access to the back side of the house.
City of Aspen
Received
VOW
Page 3 of 8
Building°aepartment
Heirloom Residence VO
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
Scope cost Code Description of Work Quantity unit Cost Current Budget Notes, Assumptions for Allowances
04 !Masonry $ 33,714
1 'Demo stone veneer Terrace above Garage 96 MH ' $59.00 $ 5,664.00 Remove stone veneer at all walls on terrace above garage. This assumes that the stone veneer will
support during the construction process. Includes upper and lower level of terrace
2 Demo tile flatwork 490 SF $10.00 $ 4,900.00 Remove tile and mortar setting at all terrace area above garage
3 Stone Paving 490 SF $35.00 $ 17,150.00 Allowance: material specification TBD. A responsible allowance that would cover random flagstone,
_ certain tiles, etc. _
4 Stone Veneer 150 SF $40.00 $ 6,000.00 Allowance: Installation of stone veneer once waterproofing and horizontal paving has been completed.
To match existing. More stone veneer may need replaced if stone does not support on the wall during
the repair
5 $ -
6 $ -
City of Aspen
Received
VOW
Page 4 of 8
Buildin °department
Heirloom Residence \i\)0
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
Scope I Cost Codes I I Description of Work I Quantity I unit I Cost Current Budget Notes, Assumptions for Allowances
06 Woods and Plastics $ 79,160
6100 Parklex panel materials package 45 PA $423.00 $ 19,035.00 Materials package for parklex
6100 Freight for parklex panels 1 LS $2,525.00 $ 2,525.00 Trucking for two palets 7501bs each _
6100 Labor For Cutting Panels 45 PA $120.00 $ 5,400.00 Prepping parklex panels for installation, panels are delivered at 4x8 and need to be custom fit.
6100 Parklex installation 7200 SF $6.00 $ 43,200.00 Installation of panels
Siding Scaffolding 7200 SF $1.25 $ 9,000.00 Allowance: Scaffolding for siding
$
$
$
$
$
City of Aspen
Received
Page 5 of 8
Building°aepartment
Heirloom Residence VO
Exterior Remodel
CONSTRUCTION
Scope Cost Codes Description of Work Quantity unit Cost Current Budget Notes, Assumptions for Allowances
107 Thermal/Moisture Protection $ 42,700
1 Materials budget for Knight system 1 LS $7,200.00 $ 7,200.00 Allowance for membrane materials.
rain shield.
Knight System Accessories 1 LS $4,950.00 $ 4,950.00 metal,fasteners and 9" flashing for knight system
2 Installation of Knight system 7200 SF $3.00 $ 21,600.00 Installation of Knight system which includes membrane and track
3 Custom flashing 1 LS $1,200.00 $ 1,200.00 Allowance for materials and installation of items that may be necessary for window and doors in
connection with Knight System rain shield.
4 Water proofing around spa above 1 LS $7,750.00 $ 7,750.00 Water proofing with tapered insulation. It is unknow what system has been used for waterproofing. If
garage there is no sub structure slope to drain it is recommended that a slope be installed. If the tapered
insulation is not necessare that portion of the budget can be removed
5 $ -
6 $ -
City of Aspen
Received
Page 6 of 8
Buildinbibepartment
Heirloom Residence VO
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
Scope Cost Description of Work Quantity unit Cost Current Budget Notes,Assumptions for Allowances
Code
115 Plumbing/HVAC (Allowance) 1 I $ 4,600
Snowmelt 460 SF $10.00 $ 4,600.00 Replace snowmel, assumes that the snowmelt is in a setting bed above the concrete slab. If snowmelt
is embedded in slab this will not be required.
City of Aspen
Received
VOW
BuildinVa leplartment Page 7 of 8
Heirloom Residence \i\)0
Exterior Remodel
WILLIAM H.BAKER
CONSTRUCTION
Scope(Cost code I (Description of Work 1 Quantity I unit I Cost Current Budget Notes, Assumptions for Allowances
16 Electrical $ 2,500 I
Removing exterior sconces and 1 LS $2,500.00 $ 2,500.00 Allowance to move and waterproof sconces.
replacing
City of Aspen
Received
VOW
Page 8 of 8