HomeMy WebLinkAboutFile Documents.121 S Galena St.0083.2018 (11).ACBK DATE: MASTER PERMIT: PERMIT NUMBER:0 0 8 3 . 2 018 .ACBK
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT APPLICATION THE CITY isPEN
PROPERTY INFORMATION
ADDRESS 121 s galena st UNIT# PARCEL ID# 273707330007
LOT s BLOCK 87 OR SUBDIVISION city of aspen
OWNER NAME godiva holdings Ilc CELL 970-309-5507 EMAIL gotgas@sopris.net
BEST CONTACT rally dupps CELL 720-481-7353 EMAIL rallydupps@gmail.com
NAME
PROJECT DETAILS
DESCR
IPTION DETAIL
WORK IN DETAIL minor office interior remodel UPSTAIRS OFFICE . NO ASSIGNED UNIT NUMBER .
PROJECT 25,000 Use of Building Class of Work Fixture Counts Equipment Checklist
VALUATION
❑■ Commericali Toilets,Bidets
SCt FT OF0New Forced Air/Gravity Systems
O 1540 ❑ Multi-FamilyBathtub
W RK AREA ❑ Addition -Wall,Suspended,or Unit Heaters
0 Single Family ❑■ Alteration -Lavatory(Wash Basin) _Gas Log
1683 0 Mixed-Use Shower
UNIT SQ FT ❑ Repair _Kitchen Sink(+Disposal) Gas Appliancew
LOT 512E El IFFR Dishwasher Appliance Vents
_
(SQ FT) 3000 0 Tenant Finish _Laundry Bar,Utility Sink Heat,Refrig,Cooling,or
DISTURBED o Will there be ❑ Demolition _Clothes Washer Absorption Unit
EXTERIOR AREA any roof/wall ❑ ChangeOrder Floor Sink Boilers(includes vent)
penetrations? ❑ _Floor Drain _Air Handling Unit
NEW SQ FT 0 ID YeS Water— Heater(Pan Req) _Cooling Systems
❑ No
QQ RIT #Gas Outlets Ventilation Fans
W F ROTOY WORK 0 _Water Treatment Other Range Hood
#of Gas System Outlets
ZONE DISTRICT CC Snowmelt System Sq Ft
v7 Project Valuation:Cost of project as defined in Valuation Affadavit. 'NOTICE: This permit becomes null and
Z Sq Ft of Work Area:Total square footage of area undergoing change or reconfiguration. void if work or construction authorized
Unit Sq Ft:Gross Square Footage,not FAR,of permitted unit. is not commenced within 180 days,or
square footage of property. if construction or work is suspended or
Lot Size:Total surveyed
q g abandoned for a period of 180 days at
Disturbed Exterior Area:Square footage of lot affected by permit application. any time after work is commenced.
LL New Sq Ft:Total added square footage for additions to net livable or net leasble space.
pSq Ft of Rooms with Utility Work:Total square footage,not FAR,of all rooms with plumbing work. Re-
FOR CITY USE ONLY APPROVALS viewer
SUBMITTAL FEES ISSUANCE FEES ISSUANCE FEES _ ReviewingNeeds sOn- D
Department Review Off Approvede
Permit Fee PC X SV 0 8/16
Plan Check 333 . 13 512 . 50 Parks Impact $1,074.20 Zoning X BN 08/20/18
Zoning(50%) HPC
Engineering 325 . 00 School Ded. 0 Building X JH 9/6/18
Zoning(50%) CMP(50%) TDM Impact $120.52 Fire X JH 9/6/18
325 . 00 823 . 90 Engineering
Ped.Amenity PH 12/18/18
Energy Code REMP 0 CMP X
Plan Check Water X SW 8/17/1 c
CMP(50%) 823 . 90 (Hourly) Housing Cash in Lieu Stormwater
Zoning Sanitation
Parks Review (Hourly) Stormwater Env. Health
Engineering Parks
Utility Review 50 . 00 (Hourly) City Use Tax Landscape
GIS County Use Tax Efficiency
62 . 50
Approved DAM 12/18/18
Lot Area Deed Restricted To Issue
Census Code #of Dwellings Plans Location Issuance
f-CITY OF ASPEN December2017 130 S. GALENA ST I ASPEN, CO pj.p,1�1l14ols
ASPEN
BUILDING DEPARTMENT
ADDRESS: 121 s galena st PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT CONTACT SHEET THE CITY OFASPEN
FOR PLAN REVIEW QUESTIONS
Name rally duPes Phone E-mail VOW OD
FOR INSPECTION QUESTIONS
Name Phone E-mail
OWNER
Name Phone Cell Phone
Mailing 435 e main st aspen co 81611
Address city p State ZIP
E-mail gotgas@sopris.net
Address
OWNER'S AUTHORIZED AGENT
Y dupps
rall
Name PP Phone Cell Phone
AdMadriliess ng pob 3662 City aspen State Co ZIP 81612
E-mail
Address
APPLICATION BEST CONTACT
Name rally dupps Phone V A • Cell Phone
Address pob 3662 City aspen State CO ZIP 81612
E-mail
Address
ARCHITECT OR DESIGNER OF RECORD
Name rally dupps Phone V A • Cell Phone
Mailing pob 3662 City aspen State CO ZIP 81612
Address
E-mail
Address
CIVIL ENGINEER OF RECORD
Name Phone Cell Phone
Mailing
Address City State ZIP
E-mail
Address
STRUCTUAL ENGINEER OF RECORD
Name ALBRIGHT AND ASSOCIATES Phone l• g • A e Cell Phone
Mailing 402 PARK AVE. UNIT E basalt co 81623
Address City State ZIP
E-mail Address jack@albright-associates.com
GENERAL CONTRACTOR
Name Phone Cell Phone
Mailing
Address City State ZIP
E-mail
Address
INSPECTIONS: The General Contractor must schedule inspections online.
Please visit www.aspenpitkin.com/Departments/Community-Development-Forms/to do so.
I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions of laws and
ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does not
presume to give authority to violate or cancel the provisions of any other state or local law regulating construction or the performance
of construction. It is my responsibility to review the approved plans and any comments that are contained thereon and see that the
structure and/or project is built in compliance with allapplicable codes.
Contractor Date
Signature
❑ Check if you are a tested owner builder(single-family homes only).You must take a test and complete the owner/building affidavit.
(CITY USE ONLY)Owner builder approved by: Date: Affidavit on file
VET
j C ITY OF ASPE NAugust 2017 ' 130 S. GALENA ST I ASPEN, CO ph1
67 018
ASPEN
'BUILDING DEPARTMENT
ADDRESS: 121 s galena st PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
SCOPE OF WORK CHECKLIST THE C11'OFASPEN
LAND USE QUESTIONS
If you check any of the boxes below,please consult with the Planner of the Day(planneroftheday@gmail.com)before submitting your
permit application.
Does your permit involve any of the following?
❑1 Part of an approved COA Land Use Review ❑ Work involves Landmark Parcel or Historic District
Work affects net leasable, net livable, or ❑ Located in 100-year flood plain or within 100' of high
non-unit space water mark
ElWork involves lot splitting or combining a lot El Work involves changes in occupancy to structure
❑ Work involves exterior of structure Changes to elevator or stair configuration
▪ Changing the number of residential units Changes to the use of existing structure or space
▪ Changes to number or location of
onsite parking
ADDITIONAL SCOPE OF WORK QUESTIONS •
Does your permit involve any of the following?
▪ Exterior lighting added or changed ❑ Work involves exterior wall penetrations
pWork involves roof penetrations Work involves digging or excavation
• ❑� Work adds removes, or changes Work involves restaurant or food service
plumbing fixtures
▪ Disturbs 1,000 sq ft or more of soil within ❑ Affects parking spaces/meters, loading zones, or alleys
12 months
▪ Work occurs in public right of way ❑ Adding structures or systems over utility lines
▪ Work affects trees or occurs within the El Work within City Mall boundaries
dripline of a tree
I CITY OF ASPE NAugust 2017 130 S. GALENA ST I ASPEN, CO EM19,11.)2018
ASPEN
BUILDING DEPARTMENT
ADDRESS: 121 s galena st PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
VALUATION AFFADAVITA,�,�,'
THE CI"CY OF ASPEN.
AFFIDAVIT POLICY
All applications for a building permit within the City of Aspen are required to include a certification of
compliance with building permit valuation requirements. The certification must be signed by the property
owner or authorized representative. The following certification shall accompany the application for a permit.
I,the property owner or authorized agent, understand and certify as follows:
City of Aspen Ordinance No. 40, Series of 2016 adopts the 2015 International Residential Code (IRC) and
International Building Code (IBC) with certain amendments. These codes define building valuation as follows:
R108.3 Building permit valuations. Building permit valuation shall include total value of the work for which a
permit is being issued, such as electrical,gas, mechanical, plumbing equipment, and other permanent systems,
including materials and labor.
109.3 Building permit valuations.The applicant for a permit shall provide an estimated permit value at time
of application. Permit valuations shall include total value of work, including materials and labor, for which the
permit is being issued, such as electrical, gas, mechanical, plumbing equipment and permanent systems. If, in
the opinion of the building official,the valuation is underestimated on the application,the permit shall be
denied, unless the applicant can show detailed estimates to meet the approval of the building official. Final
building permit valuation shall be set by the building official.
City policy indicates that permit valuation includes materials and labor for the structure and mechanical,
electrical, plumbing and gas,fire sprinkler and elevator systems and equipment. Permanent systems such as
audio visual, lighting and HVAC controls are included in the total as are expenses directly related to construction
such as equipment rental and contractor fees. Finish materials such as paint,floor coverings, tile, cabinets and
counter tops are included in the permit valuation total.
Costs such as architectural and engineering design fees, landscaping and planting,tap fees, development
mitigation fees, trash removal, and cleaning are not included.
I certify that the permit valuation entered on the permit application for this property complies with the above
valuation requirements. I understand that this document is a public document.
Owner Signature: Date:
Owner Printed Name:
or,
Authorized Agent Signature: VA ate:8/14/18
Authorized Agent Printed Name: rally dupps
CITY OF ASPEN August2017 130 S. GALENA ST I ASPEN, CO §04�1., ols
ASPEN
BUILDING DEPARTMENT
ADDRESS: PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
ZONING COMPLIANCE VERIFICATION POLICY
THE CITY OF ASPEN
Applicability:All development projects must comply with the City's zoning regulations, including height and
location, and are subject to periodic inspection during construction and a final inspection prior to project
completion. When required by the City's Zoning Officer, certain development projects within the City of Aspen
shall verify height and/or location compliance through submission of a survey report.
Unless otherwise exempted, all commercial, multi-family, lodging, and mixed-use projects proposed within one
foot of the maximum permissible height or within one foot of allowable setbacks shall verify zoning compliance
through this method.
In addition, the Zoning Officer may require this method be used to verify zoning compliance for single-family/
duplex development or other projects where compliance may be in question. Independent of this policy, all
projects must comply with all applicable zoning limitations.
The Zoning Officer will inform the applicant during building permit review if verification will be required.
However, circumstances may require zoning compliance verification of a project which is already underway.
Timing: Height verification should be accomplished at a point of construction when enough roof structure is in
place to accurately measure the structure yet early enough in the process to still make changes if the structure
is too tall. Location verification should be accomplished at a point of construction when the final exterior of the
structure can be accurately measured in relation to setback requirements. Applicants are encouraged to confer
with the Zoning Officer regarding the timing of zoning compliance verification.Applicants are encouraged to
perform their own verification during construction to ensure the building is progressing to plan, including the
height and location of foundation forms prior to concrete pours.
Survey Report:A Colorado Professional Land Surveyor shall describe and depict the height and location of a
structure compared to the dimensions shown on the zoning sheets of the approved building permit plan set.The
City's Zoning Officer can assist in determining which elements of the structure should be measured and if natural
or finished grade should be used.
The report shall include the following information:
1-A brief cover letter with the building permit number, name of the project, name of the owner and general
contractor,with a written description of the measurement methods including date(s) of measurement.
2-For location verification:A plan drawing showing property boundaries, permitted setbacks, building envelope
(if applicable), location of foundation walls, location of the outermost exterior of each structure (inclusive of all
exterior veneer or other exterior treatments), and the location and dimension of each observed measurement.
3-For height verification: Elevation drawing(s) showing the natural or finished grade of the property, maximum
permitted height, building elevations including the nominal roof form (inclusive of the first layer of exterior
sheathing or weatherproofing membrane but excluding all exterior surface treatments such as shakes, shingles,
or other veneer treatments orornamentation), and the location and dimension of each observed measurement.
Additional roof plans showing location of measurements may be necessary.
CITY OF ASPEN August2017 130 S. GALENA ST I ASPEN, CO ¢
1 018
ASPEN
BUILDING DEPARTMENT
PERMIT NUMBER: ADDRESS: 121 s galena st
COMMUNITY DEVELOPMENT DEPARTMENT
ZONING COMPLIANCE VERIFICATION POLICY THE CITY OF ASPEN
4-Plans and elevations must include height or setback exemption items unique to the building, such as stair/
elevator overruns, utility/mechanical apparatus, hot tubs and spas, and other height or setback exemption items
unique to the project.
5-The report shall include a written description or drawing notes of the benchmarks or control points used to
establish property boundaries, setbacks, building location, building height,and grades for each measurement.
6-All drawings must correlate with the building locations, elevations, and grading/drainage representations in
the approved building permit set.
7-The report must include the signature, date, and stamp of Colorado Professional Land Surveyor who
conducted the field measurements certifying that the field measurements areaccurately represented.
Review and Acceptance of Report:The Zoning Officer shall review the report(s) and either confirm the project
conforms to the dimensions shown on the zoning sheets of the approved building permit plan set and meets
the zoning limitations for the property or shall determine which elements of the project are not in compliance.
The Zoning Officer may request additional information to verify zoning compliance, which may include but is not
limited to additional survey work or a site visit.
All drawings of the survey report must correlate with representations in the approved building permit set for
acceptance. Modifications to field conditions or amendments to the building permit may be required.
A determination of non-compliance shall result in the issuance of a correction notice and possible work
stoppage. Applicants are encouraged to verify zoning compliance as early as reasonably practical in the
construction process to minimize disruption to the construction schedule.
Acknowledgment:
I (contractor name) rally dupps understand this policy. I agree that this project will
comply with the zoning limitations affecting this parcel and the representations made on the zoning sheets of
the approved building permit plans. I understand that a Certificate of Occupancy will not be issued until this
project complies with all applica
ble zoning limitations.
Contractor Signature:
Date: 8/14/18
CITY OF ASPEN August2017 130 S. GALENA ST I ASPEN, CO §$�1 1 �,
� / 018
ASPEN
BUILDING DEPARTMENT
Homeowner Association Compliance Policy
All land use applications within the City of Aspen are required to include a Homeowner Association
Compliance Form (this form) certifying the scope of work included in the land use application complies
with all applicable covenants and homeowner association policies. The certification must be signed by
the property owner or Attorney representing the property owner.
Property Name: JODIV- 0-OLD(N6 S LL (--
Owner("I"): Email: Phone No.: q
�v.lnq;5F; el& e�'`lclil' LUw+ 1-10 -30cl S SD 1
Address of 12\ S r u1E J.A S`t
Property:
(subject of 5FF P3 t
application)
I certify as follows: (pick one)
This property is not subject to a homeowners association or other form of private covenant.
n This property is subject to a homeowners association or private covenant and the improvements
proposed in this land use application do not require approval by the homeowners association or
covenant beneficiary.
n This property is subject to a homeowners association or private covenant and the improvements
proposed in this land use application have been approved by the homeowners association or
covenant beneficiary.
I understand this policy and I understand the City of Aspen does not interpret, enforce, or manage the
applicability, meaning or effect of private covenants or homeowner association rules or bylaws. I
understand that this document is publi docume t. /
. /Owner signature: date: '1" ( c t 11
7
Owner printed name: }\11G .- E-k-'6- Sf I LD
or,
Attorney signature: date:
Attorney printed name:
RECEIVED
08/16/2018
ASPEN
BUILDING DEPARTMENT
MASTER PERMIT# 0083.2018.ACBK
ACHANGE ORDER#
/ \ CHANGE ORDER#
THE CITY OF ASPEN A\ CHANGE ORDER#
Building Description Form - IBC
Property Location:
Address: t21 S Ghter-J 51- Unit#:
Legal Description: (lot, Block) L0 cg. (6-1 LOT 5
Owner: GobttrA E80 -DtOGS LLC
Owner Address: 4Z,� W MA-{t.i c-f 1 SPEN C.) 6((, ( I
Parcel ID#: 2.13"1 a"1333 pc o i
Building Code Information
2015 IBC, IMC, IECC, IPC, IFGC, AND IFC; 2017 NEC
Code Editions: 2009 IBC 2009 IMC 2009 IPC 2009 IFCC 2009 IECC 2009 IFC 2011 NEC
Fire Sprinkler System Installed: )( NO YES Fire Alarm Installed: X NO YES
NFPA
Type of Construction: VA )( VB IVA IIIA IIIB IIA IIB IA
IB
Occupancy Group(s) A-1 2 3 4 5 )( B E F-1 2
H-1 2 3 4 5 I-1 2 3 4 M R-1 2 3 4
S-1 2 U
Separated Occupancies Non-Separated Occupancies
Occupant Load(s) 41.
Required Special Inspections: High Strength Bolting Epoxy Anchors Structural Steel Welding
Permanent Micropiles k Other(specify): Pcot E-
Energy Code Compliance Path: COMMERCIAL:
Prescriptive Table COMCheck U-factor Alternative
)( COMCheck UA Alternative Total Building Performance
RESIDENTIAL:
Prescriptive Table ResCheck Performace ResCheck UA Tradeoff
External Energy Use Snowmelt 0 sq ft Existing 0 sq ft New Spa Pool
Building Description eta*xt‘kiErtx Au $Ut LOW 6 'tV/ UP Pet i.EVEi.
# Stories Above Grade Plane 'Z # Stories Below Grade Plane
Reviewed by
Plans Examiner Date
9/6/18
IBC Building Description Form New Gdrive/master files/building/apps,forms checklists RECEIVED
08/16/2018
ASPEN
BUILDING DEPARTMENT
City of Aspen - Asbestos Checklist
Project Address: 121 S 6,A(€?kJ A ` JsskSPEtJ
THE CITY OF ASPEN
Parcel ID#: 2-1'23-1 CI 33 D Db-7
Asbestos is a known human carcinogen and is an airborne hazard. Once airborne,asbestos fibers can stay suspended in the air
for days, weeks or even months before settling out of the air, only to become airborne again from some minor disturbance,such as
turning on an air conditioner. Uncontrolled asbestos abatement projects or renovation projects that disturb asbestos may cause
latent asbestos hazards that could expose people to asbestos in the future,long after the renovation activity occurred. The
airborne asbestos fiber concentrations resulting from disturbances may result in a significant exposure to the current and future
occupants of the home.
The 1989 "Ban" on asbestos-containing materials is commonly misunderstood. In fact, in 1991 the
U.S. Fifth Circuit Court of appeals vacated much of the so-called "Asbestos Ban and Phaseout
Rule" and remanded it to the EPA. Thus, much of the original 1989 EPA ban on the U.S.
manufacturing, importation, processing, or distribution in commerce of many asbestos-containing
product categories was set aside and DID NOT TAKE EFFECT. Therefore, ALL demolition, remodel
or renovation projects must determine if disturbed material above the trigger levels contains
asbestos.
1. Residential: Will you be removing more than 32 sq ft, 50 linear feet(e.g., pipe insulation), or the volume
equivalent of a 55-gallon drum of any material besides concrete, wood, bricks or steel—examples are
drywall, linoleum, ceiling tiles, roofing materials, etc.? 0 NO 11 YES
2. Commercial: Will you be removing more than 160 sq ft, 260 linear feet (e.g., pipe insulation), or the
volume equivalent of a 55-gallon drum of any material besides concrete, wood, bricks or steel—
examples are all, linoleum, carpet, carpet adhesives, ceiling tiles, roofing materials, etc.?
NO YES
3. Will you be completely demolishing the building? NO 0 YES
If the answer is YES to any of the above, you will need an asbestos test before you can apply for a
building and/or demolition permit. A state certified asbestos inspector must do this test and the test
report must be submitted with the building permit application. If the building has asbestos, a state certified
asbestos abatement firm must remove it. After removal, the abatement firm must provide a letter to the
Building Division stating that all the asbestos has been removed and that the air is clean. This letter must
be received BEFORE a permit will be issued. (See the local or statewide Yellow Pages, DexOnLine, or
http://www.cdphe.state.co.us/ap/asbestos/index.html for certified asbestos inspectors and abatement companies.
ALWAYS ask for proof of current state certification.)
If YES to question#3, you must submit a demolition permit app with the CDPHE in addition to the Aspen
permit app. This form may be found at http://www.cdphe.state.co.us/ap/asbestos/asdemo.pdf NOTE: A copy
of this demolition permit app must be submitted with the initial building permit application. When the CDPHE
approves the app,their issued permit must be given to the Aspen Building Dept before we issue our permit.
I hereby certify that the above information is true and complete.
GM kki k OLQIN&S L-LC.
Owner lul l t,C E beiS F 1 1) Phone# 110 3 01. SST i
Applicant (print name) 2 1.-L'f pU P PS Phone# 11-0 4( '1 3 c 3
Applicant Signature 1e Date / i1
Please call the City of Aspen Environmental Health Department at 920-5039 at any time if you have questions
about asbestos, interpreting your test results, or other matters.
Webpage: http://www.aspenpitkin.com/pdfs/depts/41/asbestosquestionnaire.pdf Rev. 02-10
08/16/2018
ASPEN
BUILDING DEPARTMENT
Rally Dupps architect
POB 3662
Aspen,CO 81612-3662
www.rallyduppsarchitect.com
email: rallyduppsc gmail.com
AUTHORIZATION TO REPRESENT
TO: City of Aspen Community Development
FROM: Godiva Holdings LLC
435 E. Main St
Aspen, CO 81611
DATE: April 5, 2017
I hereby authorize Rally Dupps of Rally Dupps Architect to represent the owner for
purposes of a land use application and a building permit for 121 S Galena St in Aspen,
CO.
Sincerely,
Godiva Holding, , LLC
•
RECEIVED