HomeMy WebLinkAboutFile Documents.535 E Cooper Ave.0004.2019 (19).ACBK RECEIVED
1/7/20 9
H-P--- KUMAR
5020 County Road 154
ASPEN Glenwood Springs, CO 81601
BUILDING DEPARnical Engineering I Engineering Geology g
als Testing I Environmental Phone: (970)945-7988
Fax: (970)945-8454
Email: hpkglenwood@kumarusa.com
Office Locations: Denver(HQ), Parker, Colorado Springs, Fort Collins,Glenwood Springs,Summit County, Colorado
SUBSOIL STUDY
FOR FOUNDATION DESIGN
PROPOSED STEIN ERIKSEN BUILDING ADDITION
529-535 EAST COOPER AVENUE
ASPEN, COLORADO
PROJECT NO. 18-7-522
SEPTEMBER 24, 2018
PREPARED FOR:
NJ STEIN,LLC
do ANDREW HECHT
ATTN: DON CARPENTER
625 EAST HYMAN AVENUE,#201
ASPEN, COLORADO 81611
don@projectresourceco.com
RECEIVED
1/7/2019
ASPEN
BUILDING DEPARTMENT
TABLE OF CONTENTS
PURPOSE AND SCOPE OF STUDY - 1 -
PROPOSED CONSTRUCTION - 1 -
SITE CONDITIONS - 1 -
MINE SUBSIDENCE - 2 -
FIELD EXPLORATION - 2 -
SUBSURFACE CONDITIONS - 3 -
FOUNDATION BEARING CONDITIONS - 3 -
DESIGN RECOMMENDATIONS - 3 -
FOUNDATIONS - 3 -
FOUNDATION AND RETAINING WALLS -4 -
FLOOR SLABS - 6 -
UNDERDRAIN SYSTEM - 6 -
SURFACE DRAINAGE - 7 -
DRYWELL - 7 -
LIMITATIONS - 7 -
FIGURE 1 - LOCATION OF EXPLORATORY BORING
FIGURE 2 - LOG OF EXPLORATORY BORING
FIGURE 3 - GRADATION TEST RESULTS
TABLE 1- SUMMARY OF LABORATORY TEST RESULTS
TABLE 2-PERCOLATION TEST RESULTS
H-PvKUMAR
Project No. 18-7-522
RECEIVED
1/7/2019
ASPEN
BUILDING DEPARTMENT PURPOSE AND SCOPE OF STUDY
This report presents the results of a subsoil study for a proposed addition to the Stein Eriksen
building located at 529-535 East Cooper Avenue, Aspen, Colorado. The project site is shown on
Figure 1. The purpose of the study was to develop recommendations for the foundation design.
The study was conducted in accordance with our proposal for geotechnical engineering services
to NJ Stein, LLC dated July 30, 2018.
An exploratory boring was drilled to obtain information on the subsurface conditions. Samples
of the subsoils obtained during the field exploration were tested in the laboratory to determine
their classification, and other engineering characteristics. The results of the field exploration and
laboratory testing were analyzed to develop recommendations for foundation types, depths and
allowable pressures for the proposed building foundation. This report summarizes the data
obtained during this study and presents our conclusions, design recommendations and other
geotechnical engineering considerations based on the proposed construction and the subsurface
conditions encountered.
PROPOSED CONSTRUCTION
The proposed building addition will be a 1 story structure attached to the north side of the
building. Ground floors will be structural over crawlspace and slab-on-grade. Grading for the
structure is assumed to be relatively minor with cut depths between about 3 to 5 feet. We
assume relatively light foundation loadings, typical of the proposed type of construction.
If building loadings, location or grading plans change significantly from those described above,
we should be notified to re-evaluate the recommendations contained in this report.
SITE CONDITIONS
The subject site was a developed lot with apartments and commercial sections at the time of our
field exploration. The ground surface is graded mostly flat about 2 feet below the alley
elevation. Elevation difference across the building addition area is about 2 feet. Vegetation
consists of landscaped trees, bushes and shrubs.
H-PvKUMAR
Project No. 18-7-522
RECEIVED
1/7/2019 - 2 -
ASPEN MINE SUBSIDENCE
BUILDING DEPARTMENT
Portions of the Aspen area are underlain by mine workings. The workings are primarily
underground tunnels between Aspen and Smuggler Mountains southeast and east of the
downtown area. The works consist of numerous tunnels beginning a few hundred feet below the
ground surface becoming shallower to the south. Under certain conditions these workings may
collapse and cause surface subsidence. Glory Hole Park, which is about three blocks southeast
of the subject site, is believed to have been caused by the collapse of one or more tunnels. The
subject site appears to be west of these main tunnel works.
Our borings were relatively shallow and for foundation design only, however, no indications of
subsurface voids were found at the subject site. We believe the risk of subsidence due to the
collapse of underground mine works throughout the service life of the proposed development to
be low. If further evaluation of the mine works subsidence potential is desired, we should be
contacted.
FIELD EXPLORATION
The field exploration for the project was conducted on September 12, 2018. One exploratory
boring was drilled at the location shown on Figure 1 to evaluate the subsurface conditions. The
boring was advanced with 4 inch diameter continuous flight augers powered by a truck-mounted
CME-45B drill rig. The boring was logged by a representative of H-P/Kumar.
Samples of the subsoils were taken with a 1% inch I.D. spoon sampler. The sampler was driven
into the subsoils at various depths with blows from a 140 pound hammer falling 30 inches. This
test is similar to the standard penetration test described by ASTM Method D-1586. The
penetration resistance values are an indication of the relative density or consistency of the
subsoils. Depths at which the samples were taken and the penetration resistance values are
shown on the Log of Exploratory Boring, Figure 2. The samples were returned to our laboratory
for review by the project engineer and testing.
H-PyKUMAR
Project No. 18-7-522
RECEIVED
1/7/2019 - 3 -
ASPEN SUBSURFACE CONDITIONS
BUILDING DEPARTMENT
A graphic log of the subsurface conditions encountered at the site is shown on Figure 2. The
subsoils consist of about 6 inches of concrete over 4 inches of base course overlying silty sand
and gravel fill to 5 feet underlain by medium dense to dense, slightly silty sand and gravel with
cobbles to the drilled depth of 16 feet.
Laboratory testing performed on samples obtained from the boring included natural moisture
content and gradation analyses. Results of gradation analyses performed on a small diameter
drive sample (minus 11h inch fraction) of the coarse granular subsoils are shown on Figure 4.
The laboratory testing is summarized in Table 1.
No free water was encountered in the boring at the time of drilling and the subsoils were slightly
moist to moist.
FOUNDATION BEARING CONDITIONS
The upper 5 feet of subsoils encountered at the site consists of man placed fill that is unsuitable
for foundation and floor slab support. The underlying relatively dense, slightly silty sand and
gravel with cobbles soils possess moderate bearing capacity and low settlement potential. At
proposed excavation depths for the foundation, we expect the subgrade will consist of the natural
slightly silty sand and gravel soils. Shallow excavations may need to be deepened to expose
natural coarse granular soils and the sub-excavated depth backfilled with compacted structural
fill. A spread footing foundation system should be feasible for foundation support of the
structure with a low risk of differential movement.
DESIGN RECOMMENDATIONS
FOUNDATIONS
Considering the subsurface conditions encountered in the exploratory boring and the nature of
the proposed construction, we recommend the building addition be founded with spread footings
bearing on the natural granular soils or compacted structural fill.
H-PWUMAR
Project No. 18-7-522
RECEIVED
1/7/2019 -4 -
ASPEN, ign and construction criteria presented below should be observed for a spread footing
BUILDING DEPAR � b
foundation system.
1) Footings placed on the undisturbed natural granular soils or compacted structural
fill should be designed for an allowable bearing pressure of 2,500 psf. Based on
experience, we expect settlement of footings designed and constructed as
discussed in this section will be about 1 inch or less.
2) The footings should have a minimum width of 18 inches for continuous walls and
2 feet for isolated pads.
3) Exterior footings and footings beneath unheated areas should be provided with
adequate soil cover above their bearing elevation for frost protection. Placement
of foundations at least 42 inches below exterior grade is typically used in this
area.
4) Continuous foundation walls should be reinforced top and bottom to span local
anomalies such as by assuming an unsupported length of at least 12 feet.
Foundation walls acting as retaining structures should also be designed to resist
lateral earth pressures as discussed in the "Foundation and Retaining Walls"
section of this report.
5) The existing fill, debris and loose disturbed soils should be removed and the
footing bearing level extended down to the relatively dense natural granular soils.
The exposed soils in footing area should then be moistened and compacted.
Structural fill used to reestablish design bearing level should consist of a
relatively well graded granular material compacted to at least 98% of standard
proctor density at near optimum moisture content.
6) A representative of the geotechnical engineer should observe all footing
excavations prior to concrete placement to evaluate bearing conditions.
FOUNDATION AND RETAINING WALLS
Foundation walls and retaining structures which are laterally supported and can be expected to
undergo only a slight amount of deflection should be designed for a lateral earth pressure
computed on the basis of an equivalent fluid unit weight of at least 45 pcf for backfill consisting
of the on-site granular soils. Cantilevered retaining structures which are separate from the
H-P-WUMAR
Project No. 18-7-522
RECEIVED
1/7/2019 - 5 -
ASP E n and can be expected to deflect sufficiently to mobilize the full active earth pressure
BUILDING DEPAMIE
condition (if any) should be designed for a lateral earth pressure computed on the basis of an
equivalent fluid unit weight of at least 40 pcf for backfill consisting of the on-site granular soils.
All foundation and retaining structures should be designed for appropriate hydrostatic and
surcharge pressures such as adjacent footings, traffic, construction materials and equipment. The
pressures recommended above assume drained conditions behind the walls and a horizontal
backfill surface. The buildup of water behind a wall or an upward sloping backfill surface will
increase the lateral pressure imposed on a foundation wall or retaining structure. An underdrain
should be provided to prevent hydrostatic pressure buildup behind walls.
Backfill should be placed in uniform lifts and compacted to at least 95% of the maximum
standard Proctor density at a moisture content near optimum. Backfill placed in pavement and
walkway areas should be compacted to at least 95% of the maximum standard Proctor density.
Care should be taken not to overcompact the backfill or use large equipment near the wall, since
this could cause excessive lateral pressure on the wall. Some settlement of deep foundation wall
backfill should be expected, even if the material is placed correctly, and could result in distress to
facilities constructed on the backfill. Backfill should not contain organics, debris or rock larger
than about 6 inches.
The lateral resistance of foundation or retaining wall footings will be a combination of the
sliding resistance of the footing on the foundation materials and passive earth pressure against
the side of the footing. Resistance to sliding at the bottoms of the footings can be calculated
based on a coefficient of friction of 0.45. Passive pressure of compacted backfill against the
sides of the footings can be calculated using an equivalent fluid unit weight of 450 pcf. The
coefficient of friction and passive pressure values recommended above assume ultimate soil
strength. Suitable factors of safety should be included in the design to limit the strain which will
occur at the ultimate strength, particularly in the case of passive resistance. Fill placed against
the sides of the footings to resist lateral loads should be a granular material compacted to at least
95% of the maximum standard Proctor density at a moisture content near optimum.
H-P <UMAR
Project No. 18-7-522
RECEIVED
1/7/2019 - 6 -
ASPE(�
BUILDING DEPARR SLABS
The natural on-site granular soils, exclusive of man placed fill, are suitable to support lightly
loaded slab-on-grade construction. To reduce the effects of some differential movement, floor
slabs should be separated from all bearing walls and columns with expansion joints which allow
unrestrained vertical movement. Floor slab control joints should be used to reduce damage due
to shrinkage cracking. The requirements for joint spacing and slab reinforcement should be
established by the designer based on experience and the intended slab use. A minimum 4 inch
layer of free-draining gravel should be placed beneath basement level slabs to facilitate drainage.
This material should consist of minus 2 inch aggregate with at least 50% retained on the No. 4
sieve and less than 2% passing the No. 200 sieve.
All fill materials for support of floor slabs should be compacted to at least 95% of maximum
standard Proctor density at a moisture content near optimum. Required fill can consist of the on-
site granular soils devoid of vegetation, topsoil and oversized rock.
UNDERDRAIN SYSTEM
Although free water was not encountered during our exploration, it has been our experience in
the area that local perched groundwater can develop during times of heavy precipitation or
seasonal runoff. Frozen ground during spring runoff can create a perched condition. We
recommend below-grade construction, such as retaining walls, crawlspace and basement areas,
be protected from wetting and hydrostatic pressure buildup by an underdrain system.
The drains should consist of drainpipe placed in the bottom of the wall backfill surrounded above
the invert level with free-draining granular material. The drain should be placed at each level of
excavation and at least 1 foot below lowest adjacent finish grade and sloped at a minimum 1% to
a suitable gravity outlet, sump and pump, or drywell. Free-draining granular material used in the
underdrain system should contain less than 2% passing the No. 200 sieve, less than 50%passing
the No. 4 sieve and have a maximum size of 2 inches. The drain gravel backfill should be at
least 11 feet deep.
H-P-WUMAR
Project No. 18-7-522
RECEIVED
1/7/2019 - 7 -
ASPPII�T Tpp ACE DRAINAGE
BUILDING DEPArfl IST
The following drainage precautions should be observed during construction and maintained at all
times after the addition has been completed:
1) Inundation of the foundation excavations and underslab areas should be avoided
during construction.
2) Exterior backfill should be adjusted to near optimum moisture and compacted to
at least 95% of the maximum standard Proctor density in pavement and slab areas
and to at least 90% of the maximum standard Proctor density in landscape areas.
3) The ground surface surrounding the exterior of the building should be sloped to
drain away from the foundation in all directions. We recommend a minimum
slope of 6 inches in the first 10 feet in unpaved areas and a minimum slope of 21/
inches in the first 10 feet in paved areas. Free-draining wall backfill should be
covered with filter fabric and capped with about 2 feet of the on-site, finer graded,
soils to reduce surface water infiltration.
4) Roof downspouts and drains should discharge well beyond the limits of all
backfill.
DRYWELL
Drywells and bio-swales are often used in the Aspen area for site runoff detention and disposal.
The Natural Resources Conservation Service has identified four hydrologic groups (HSG) in the
Aspen area and the site is located in Type B soil having a moderate infiltration rate. The results
of percolation testing performed in Boring 1, presented in Table 2, indicate an infiltration rate
between about 2 to 5 minutes per inch. The bedrock is generally known to be relatively deep in
this area and groundwater level was not encountered to the boring depth of 16 feet. The drywell
should have solid casing down to at least basement level and perforation below that level.
LIMITATIONS
This study has been conducted in accordance with generally accepted geotechnical engineering
principles and practices in this area at this time. We make no warranty either express or implied.
H-PtiKUMAR
Project No. 18-7-522
RECEIVED
1/7/2019 - 8 -
ASPEN'tneclusions and recommendations submitted in this report are based upon the data obtained
BUILDING DEPARI
from the exploratory boring drilled at the location indicated on Figure 1, the proposed type of
construction and our experience in the area. Our services do not include determining the
presence,prevention or possibility of mold or other biological contaminants (MOBC) developing
in the future. If the client is concerned about MOBC, then a professional in this special field of
practice should be consulted. Our findings include interpolation and extrapolation of the
subsurface conditions identified at the exploratory boring and variations in the subsurface
conditions may not become evident until excavation is performed. If conditions encountered
during construction appear different from those described in this report, we should be notified so
that re-evaluation of the recommendations may be made.
This report has been prepared for the exclusive use by our client for design purposes. We are not
responsible for technical interpretations by others of our information. As the project evolves, we
should provide continued consultation and field services during construction to review and
monitor the implementation of our recommendations, and to verify that the recommendations
have been appropriately interpreted. Significant design changes may require additional analysis
or modifications to the recommendations presented herein. We recommend on-site observation
of excavations and foundation bearing strata and testing of structural fill by a representative of
the geotechnical engineer.
Respectfully Submitted,
H-P,z,KUMAR
974,/
James H. Parsons, E.I.
Reviewed by: _
4 ''
�f . 16222
Steven L. Pawlak,
JHP/kac ""
H-P-KUMAR
Project No. 18-7-522
RECEIVED
1/7/2919 `
ASPS
G 1
BUILDING DEPA TMENT
WESTERLY 25'OF LOT G
I I ASPEN GROVE 1
BUILDING
I—II '1L:' 1 = j . t.s,
.e
�,p.t ■E. • wrv�o ��
>6 RW
®!!: - •1'•°O• EASTERLY S.OF LOT G SO 5
'^I t�6V
/ N - v 2 75 \ L a
AVAIL
I
��'°wil
LOTN I *A
�Y5 a a
ce
CONCRETE i u O
l' �'; (� so
SLOPE. BORING 21 - 2 \,=�
i17
(61F �,Ea `.,
BOWMAN �'
�� BUILDING
ALEY >..
I..R.LO.W., NAV !III! I I a 3 w ,� R PARK
IGN
O
10
— (0...„,.) 0,... — ea,6 PROPERTY LJNE {}
1 a17 w.E a.rz ENTRY ENTRY LIGHT
POLE
CONCRETE
S oEWALK i
a�1 \/7�1 \---� ..., , I \tom 1 f�l
1.r :`��:_��-47Z�ice.��:=
I\ I\. ;I OIL
0 •
'W'
HUNTER STREET
I.
1���
10 0 10 20
APPROXIMATE SCALE—FEET
18-7-522 H-PtiKIJMAR LOCATION OF EXPLORATORY BORING Fig. 1
RECEIVED
1/7/2019
BORING 1 LEGEND
ASPEN
BUILDING DEPA' 11 61 T (6) CONCRETE, THICKNESS IN INCHES SHOWN IN PARENTHESES TO
/6) 1111111111 LEFT OF THE LOG.
11
• (4) BASE COURSE, THICKNESS IN INCHES SHOWN IN PARENTHESES
:4.
8/121: TO LEFT OF THE LOG.
r4.
FILL: SAND AND GRAVEL, SILTY, LOOSE, MOIST, DARK
5 0#70' 35/12 BROWN.
SAND AND GRAVEL (SM—GM): SLIGHTLY SILTY, COBBLES,
WC=1.4 MEDIUM DENSE TO DENSE, SLIGHTLY MOIST, BROWN GRAY,
—200=7 ROUNDED ROCK.
w '
= 10 DRIVE SAMPLE, 1 3/8—INCH I.D. LINER SAMPLE.
50/3
o_
w
8/12 DRIVE SAMPLE BLOW COUNT. INDICATES THAT 8 BLOWS OF
A 140—POUND HAMMER FALLING 30 INCHES WERE REQUIRED
TO DRIVE THE SAMPLER 12 INCHES.
15
30/6, 50/4
WC=4.0
+4=47 NOTES
—200=9
1. THE EXPLORATORY BORING WAS DRILLED ON SEPTEMBER 12, 2018
WITH A 4—INCH DIAMETER CONTINUOUS FLIGHT POWER AUGER.
20 2. THE LOCATION OF THE EXPLORATORY BORING WAS MEASURED
APPROXIMATELY BY PACING FROM FEATURES SHOWN ON THE SITE
PLAN PROVIDED.
3. THE ELEVATION OF THE EXPLORATORY BORING WAS NOT
MEASURED AND THE LOG OF THE EXPLORATORY BORING IS
PLOTTED TO DEPTH.
4. THE EXPLORATORY BORING LOCATION SHOULD BE CONSIDERED
ACCURATE ONLY TO THE DEGREE IMPLIED BY THE METHOD USED.
5. THE LINES BETWEEN MATERIALS SHOWN ON THE EXPLORATORY
BORING LOG REPRESENT THE APPROXIMATE BOUNDARIES BETWEEN
MATERIAL TYPES AND THE TRANSITIONS MAY BE GRADUAL.
6. GROUNDWATER WAS NOT ENCOUNTERED IN THE BORING AT THE
TIME OF DRILLING.
7. LABORATORY TEST RESULTS:
WC = WATER CONTENT (%) (ASTM D 2216);
+4 = PERCENTAGE RETAINED ON NO. 4 SIEVE (ASTM D 422);
—200 = PERCENTAGE PASSING NO. 200 SIEVE (ASTM D 1140).
18-7-522 H-P- -KUMAR LOG OF EXPLORATORY BORING Fig. 2
RECEIVED
1/ I / O I w9 HYDROMETER ANALYSIS SIEVE ANALYSIS
1 TIME READINGS U.S. STANDARD SERIES CLEAR SQUARE OPENINGS
24 HRS 7 HRS
100 45 MIN 15 MIN 6OMIN 19MIN ♦MIN 1MIN COO f100 /50/40/30 /1 1 /8 /4 3/8" 3/4" 1 1 2" 3" 5"6" 8"0
ASPEN ,
BUILDING JEPARTMI)NT +- 1__ _ - 1 , 1 - 70
80
20
70
30
f I
60 ( I
40
t rg
C, I �— —I 50 8`
a 40
60
30 _ r ( 70
zo i __T — — — ! — I
_ —_ — 1 ! ao
10�-- I --- I i —
I 90
o I I
.001 .002 i (.005i .009 .0119 .037 1 I.0751 I .150 I .300 I I I.600 I 1 11.18 !2.361 14.75 I 1 19.5 19 1 38.1 I 176.2t 1127 200
.425 2.0I DIAMETER OF PARTICLES IN MILLIMETERS 152
I
CLAY TO SILT SAND GRAVEL
FINE MEDIUM COARSE FINE COARSE COBBLES
GRAVEL 47 X SAND 44 X SILT AND CLAY 9 X
SAMPLE OF: Slightly Silty Sand and Gravel FROM: Boring 1 0 15'
These test results apply only to the
samples which were tested. The
testing report shall not be reproduced,
except In full, without the written
approval of Kumar & Associates, Inc.
Sieve analysis testing Is performed In
accordance with ASTM D422, ASTM C136
and/or ASTM D1140.
18-7-522 H-PtiKUIVIAR GRADATION TEST RESULTS Fig. 3
RECEIVED
N
1/7/201 °d
NI. "c1 --
r
ASPEN 00 r 0
BUILDING DEPARTgENT a =
� c
a o
•o co �n v)
L.
d >, >,
y
.an tu
v, C7vDC7
a
W>2
Oaf S
Fes-- ZoN
U
D
a QD o 17)
J az
w ix
m
2 . W =~ °
k a-
O Q J J
L!J Ix
J ® Zz0W
0WQ Z CO ci CI)
0-1 0 ON IIIIIIII III I
zo d
O 0 �r
a
2
Q J
(1) Q c
x
0
J
cc)-m cc - V
F-O W a
Z O
HW I . _J�Z
QQZ
o . O
<00
Z m 0
Z 2 O N
111
V 0 If) •-
O v
J
d Z
0
m
RECEIVED
1/7/2019
ASPEN
H-PKUMAR
BUILDING DEPARTMENT TABLE 2
PERCOLATION TEST RESULTS
PROJECT NO. 18-7-522
HOLE NO. HOLE LENGTH OF WATER WATER DROP IN AVERAGE
DEPTH INTERVAL DEPTH AT DEPTH AT WATER PERCOLATION
(INCHES) (MIN) START OF END OF LEVEL RATE
INTERVAL INTERVAL (INCHES) (MIN./INCH)
(INCHES) (INCHES)
B-1 106 2 48 34 14
0.14
34 30 4 0.5
30 28 2 1
4 28 27 1 4
5 27 25 2 2.5
25 23 2 2.5
23 22 1 5
22 21 1 5
21 20 1 5
20 19 1 5
Note: The percolation test was conducted in the completed 4-inch diameter borehole
on September 12, 2018.