HomeMy WebLinkAboutFile Documents.535 E Cooper Ave.0004.2019 (20).ACBK RECEIVED
l COMcheck Software Version 4.1.1.0
Interior Lighting Compliance Certificate
BUILDIN DE TM NT
Project Information Fill out the
Energy Code: 2015 IECC owner/agent section of
Project Title: Stein Bldg the lighting comcheck.
Project Type: Alteration
Construction Site: Owner/Agent: Designer/Contractor:
529-535 E Cooper AVE BGbuildingworks
Aspen, CO 81611 PO Box 9650
Avon, CO 81620
970.949.6108
Allowed Interior Lighting Power
A B C D
Area Category Floor Area Allowed Allowed Watts
(ft2) Watts/ft2 (B X C)
1-Unit#1 101 (Retail:Sales Area) 875 1.59 1391
2-Unit#2 102(Retail:Sales Area) 239 1.59 380
3-Unit#3 103(Retail:Sales Area) 466 1.59 741
4-Unit#4 104(Retail:Sales Area) 720 1.59 1145
5-Unit#5 105(Retail:Sales Area) 1156 1.59 1838
6-Unit#6 106(Retail:Sales Area) 927 1.59 1474
7-Common Corridor 111 (Common Space Types:Corridor/Transition<8 ft wide) 395 0.66 261
8-Unit#4 RR(Common Space Types:Restrooms) 58 0.98 57
9-Unit#5 RR(Common Space Types:Restrooms) 52 0.98 51
10-Unit#6 RR(Common Space Types:Restrooms) 34 0.98 33
11-Common Bath 112(Common Space Types:Restrooms) 52 0.98 51
12-Trash 110(Common Space Types:Storage>=50-<=1000 sq.ft.) 185 0.63 117
Total Allowed Watts= 7538
Proposed Interior Lighting Power
A B C D E
Fixture ID : Description/Lamp/Wattage Per Lamp/Ballast Lamps/ #of Fixture (C X D)
Fixture Fixtures Watt.
Unit#1 101 ( Retail:Sales Area 875 sq.ft.)
LED 1: R1:Other: 1 9 16 144
Track lighting 1:T2:Track Lighting: Wattage based on current limiting device capacity 0 0 480 480
Unit#2 102 ( Retail:Sales Area 239 sq.ft.)
LED 4: R1:Other: 1 10 16 160
Unit#3 103( Retail:Sales Area 466 sq.ft.)
LED 2: R1:Other: 1 9 16 144
LED 3:C1:Other: 1 2 192 384
Unit#4 104( Retail:Sales Area 720 sq.ft.)
LED 5: R1:Other: 1 1 16 16
Track lighting 2:T2: Wattage based on current limiting device capacity 0 0 720 720
Project Title: Stein Bldg Report date: 12/07/18
Data filename: S:\BGProjects\10014.00 Stein Building\Engineering\Energy\Calcs\Stein COMcheck.cck Page 1 of 6
RECEIVED
1/7/2019 A B C D E
fixture ID : Description/Lamp/Wattage Per Lamp/Ballast Lamps/ #of Fixture (C X D)
Fixture Fixtures Watt.
ASPEN
BUILDIWi AR5 € tail:Sales Area 1156 sq.ft.)
Track lighting 3:Ti: Wattage based on current limiting device capacity 0 0 720 720
Track lighting 4:T2: Wattage based on current limiting device capacity 0 0 840 840
Unit#6 106( Retail:Sales Area 927 sq.ft.)
LED 8: R1:Other: 1 1 16 16
LED 14:Other: 3 9 50 446
Common Corridor 111 (Common Space Types:Corridor/Transition<8 ft wide 395 sq.ft.)
LED 11:R2:Other: 1 10 11 110
Unit#4 RR(Common Space Types:Restrooms 58 sq.ft.)
LED 6:V1:Other: 1 1 18 18
Unit#5 RR(Common Space Types:Restrooms 52 sq.ft.)
LED 7:V1:Other: 1 1 18 18
Unit#6 RR(Common Space Types:Restrooms 34 sq.ft.)
LED 9:V1:Other: 1 1 18 18
Common Bath 112 (Common Space Types:Restrooms 52 sq.ft.)
LED 10:V1:Other: 1 1 18 18
Trash 110(Common Space Types:Storage>=50-<=1000 sq.ft. 185 sq.ft.)
LED 12:S1:Other: 1 3 25 75
Total Proposed Watts= 4326
Interior Lighting PASSES
Interior Lighting Compliance Statement
Compliance Statement: The proposed interior lighting alteration project represented in this document is consistent with the
building plans, specifications, and other calculations submitted with this permit application.The proposed interior lighting
systems have been designed to meet the 2015 IECC requirements in COMcheck Version 4.1.1.0 and to comply with any
applicable mandatory requirements listed in the Inspection Checklist.
Brent Schumacher, EIT- Electrical Engineer 12/10/2018
Name-Title Signature Date
Project Title: Stein Bldg Report date: 12/07/18
Data filename: S:\BGProjects\10014.00 Stein Building\Engineering\Energy\Calcs\Stein COMcheck.cck Page 2 of 6
RECEIVED
1/7 COMcheck Software Version 4.1.1.0
Inspection Checklist
BUILDIN DE TM NTEnergy Code: 2015 IECC
Requirements: 94.0% were addressed directly in the COMcheck software
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Section
# Plan Review Complies? Comments/Assumptions
& Req.ID
C103.2 Plans, specifications, and/or ❑Complies Requirement will be met.
[PR4]1 calculations provide all information Does Not
with which compliance can be Location on plans/spec: E0.2, E3.1
determined for the interior lighting ❑Not Observable
and electrical systems and equipment ❑Not Applicable
and document where exceptions to
the standard are claimed. Information
provided should include interior
lighting power calculations, wattage of
bulbs and ballasts,transformers and
control devices.
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Stein Bldg Report date: 12/07/18
Data filename: S:\BGProjects\10014.00 Stein Building\Engineering\Energy\Calcs\Stein COMcheck.cck Page 3 of 6
RECEIVED
i is? V,9Rough-In Electrical Inspection Complies? Comments/Assumptions
& Req.ID
Asp. .iti ;Lighting controls installed to uniformly ❑Complies Requirement will be met.
BUILDIC ARTIITe the lighting load by at least ❑Does Not
° ❑Not Observable Location on plans/spec: E3.1
' ❑Not Applicable
C405.2.1 i Occupancy sensors installed in ❑Complies Requirement will be met.
[EL18]1 I required spaces. ❑Does Not
❑Not Observable Location on plans/spec: E3.1
❑Not Applicable
C405.2.1, Independent lighting controls installed ❑Complies Requirement will be met.
C405.2.2. per approved lighting plans and all ❑Does Not
3 manual controls readily accessible and ❑Not Observable Location on plans/spec: E3.1
[EL23]2 visible to occupants.
ENot Applicable
C405.2.2. Automatic controls to shut off all ❑Complies Exception: Lighting controlled by occupancy sensors.
1 building lighting installed in all ❑Does Not
[EL22]2 buildings. ❑Not Observable Location on plans/spec: E3.1
❑Not Applicable
01 .3 Daylight zones provided with ;❑Complies Exception: Requirement does not apply.
individual controls that control the ❑Does Not
lights independent of general area
lighting. ❑Not Observable
❑Not Applicable
C405.2.3, Primary sidelighted areas are Complies Exception: Requirement does not apply.
C405.2.3. equipped with required lighting ❑Does Not
1, controls.
C405.2.3. ❑Not Observable,
2 ❑Not Applicable
[EL20]1
1
C405.2.3, Enclosed spaces with daylight area ;❑Complies Exception: Requirement does not apply.
C405.2.3. under skylights and rooftop monitors ❑Does Not
1, are equipped with required lighting
C405.2.3. controls. ❑Not Observable
3 ❑Not Applicable
[EL21]1
C405.2.4 Separate lighting control devices for EComplies Requirement will be met.
[EL4]1 specific uses installed per approved Does Not
lighting plans. Location on plans/spec: E3.1
❑Not Observable
❑Not Applicable
C405.2.4 Additional interior lighting power ❑Complies Requirement will be met.
[EL8]1 allowed for special functions per the ❑Does Not
approved lighting plans and is ❑Not Observable Location on plans/spec: E3.1
automatically controlled and
separated from general lighting. ❑Not Applicable
1
C405.3 Exit signs do not exceed 5 watts per ❑Complies Requirement will be met.
[EL6]1 face. ❑Does Not
❑Not Observable Location on plans/spec: E0.2
❑Not Applicable
Additional Comments/Assumptions:
High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3) '
Project Title: Stein Bldg Report date: 12/07/18
Data filename: S:\BGProjects\10014.00 Stein Building\Engineering\Energy\Calcs\Stein COMcheck.cck Page 4 of 6
RECEIVED
1/ 7 Vv 19 Final Inspection Complies? Comments/Assumptions
& Req.ID
N Furnished O&M instructions for ❑Complies
BUILDII RT V s and equipment to the ❑Does Not
. ng owner or designated
[F117]3 representative. ❑Not Observable
❑Not Applicable
C405.4.1 Interior installed lamp and fixture ❑Complies See the Interior Lighting fixture schedule for values.
[F118]1 lighting power is consistent with what ❑Does Not
is shown on the approved lighting
plans, demonstrating proposed watts ❑Not Observable
are less than or equal to allowed ❑Not Applicable
watts.
C408.2.5. :Furnished as-built drawings for ❑Complies
1 :electric power systems within 90 days ❑Does Not
[F116]3 of system acceptance.
❑Not Observable
❑Not Applicable
C408.3 1 Lighting systems have been tested to ❑Complies
[F133]1 ensure proper calibration, adjustment, ❑Does Not
programming, and operation. ❑Not Observable
❑Not Applicable
Additional Comments/Assumptions:
1 High Impact(Tier 1) 2 Medium Impact(Tier 2) 3 Low Impact(Tier 3)
Project Title: Stein Bldg Report date: 12/07/18
Data filename: S:\BGProjects\10014.00 Stein Building\Engineering\Energy\Calcs\Stein COMcheck.cck Page 5 of 6
RECEIVED
1/7/2019
ASPEN
BUILDING DEPARTMENT
Project Title: Stein Bldg Report date: 12/07/18
Data filename: S:\BGProjects\10014.00 Stein Building\Engineering\Energy\Calcs\Stein COMcheck.cck Page 6 of 6