HomeMy WebLinkAboutFile Documents.221 E Main St.0112.2018 (6).ACBK ASPEN RE-ROOFING APPLICATION CHECKLIST
[41 2015 IBC/IRC
For Building and Permit Information,please refer to our website at:
THE CITY OF ASPEN http://www.aspenpitkin.com/depts/41/main building.cfm
NOTE: This is a general list of required information.More information may be required as each project is individually evaluated. If the proposed
structure requires City Land Use Review,all final approvals must be obtained PRIOR to submission of a building permit application. Contact a city
planner at 970/920-509�07to determine if a Land Use Review is needed.
JOB ADDRESS 2` I F l'1Qi l S+ • PARCEL I.D.NUMBER Z} 3� 6-4 3L $OOZ
OWNER 15 q 3 t �,C, DATE: 1 0/ l h J I g
All reroofing projects require a roof nj'permit*
*Roof work involving changes to height,slope,footprint,structural framing,or cavity insulation requires a Building Permit.
*Patching less than 1 square(10'x10')does not require a permit.
Plea e submit the following:
5' Permit Application form completely filled out with accompanying 0 Contact Sheet
UK-MA Certification form signed by the owner of the property
E 'YES/❑ NO -Is the site listed on the"Inventory of Historic Sites and Structures"or in the Historic District?
�
If yes,HPC Approval required. Contact the Historic Preservation Officer at 429-2758
E Site Plan(2 copies)showing the roof and including the following(may be hand drawn):
❑ Extent of proposed work
❑ Impervious Areas Show and label all hardscape vs. landscaping
❑ Downspout& Gutter locations draw and label each one and show if they drain to hardscape or landscaping
❑ Snowguards/stops required on all roofs that shed onto neighboring properties or potentially occupied areas such as a
walkway, stairway,alley,deck,pedestrian and vehicular exit from buildings or areas where there is potential for
personal injury or property damage and areas directly above or in front of gas utility or electric utility meters.
' (Ordinance 40,2016)
Car/Photographs(2 copies),one clearly showing the structure involved and one showing a close-up of the existing roof
❑ Construction Management Plan(CMP) (2 copies)which includes a Right-of-Way permit required for work in the public
ROW and an Encroachment License required for occupancy of a public ROW.
❑ Asbestos Checklist(1 copy)regarding material removed.
If you answered YES to the Asbestos Checklist,answer these questions:
❑YES/0 NO-Are all the roofing materials to be removed asphaltic,tar impregnated and non-friable(will not crumble by hand
pressure when dry)?
❑YES/0 NO-Will you be removing the roofing materials by hand(no circular saws)?
❑YES/0 NO-Will you dispose asphaltic roof shingles and NOT recycle them?
If you answer YES to all of the above,an asbestos test will not be required.
re--Assembly:
❑ Proposed Roof assembly drawing label each component,including product and manufacturer name and existing
to remain components and number of layers. Show flashing and ice barrier.
Roof Class:
❑Provide a listed roof assembly specific to your roofing product and installation(provide the UL or ESR report)
0 Class A(minimum required for all roofs per Ordinance 40,2016)
� ❑Existing roofing and number of layers: 1.,
BYES/❑ )1O-Is the roof vented?
❑ YES/0-Are you removing,replacing,or adding roof deck insulation(including tapered)?
If YES,describe:
0 Letter of Structural Integrity(1 copy)required if adding insulation due to potential increase in snow load.
❑ YES/ENO—Are you replacing damaged roof deck?Approximate square feet: If YES,the roof must
comply with the energy code which may require insulation.
Additional requirements from Ordiannce 40,2016:
Ice barrier consisting of either self-adhering polymer modified bitumen sheet or two layers of underlayment cemented together required to
extend from the roof eave edge at least 6 feet inside the exterior wall line as measured along the roof surface, 18 inches from the
centerline of the valley and 24 inches on the vertical wall at a roof and wall juncture.
Ventilation openings,including ridge vents,must protect against rain and snow.Individual vents may not exceed 144 sq inc es;V. s
be covered with noncombustible corrosion-resistant mesh or screen with openings no smaller than 1/16"and no larg$1`tli n ED
Wood shakes and shingles require a minimum'/4"vented airspace separating the shingles from the roofing underlayment above the
structural sheathing.
Updated 2/22/2017 11/15/2 018
ASPEN
BUILDING DEPARTMENT
DATE: MASTER PERMIT: PERMIT NUMBER: 0112 . 2018 .ACBK `
COMMUNITY DEVELOPMENT DEPARTMENT 141161
BUILDING PERMIT APPLICATION THE C11Y0EASPEN
PROPERTY INFORMATION ADDRESS 77 I telQan 6.4-, UNIT# PARCEL ID# 2373 1"O'43 ZOp
(DOZ
LOT BLOCK TRACT
OR SUBDIVISION OWNER NAME 15€43 , r\L LC CELL EMAIL eh oej ) p i G.+n+Crestvgkworl--•
BEST CONTACT A�Q�(IA ���-� CELL EMAIL(`lr'tGC1�' �U6I;CinVrc4r�GkWadk•NAME
PROJECT DETAILS
DESCRIPTION OF
WORK IN DETAIL
PROJECT AI
t I� gZBuilding Class ofWorkFixtureCounts 5,0o Use of Equipment ment Checklist
VALUATION
SQQFTOF El Commerical El New Toilets,Bidets Forced Air/Gravity Systems
S%FTOF EA yZ 00 ❑ Multi-Family 0 Addition Bathtub
❑ Single Family 0 Alteration __Lavatory(Wash Basin) Wall,Suspended,or Unit Heaters
UNIT SQ FT I Mixed-Use Shower -Gas Log
❑ Repair _Kitchen Sink(+Disposal) -Gas Appliancew
LOT SIZE ❑ El IFFR Dishwasher -Appliance Vents
(SQ FT) ❑ Tenant Finish _Laundry Bar,Utility Sink Heat,Refrig,Cooling,or
DISTURBED Will there be El Demolition _Clothes Washer Absorption Unit
EXTERIOR AREA any roof/wall ❑ Change Order Floor Sink Boilers(includes vent)
penetrations? ❑ -Floor Drain _Air Handling Unit
NEW SQ FT 0 Yes _Water Heater(Pan Req) _Cooling Systems
_#Gas Outlets
SQ FT OF ROOMS ❑ No Water Treatment Ventilation Fans
WITH UTILITY WORK Other Range Hood
#of Gas System Outlets
ZONE DISTRICT MU -Snowmelt System Sq Ft
N Project Valuation:Cost of project as defined in Valuation Affadavit. NOTICE: This permit becomes null and
Sq Ft of Work Area:Total square footage of area undergoing change or reconfiguration. void if work or construction authorized
Unit Sq Ft:Gross Square Footage,not FAR,of permitted unit. is not commenced within 180 days,or
~ Lot Size:Total surveyed square footage of property. if construction or work is suspended or
abandoned for a period of 180 days at
Z Disturbed Exterior Area:Square footage of lot affected by permit application. any time after work is commenced.
" New Sq Ft:Total added square footage for additions to net livable or net leasble space.
pSq Ft of Rooms with Utility Work:Total square footage,not FAR,of all rooms with plumbing work. Re-
FOR CITY USE ONLY APPROVALS viewer
SUBMITTAL FEES ISSUANCE FEES ISSUANCE FEES Department Reviewing
ReviewN SOff Ap- proved
Plan Check Permit Fee Parks Impact PC SV 1111 .1155
Zoning X SS 11/2t)/'ftd
Zoning(50%) HPC X
Engineering School Ded. Building X SV 11 . 15
Zoning(50%) CMP(50%) TDM Impact Fire X SV 11 .15
Engineering
Energy Code REMP Ped.Amenity CMP X t k 11 . 2 0
Plan Check Water
CMP(50%) (Hourly) Housing Cash in Lieu Stormwater
Zoning Sanitation
Parks Review Stormwater
(Hourly) Env. Health
Engineering Parks X Dr 11/15/18
Utility Review City Use Tax
(Hourly) Landscape
GIS County Use Tax Efficiency
Approved DAM 1 1/20/IF
Lot Area Deed Restricted To Issue ` t"'�r �
Census Code #of Dwellings Plans Location Issuance 'Y,, - `
CITY OF ASPEN December2017 130 S. GALENA ST I ASPEN, CO614t8
ASPEN
BUILDING DEPARTMENT
ADDRESS: 27 I E. Mari ,5S PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT CONTACT SHEET THE CI'IYOFASPEN
FOR PLAN REVIEW QUESTIONS 1
Name fk rX C C_S Phone TV. 19- 0 E-mail 171 ,MOMLa. ; •Ceh
FOR INSPECTION QUESTIONS
Name 1 Mallra. • a, Phone • _) Ctq E-mail C a. r i'.CaM
OWNER
Name is )4 LLC Phone Cell Phone
Mddress ailing VQ T CC S'! • L-Liao City State CO ZIP g b Z OZ
A
Address 011 ,Cin4& 4+ne:t IJOik.. !}/
OWNER'S AUTHORIZED AGENT Name kC.Cl Acura'CY1 Phone Cell Phone q�i-1
t7),30(0 -378'4
Mailing
Address City State ZIP
Address kC` eNC �ic5 rb'Nr r CS •Cor
APPLICATION BEST CONTACT P. � n_ t�
Name *VIfX. r- P S Phone 'I 3 l"tn" !C•� PhoneC0
11 Phon/e�
Add ess P. 0• C ' CQ City r elel t'' State ZIP /K'DZA
E-mail O(1 �� ' (�
Addressl�. txlrh j'�['1 ��..1 �I.�--(DCY1
ARCHITECT OR DESIGNER OF RECORD
Name Phone Cell Phone
Mailing
Address City State ZIP
E-mail
Address
CIVIL ENGINEER OF RECORD
Name Phone Cell Phone
Mailing
Address City State ZIP
E-mail
Address
STRUCTUAL ENGINEER OF RECORD
Name Phone Cell Phone
Mailing
Address City State ZIP
E-mail
Address
GENERAL CONTRACTOR
Name tbCSr31--1 InC Phone Cell Phone L • - r
Address , .etQKLI$' City CQ(6xndQ iC State C d ZIP RI wZ3
M AE-mail ss Q I i7kr ll \`✓ S C 1 I • C9Ir-1
ddre
INSPECTIONS: The General Contractor must schedule inspections online.
Please visit www.aspenpitkin.com/Departments/Community-Development-Forms/to do so.
I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions of laws and
ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does not
presume to give authority to violate or cancel the provisions of any other state or local law regulating construction or the performance
of construction. It is my responsibility to review the approved plans and any comments that are contained thereon and see that the
structure and/or project' uilt• compliance ' h all appli a codes.
Contractor
Signature / ,' Date 40"to11g'
❑ Check if you are a tested owner builder(single-family homes only).You must take a test and complete the owner/buitiiinOffiiiav
(CITY USE ONLY)Owner builder approved by: Date: Affidavit on'file
CITY OF ASPEN August2017 130 S. GALENA ST I ASPEN, Co 11 8
ASPEN
BUILDING DEPARTMENT
ADDRESS: Z7 I F . !e1Qin 5f . PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
ASBESTOS VERIFICATION AND CHECKLIST THE CI CY OF ASPEN
ASBESTOS INFORMATION
Asbestos is a known human carcinogen and is an airborne hazard.Once airborne,asbestos fibers can stay suspended in the air for days,
weeks,or even months before settling out of the air.The fibers can easily become airborne again from a minor disturbance like turning
on an air conditioner. Uncontrolled asbestos abatement projects or renovation projects that disturb asbestos may cause latent asbestos
hazards that could expose people to asbestos in the future, long after the renovation activity occurred.The airborne asbestos fiber
concentrations resulting from disturbances may result in a significant exposure to the current and future occupants of the home.
The 1989"ban"on asbestos-containing materials is commonly misunderstood. In fact,in 1991 the U.S. Fifth Circuit Court of appeals
vacated much of the so-called"Asbestos Ban and Phaseout Rule"and remanded it to the EPA.Thus, much of the original 1989 EPA ban
on the U.S.manufacturing,importation, processing,or distribution in commerce of many asbestos-containing product categories was
set aside and DID NOT TAKE EFFECT.Therefore,ALL demolition, remodel or renovation projects must determine if disturbed material
above the trigger levels contains asbestos.
ASBESTOS CHECKLIST
❑Yes pNo
Residential:Will you be removing more than 32 sq ft, 50 linear feet (e.g., pipe insulation), or the volume
equivalent of a 55-gallon drum of any material besides concrete, wood, bricks, or steel—examples are drywall,
linoleum, ceiling tiles, roofing materials, etc.?
❑Yes 131 o
Commercial:Will you be removing more than 160 sq ft, 260 linear feet (e.g., pipe insulation), or the volume
equivalent of a 55-gallon drum of any material besides concrete, wood, bricks, or steel—examples are drywall,
linoleum, carpet, carpet adhesives, ceiling tiles, roofing materials, etc.?
If the answer is YES to any of the above,you will need an asbestos test before you can receive a building and/
or demolition permit.You will also need to provide plans indicating areas to be demolished and determine if a
CO state demolition license is required.A state certified asbestos inspector must do this test and the test report
must be submitted with the building permit application. If the building has asbestos, a state certified asbestos
abatement firm must remove it. After removal, the abatement firm must provide a letter to the Building
Department stating that all the asbestos has been removed and that the air is clean. This letter must be received
BEFORE a permit will be issued. (See the local or statewide Yellow Pages, DexOnLine, or http://www.cdphe.state.
co.us/ap/asbestos/index.html for certified asbestos inspectors and abatement companies. ALWAYS ask for proof
of current state certification.)
If you are demolishing the building, you must submit a demolition permit app with the CDPHE in addition to the
Aspen permit app.This form may be found at https://www.colorado.gov/pacific/cdphe/asbestos-forms NOTE:
A copy of this demolition permit app must be submitted with the initial building permit application. When the
CDPHE approves the app, their issued permit must be given to the Aspen Building Dept before we issue our
permit.
I hereby certify that the above information is true and complete.
Owner Phone#
Applicant (print name),4L )c Cerifenf e5 Phone# ci 3.L 31G'I(IO9
Applicant Signature Date id l(e) I lI
Please call the City of Aspen Environmental Health Department at 920-5039 at any time if you have El e fio si 1\ r r;
about asbestos, interpreting your test results, or other matters.
( CITY OF ASPEN August z017 130 S. GALENA ST I ASPEN, CO1C .I#8
ASPEN
BUILDING DEPARTMENT
ADDRESS: 221 E Main St PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT .
VALUATION AFFADAVIT
THE CITY OF ASPEN
AFFIDAVIT POLICY
All applications for a building permit within the City of Aspen are required to include a certification of
compliance with building permit valuation requirements. The certification must be signed by the property
owner or authorized representative. The following certification shall accompany the application for a permit.
I,the property owner or authorized agent, understand and certify as follows:
City of Aspen Ordinance No.40,Series of 2016 adopts the 2015 International Residential Code(IRC) and
International Building Code(IBC)with certain amendments.These codes define building valuation as follows:
R108.3 Building permit valuations. Building permit valuation shall include total value of the work for which a
permit is being issued,such as electrical,gas, mechanical, plumbing equipment,and other permanent systems,
including materials and labor.
109.3 Building permit valuations.The applicant for a permit shall provide an estimated permit value at time
of application. Permit valuations shall include total value of work, including materials and labor,for which the
permit is being issued,such as electrical, gas, mechanical, plumbing equipment and permanent systems. If, in
the opinion of the building official,the valuation is underestimated on the application,the permit shall be
denied,unless the applicant can show detailed estimates to meet the approval of the building official. Final
building permit valuation shall be set by the building official.
City policy indicates that permit valuation includes materials and labor for the structure and mechanical,
electrical, plumbing and gas,fire sprinkler and elevator systems and equipment. Permanent systems such as
audio visual, lighting and HVAC controls are included in the total as are expenses directly related to construction
such as equipment rental and contractor fees. Finish materials such as paint,floor coverings,tile, cabinets and
counter tops are included in the permit valuation total.
Costs such as architectural and engineering design fees, landscaping and planting,tap fees, development
mitigation fees,trash removal, and cleaning are not included.
I certify that the permit valuation entered on the permit application for this property complies with the above
valuation requirements. I understand that this document is a public document.
Owner Signature: Date:
Owner Printed Name:
or,
Authorized Agent Signatur . , Date: (;)
Authorized Agent Printed lime: 14ri,t) � ) G���,►o'�
I CITY OF ASPEN August2017 130 S. GALENA ST I ASPEN, CO 81611 .
rry. /c018
ASPEN
BUILDING DEPARTMENT
PERMIT NUMBER: ADDRESS: 2 ,I "F .friC,n 61-•
COMMUNITY DEVELOPMENT DEPARTMENT rt 0 k
ZONING COMPLIANCE VERIFICATION POLICY THE CITY OF ASPEN
4-Plans and elevations must include height or setback exemption items unique to the building, such as stair/
elevator overruns, utility/mechanical apparatus, hot tubs and spas, and other height or setback exemption items
unique to the project.
5-The report shall include a written description or drawing notes of the benchmarks or control points used to
establish property boundaries, setbacks, building location, building height,and grades for each measurement.
6-All drawings must correlate with the building locations, elevations, and grading/drainage representations in
the approved building permit set.
7-The report must include the signature, date, and stamp of Colorado Professional Land Surveyor who
conducted the field measurements certifying that the field measurements areaccurately represented.
Review and Acceptance of Report:The Zoning Officer shall review the report(s)and either confirm the project
conforms to the dimensions shown on the zoning sheets of the approved building permit plan set and meets
the zoning limitations for the property or shall determine which elements of the project are not in compliance.
The Zoning Officer may request additional information to verify zoning compliance, which may include but is not
limited to additional survey work or a site visit.
All drawings of the survey report must correlate with representations in the approved building permit set for
acceptance. Modifications to field conditions or amendments to the building permit may be required.
A determination of non-compliance shall result in the issuance of a correction notice and possible work
stoppage. Applicants are encouraged to verify zoning compliance as early as reasonably practical in the
construction process to minimize disruption to the construction schedule.
Acknowledgment:
I (contractor name)<r�� 'j Qj 'n I AC understand this policy. I agree that this project will
comply with the zoning lim lions affect' this parcel and the representations made on the zoning sheets of
the approved building permit plans. I understand that a Certificate of Occupancy will not be issued until this
project complies with all applicable zoning li itations.
Contractor Signature: � � � � � /
Date: I O l I (,I I s'
,,i, r i; `'1 i t
CITY OF ASPEN August2017 130 S. GALENA ST ASPEN, CO38' ii/18
ASPEN
BUILDING DEPARTMENT
ADDRESS: 7_7 I E. Mci:e) S-f. PERMIT NUMBER:
COMMUNITY DEVELOPMENT DEPARTMENT
ZONING COMPLIANCE VERIFICATION POLICY THE CITY OF ASPEN
Applicability:All development projects must comply with the City's zoning regulations, including height and
location, and are subject to periodic inspection during construction and a final inspection prior to project
completion. When required by the City's Zoning Officer, certain development projects within the City of Aspen
shall verify height and/or location compliance through submission of a survey report.
Unless otherwise exempted, all commercial, multi-family, lodging, and mixed-use projects proposed within one
foot of the maximum permissible height or within one foot of allowable setbacks shall verify zoning compliance
through this method.
In addition, the Zoning Officer may require this method be used to verify zoning compliance for single-family/
duplex development or other projects where compliance may be in question. Independent of this policy, all
projects must comply with all applicable zoning limitations.
The Zoning Officer will inform the applicant during building permit review if verification will be required.
However, circumstances may require zoning compliance verification of a project which is already underway.
Timing: Height verification should be accomplished at a point of construction when enough roof structure is in
place to accurately measure the structure yet early enough in the process to still make changes if the structure
is too tall. Location verification should be accomplished at a point of construction when the final exterior of the
structure can be accurately measured in relation to setback requirements. Applicants are encouraged to confer
with the Zoning Officer regarding the timing of zoning compliance verification. Applicants are encouraged to
perform their own verification during construction to ensure the building is progressing to plan, including the
height and location of foundation forms prior to concrete pours.
Survey Report:A Colorado Professional Land Surveyor shall describe and depict the height and location of a
structure compared to the dimensions shown on the zoning sheets of the approved building permit plan set. The
City's Zoning Officer can assist in determining which elements of the structure should be measured and if natural
or finished grade should be used.
The report shall include the following information:
1-A brief cover letter with the building permit number, name of the project, name of the owner and general
contractor, with a written description of the measurement methods including date(s) of measurement.
2-For location verification: A plan drawing showing property boundaries, permitted setbacks, building envelope
(if applicable), location of foundation walls, location of the outermost exterior of each structure (inclusive of all
exterior veneer or other exterior treatments), and the location and dimension of each observed measurement.
3-For height verification: Elevation drawing(s) showing the natural or finished grade of the property, maximum
permitted height, building elevations including the nominal roof form (inclusive of the first layer of exterior
sheathing or weatherproofing membrane but excluding all exterior surface treatments such as shakes, shingles,
or other veneer treatments orornamentation), and the location and dimension of each observed measurement.
Additional roof plans showing location of measurements may be necessary.
CITY OF ASPEN August2017 130 S. GALENA ST I ASPEN, CQ 6/. 4L8
ASPEN