HomeMy WebLinkAboutresolution.council.112-24RESOLUTION 4112
(Series of 2024)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN,
COLORADO, APPROVING A CONTRACT CHANGE ORDER 04 BETWEEN
THE CITY OF ASPEN AND NORTH PEAK, INC., AND AUTHORIZING THE
CITY MANAGER TO EXECUTE SAID CONTRACT CHANGE ORDER ON
BEHALF OF THE CITY OF ASPEN, COLORADO.
WHEREAS, there has been submitted to the City Council a Contract Change
Order 04 between the City of Aspen and North Peak, Inc., a true and accurate copy
of which is attached hereto as Exhibit " A";
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO,
That the City Council of the City of Aspen hereby approves that Contract
Change Order between the City of Aspen and North Peak, Inc., a copy of which is
annexed hereto and incorporated herein, and does hereby authorize the City
Manager to execute said agreement on behalf of the City of Aspen.
INTRODUCED, READ AND ADOPTED by the City Council of the City of
Aspen on the loth day of September, 2024.
Torre, Mayor
I, Nicole Henning, duly appointed and acting City Clerk do certify that the
foregoing is a true and accurate copy of that resolution adopted by the City Council
of the City of Aspen, Colorado, at a meeting held, September 10th, 2024.
Nicole Henning, City Clerk
Docusign Envelope ID: 6CE507D9-131`78-4E47-98C7-1 D86061 OA30D
General Information
Vendor
Change Order Number
Date of Issuance
Project Name
Project Number
Project Completion Date
Project Manager
CCIA Account Code
Project Information
Change Order Form Revision 12/08/2021
Change Order Form
North Peak, Inc.
04
August 30, 2024
Red Bric!< Arts Gallery &Corridor Improvements
2023455, Resolution 163-23
October 15, 2024
Scott Chism/Elen Mitchell
20o552w8 1200*573 10o5 1363
ie Owner is requesting supplemental work to the Red Brick
is Gallery & Corridor work scope to increase functionality in
ree high use areas: 1.) Art Classroom 2.) Women's Corridor
�stroom 3.) Corridor entrances and exits.
1. The Art Classroom is a high traffic area for children. Add
upgrades to the wet sink clean up area, addition of
robust flooring material, cabinet refinishing, countertop
replacements and additional track lighting
2. The Women's Corridor Restroom requires relocation of
the two (2) restroom sinks and associated infrastructure
following demolition discoveries to avoid detrimental impacts
to an interior brick wall and achieve code required ADA
dimensional access clearances. Installation of temporary
outdoor restrooms with water for a multi -month duration to
support tenant and visitor needs during restroom renovation
work. Supplemental women's toilets are necessary during
restroom renovation work to accommodate the influx of
interns and students in the building for classes and rehearsals.
3. The main Corridor of the Arts building requires many
emergency exit signs that need battery backup packs (in
the event of power outage) Add emergency exit signs with
battery backup within the primary corridor per building
inspection direction to supplement emergency exit signs
installed as part of the base contracted scope of work.
Paae 1 of 3
Docusign Envelope ID: 6CE507D9-BF7&4E47-98C7-1 D86061 OA30D
Description Of Change
Order
Contract Information
Original Contract Amount
Previous Change Order(s)
Change Order Amount
(If Over SOk Change Order
To Be Presented To Council
For Approval)
Final Contract Amount
(Including All Change
Orders)
Change Order Form Revision 12/08/2021
4. The Red Brick Arts Executive Director is requesting a
closet in the Corridor on the South entrance to provide
storage for custodial materials out of the way of
classroom and tenant activities. Extra shelving to
accommodate storage is necessary.
Change Order 04 will be funded from available Capital project
budget for reconfigurations expected during renovation within
an 82-year4d building. Scope of work is more specifically
identified in attached work scopes from North Peak, Inc.
(Attachment A)
$1,473,966.00
$93,389.65
$121,435.66
$1,688,791.31
Revised Completion Date October 15, 202
Signature
Contractor (Required)
2. Project Manager
(Required)
3. Department Head
(Required)
4. Procurement Officer
(Required)
5. City Attorney (Required
Based On Value Of
Thresholds)
—Dacu9pnW by
8/30/2024
—DocuSipned by:
Slgned by:
___432FOA40A55C4BD,44
Page 0 of 3
9/3/Z024 17:5Z:36 AM
9/3/ZOZ4 18:59:�1 AM MDT
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D86061 OA30D
Change Order Form Revision 12/08/2021
6. City Manager (Required Signed by:
Based On Value Of [EACOCC3793DO470.1.
��FdW
Thresholds)
Original contract, if applicable all other change orders, and vendor quote for requested
change order must be attached to this document.
For additional information: See Procurement Policy "Change Orders And Add Services
Request" (page 30).
Paae 3 of 3
Docusign Envelope ID: 6CE507D9-BF7&4E47-98C7-1 D86061 OA30D
ATTACHMENT A
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D86061 OA30D
►i` North Peak Construction
,�w
NORTH
PEAK
TIME & MATERIALL PROPOSAL
T&M Date 8/28/2024
ART CLASSROOM UPGRADES
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
(enter information ONLY in YELLOWED cell
T&M
Description of Work: (enter into text box)
Date 8/28/2024
ART CLASSROOM UPGRADES: ;
FRP
VINYL FLOORING
STAINLESSSTEELSHELVING ;
I CAMBRIA COUNTERTOPS
(Before completing this form, read instructions on reverse side.)
PART I - WORK PERFORMED BY CONTRACTOR
Line 1. 11 Direct Labor Costs $ 2,380.00
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 238.00
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 21618000
Line 4. Direct Materials Costs $ 11958027
Line 5. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 4) $ 97,91
Line 6. Total Materials Costs (Lines 4 and 5) $ 2,056.18
Line 7. Total Equipment Costs $
Line 8. PART I - TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3,6 and 7) Part I is 41674,18
PART II - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $ 31053,05
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 152.65
Line 11. Total Subcontractor's Labor Costs (Lines 9 and 10) $ 3,205.70
Line 12. Direct Materials Costs 91074489
Line 13. Materials Overhead (Delivery Costs & Taxes) ( 5% x Line 12) $ 453,74
Line 14. Total Subcontractor's Materials Costs (Lines 12 and 13) $ 9,528.63
Line 15. Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 121734,33
Line 17. Subcontractor's Overhead (Indirect costs) ( 0.0% x Line 16) $ 0.00
Line 18, Subcontractor's Profit (on line 16) DAddition or Deduct 0 $ 0.00
Line 19, PART II - TOTAL SUBCONTRACTOR'S COSTS (Lines 16,17 and 18) Part II $ 12,734.33
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20. Contractor's Overhead (Indirect Costs) ( 9.0% x Part I'Total) $ 420.68
Line 21. iContr2ctor's Profit ( 5.0% x Part I_�fotal) $ 233,71
Line 22. PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 654.39
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23. Contractor's Commission on Subcontractor ( 5.0% x Part II Total) $ 636.72
Line 24. Contractor's Profit (on Line 19) 1 Addition or Deduct 0 $ 0.00
Line 25, PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) _Part IV $
PART V - SUBTOTAL C.O. PROPOSAL (Parts I and II and III and IV) Part V (subtotal $
PART VI - CONTRACTOR'S BOND COST ( 3% x Part V Total) Part VI $
PART VII - GRAND TOTAL CHANGE ORDER PROPOSAL (Sum of Totals: Parts V and VI) Grand Total $ 11
PART VIII •CONTRACT TIME (CALENDAR DAYS CHANGED) EXTENDED �NO CHANGE REDUCED
636.72
181699.62
560.99
19,260.61
THE TIME OF COMPLETION MAY CHANGE BY THE CALENDAR DAYS INDICATED (ABOVE) FROM THE TOTAL NUMBER OF DAYS
LISTED IN THE CONTRACTOR'S AGREEMENT TO COMPLETE THE ENTIRE PROJECT.
CONTRACTOR'S CERTIFICATE:
This is to certify that, to the best of my knowledge and belief, th
e
cost/price data submitted in response to the listed T&M Bulletin,
are accurate, complete and current as of 8/28/2024
Firm: North Peak Inc.
Name &title Bryce Johnson PM
✓r
Signature: �/2
ARCHITECT/ENGINEER'S CERTIFICATE:
This is to certify that I have analyzed the proposal and findto the best of my
,
knowledge and belief, that the proposal represents current, fair, factual and
competitive cost/price data.
Firm:
Name &title:
Signature:
*Date: 8/28/2024 Date:
* The proposal shall remain in full force and effect for a period of calendar days from d
ate of signature.
Owners Rep (or Authorized Delegate)
Date:
State Form SC-6.312 (Rev. 7/2015)
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D86061 OA30D
North Peak Construction
14W " kX4 6 NORTH
PEAK
TIME &MATERIAL PROPOSAL
T&M Date 8/2/2024
ALUMINUM FABRICATION
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
nter information ONLY in YELLOWED cells)
T&M
Description of Work: (enter into text box)
Date 8/2/2024
FABRICATE 4 PERFORATED ALUMINUM CABINET DOORS. '
CNC 2 PERFORATED ALUMINUM RADIATOR COVERS,
i
r �
(Before completing this form, read instructions on reverse side.)
PART I - WORK PERFORMED BY CONTRACTOR
Line 1. Direct Labor Costs $ 848.00
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 84.80
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 932.80
Line 4. Direct Materials Costs $
Line 5. Materials Overhead (Delivery Costs & Taxes) ( 5% x Line 4) $ 0.00
Line 6. Total Materials Costs (Lines 4 and 5) $ 0.00
Line 7. Total Equipment Costs $
Line 8. PART I - TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3, 6 and 7) Part I $ 932.80
PART II - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $ 628.10
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 31.41
Line 11, Total Subcontractor's Labor Costs (Lines 9 and 10) $ 659.51
Line 12. Direct Materials Costs
Line 13. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 12) $ 0.00
Line 14. Total Subcontractor's Materials Costs (Lines 12 and 13) $ 0.00
Line 15. Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 659.51
Line 17. Subcontractor's Overhead (Indirect Costs) ( 0.0% x Line 16) $ 0.00
Line 18. Subcontractor's Profit (on line 16) DAddition or Deduct $ 0.00
Line 19. PART II - TOTAL SUBCONTRACTOR'S COSTS (Lines 16, 17 and 18) Part it $ 659.51
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20. Contractor's Overhead (Indirect costs) ( 9.0% x Part I otal) $ 83.95
Line 21. Contractor's Profit ( 5.0% x Part I, otal) $ 46.64
Line 22, PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 130.59
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23, Contractor's Commission on Subcontractor ( 5.0% x Part II Total) $ 32.98
Line 24. Contractor's Profit (on Line 19) DAddition or Deduct F�j $ 0.00
Line 25. PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) _Part IV $ 32,98
PART V - SUBTOTAL C.O. PROPOSAL (Parts I and II and III and IV) Part V (Subtotal $ 11755,88
PART VI - CONTRACTOR'S BOND COST ( 3% x Part V Total) Part VI $ 52.68
PART VII - GRAND TOTAL CHANGE ORDER PROPOSAL (Sum of Totals: Parts V and VI) Grand Total $ 1,808.56
PART VIII CONTRACT TIME (CALENDAR DAYS CHANGED) 11 EXTENDED �NO CHANGE REDUCED
THE TIME OF COMPLETION MAY CHANGE BY THE CALENDAR DAYS INDICATED (ABOVE) FROM THE TOTAL NUMBER OF DAYS
LISTED IN THE CONTRACTOR'S AGREEMENT TO COMPLETE THE ENTIRE PROJECT,
CONTRACTOR'S CERTIFICATE:
This is to certify that, to the best of my knowledge and belief, the
cost/price data submitted in response to the listed T&M Bulletin,
are accurate, complete and current as of 8/2/2024
Firm: North Peak Inc.
Name &title B
Signature:
Johnson PM
ARCHITECT/ENGINEER'S CERTIFICATE:
This is to certify that I have analyzed the proposal and findto the best of
, my
knowledge and belief, that the proposal represents current, fair, factual and
competitive cost/price data.
Firm:
Name &title:
Signature:
*Date: 8/2/2024 Date:
The proposal shall remain in full force and effect for a period of calendar days from date of signature.
Owners Rep (or Authorized Delegate)
Date:
State Form SC-6.312 (Rev. 7I2015)
Docusign Envelope ID: 6CE507D9-BF784E47-98C7-1 D86061 OA30D
• North Peak Construction
,4\a
NORTH
PEAK
TIME &MATERIAL PROPOSAL
T&M Date 8/6/2024
ART CLASSROOM TRACK LIGHTING
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
(enter information ONLY in YELLOWED
T&M
Description of Work: (enter into text box)
Date 8/6/2024
INSTALL TWO ROWS OF TRACK IN THE ART CLASSROOM TO PROVIDE BETTER ;
i LIGHTING FOR THE EVENING CLASSES.
r ,
(Before completing this form, read instructions on reverse side.)
PART I - WORK PERFORMED BY CONTRACTOR
Line 1. Direct Labor Costs $ 11696900
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 169.60
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 11865.60
Line 4. Direct Materials Costs $
Line 5. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 4) $ 0.00
Line 6. Total Materials Costs (Lines 4 and 5) $ 0.00
Line 7. Total Equipment Costs $
Line 8. PART I - TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3,6 and 7) Part I $ 11865,60
PART II - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $ 21262050
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 113.13
Line 11, Total Subcontractor's Labor Costs (Lines 9 and 10) $ 21375663
Line 12. Direct Materials Costs 11178.51
Line 13. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 12) $ 58.93
Line 14. Total Subcontractor's Materials Costs (Lines 12 and 13) $ 11237.44
Line 15. Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 31613.07
Line 17. Subcontractor's Overhead (Indirect costs) ( 0.0% x Line 16) $ 0.00
Line 18. Subcontractor's Profit (on line 16) DAddition or Deduct 0 $ 0.00
Line 19. PART II "TOTAL SUBCONTRACTOR'S COSTS (Lines 16,17 and 18) 'Part II $ 31613.07
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20. Contractor's Overhead (Indirectcosts) ( 9.0% x Part 'II otal) $ 167.90
Line 21. Contractor's Profit ( 5.0% x Part otal) $ 93.28
Line 22. PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 261.18
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23. Contractor's Commission on Subcontractor ( 5.0% x Fart II Total) $ 180.65
Line 24. Contractor's Profit (on Line 19) DAddition or Deduct $ 0.00
Line 25. PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) -Part IV $
PART VIII •CONTRACT TIME (CALENDAR DAYS CHANGED) EXTENDED �NO CHANGE REDUCED
180.65
CONTRACTOR'S CERTIFICATE:
This is to certify
Firm: North Peak Inc.
Name &title Brvice Johnson PM
Signature:
ARCHITECT/ENGINEER'S CERTIFICATE:
Firm:
Name &title:
Signature:
*Date: 8/6/2024 Date:
* The proposal shall remain in full force and effect for a period of calendar days from date of signature.
Owners Rep (or Authorized Delegate)
Date:
State Form SG6.312 (Rev. 7I2015)
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D860610A30D
Bryce Johnson
North Peak Construction
Grand junction CO 81501
Description
Addiotnal work not in original scope of work
-Add track lighting in the Art Class
-Replace all exit lights
Littell Electric, Inc
7094 Highway 82, Unit A
Glenwood Springs, CO 81601
Tel. 970-429-8357
www.LittellElectric.com
License # EC-7825
CUSTOMER JOB NO. 26382
Job No:
Site:
Site Contact:
Site Phone:
Salesperson:
Re: Red Brick Center for the Arts
Added track lighting in the Art room
Add track in art room on the West end to match the East end
This includes: track with connectors, current limiting devices, and dead ends
need to miter cut the track to hit the exact lengths,
26382
Red Brick Center for the Arts
Anthony Walker
There is enough material to cover 50' we will
There is NO track
heads included in this track, These will be used
from previous
li htin packs e
L3-TRACK
GES-208-
7.00
$0.00 $0.00
L3-CONNECTO
R
GES-21-2
5.00
$0.00
� $0.00
_
L3-ENDS
GES41-2 ~_ _.__
3.00
$0.00
$0.00
L3-CURRENTLI
i
MIT
ACL-GES12-2-5A
3.00
$0.00
$0.00
AMLX TRACK (HEADS NOT INCLUDED)
1.00
$1007.50
$1007.50
SHIPPING AND FREIGHT
1.00
$125.22
$125.22
_ _
12/2 MC Cable with Ground, Includes Straps -PER
FOOT
50.00
$0.92
$45.79
_ __ _
Journeyman 1
10
$110.00
$1100.00
_ _
Apprentice 1
10
$85.00
$850.00
Project Management
2.5
$125.00
$312.50
Sub -Total ex Tax
_ �� $3441.01
Tax
$0.00
Total inc Tax
_
$3441.01
Page 1 /3
Docusign Envelope ID: 6CE507D9-BF784E47-98C7-1 D86061 OA30D
► North Peak Construction
NORTH
PEAK
TIME &MATERIAL PROPOSAL
T&M Date 6/27/2024
WOMEN'S RESTROOM PLUMBING
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
(enter information ONLY in YELLOWED
T&M
Description of Work: (enter into text box)
Date 6/27/2024
WOMEN'S RESTROOM
Remove plumbing and framing on the north wall.
Replumb east wall to meet ADA requirements for new layout.
Furr out north wall for tile.
i
(Before completing this form, read instructions on reverse side.)
PART I - WORK PERFORMED BY CONTRACTOR
Line 1. Direct Labor Costs $ 41200.00
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 420.00
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 41620000
Line 4. Direct Materials Costs $ 512.78
Line 5. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 4) $ 25.64
Line 6. Total Materials Costs (Lines 4 and 5) $ 538.42
Line 7. Total Equipment Costs $
Line 8. PART I - TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3, 6 and 7) Part I $ 51158.42
PART II - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $ 21375600
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 118.75
Line 11. Total Subcontractor's Labor Costs (Lines 9 and 10) $ 21493675
Line 12. Direct Materials Costs 589.64
Line 13. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 12) $ 29A8
Line 14. Total Subcontractor's Materials Costs (Lines 12 and 13) $ 619.12
Line 15, Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 31112687
Line 17. Subcontractor's Overhead (Indirect costs) ( 0.0% x Line 16) $ 0.00
Line 18. Subcontractor's Profit (on line 16) 1 Addition or Deduct = $ 0.00
Line 19. PART II - TOTAL SUBCONTRACTOR'S COSTS (Lines 16,17 and 18) Part 11 $ 3,112.87
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20. Contractor's Overhead (Indirect costs) ( 9.0% x Part I Total) $ 464.26
Line 21. Contractor's Profit ( 5.0% x Part I Total) .$ 257.92
Line 22. PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 722.18
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23. Contractor's Commission on Subcontractor ( 5.0% x Part II Total) $ 155.64
Line 24. Contractor's Profit (on Line 19) Addition or Deduct $ 0.00
Line 25. PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) _ Part IV $
PART V - SUBTOTAL C.O. PROPOSAL (Parts I and II and III and IV) Part V (Subtotal) $
PART VI - CONTRACTOR'S BOND COST ( 3% x Part V Total) Part VI $
PART VII - GRAND TOTAL CHANGE ORDER PROPOSAL (Sum of Totals: Parts V and VI) Grand Total $
PART VIII -CONTRACT TIME (CALENDAR DAYS CHANGED) EXTENDED 11 NO CHANGE []REDUCED
155.64
91149.11
274.47
9,423.58
THE TIME OF COMPLETION MAY CHANGE BY THE CALENDAR DAYS INDICATED (ABOVE) FROM THE TOTAL NUMBER OF DAYS
LISTED IN THE CONTRACTOR'S AGREEMENT TO COMPLETE THE ENTIRE PROJECT.
CONTRACTOR'S CERTIFICATE:
This is to certify that, to the best of my knowledge and belief, the
cost/price data submitted in response to the listed C.O. Bulletin,
are accurate, complete and current as of
ARCHITECT/ENGINEER'S CERTIFICATE:
This is to certify that I have analyzed the proposal and find, to the best of my
knowledge and belief, that the proposal represents current, fair, factual and
competitive cost/price data.
Firm: North Peak Inc. Firm:
Name &title Bryce Johnson PM Name &title:
Signature: flee�lnaon Signature:
*Date: 6/27/2024 Date:
* The proposal shall remain in full force and effect for a period of calendar days from date of signature.
Owners
Rep (or Authorized Delegate)
Date:
i
State Form SC-6.312 (Rev. 7/2015)
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D86061 OA30D
► North Peak Construction
NORTH
PEAK
TIME &MATERIAL PROPOSAL
T&M Date 7/9/2024
COLORADO SITE SERVICES
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
(Before
PART I - WORK PERFORMED BY CONTRACTOR
(enter information ONLY in YELLOWED cells)
T&M
Description of Work: (enter into text box) Date 7/9/2024
The temporary restrooms provided by Colorado Site Services have been a ;
crucial amenity during the sewer line replacement project. While initially
intended for short-term use, they have proven to be essential for
accommodating the needs of staff and students on site. With construction ;
projects often causing disruptions to regular facilities, having these
temporary restrooms available has helped maintain a comfortable and
functional environment for everyone involved. The convenience and ;
reliability of these facilities have made them a valuable resource throughout
the duration of the project. This billing period covers five months, from
March through July,
n, read instructions on reverse side.)
Line 1. Direct Labor Costs $ 840.00
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 84.00
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 924.00
Line 4. Direct Materials Costs $ 375.00
Line 5. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 4) $ 18.75
Line 6. Total Materials Costs (Lines 4 and 5) $ 393.75
Line 7. Total Equipment Costs $
Line 8. PART I - TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3,6 and 7) Part I Is 11317.75
PART II - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 0.00
Line 11. Total Subcontractor's Labor Costs (Lines 9 and 10) $ 0.00
Line 12. Direct Materials Costs 551000000
Line 13. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 12) $ 21750,00
Line 14. Total Subcontractor's Materials Costs (Lines 12 and 13) $ 571750.00
Line 15. Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 57,750000
Line 17. Subcontractor's Overhead (Indirect costs) ( 0.0% x Line 16) $ 0.00
Line 18. Subcontractor's Profit (on line 16) Addition or Deduct $ 0.00
Line 19. PART II - TOTAL SUBCONTRACTOR'S COSTS (Lines 16, 17 and 18) Part II $ 57,750600
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20, Contractor's Overhead (Indirect costs) ( 9.0% x Part I otal) $ 118.60
Line 21. Contractor's Profit ( 5.0% x Part I otal) $ 65.89
Line 22. PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 184.49
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23. Contractor's Commission on Subcontractor ( 5.0% xlPart II Total) $ 21887650
Line 24. Contractor's Profit (on Line 19) Addition or Deduct $ 0.00
Line 25. PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) _Part IV $ 2,887.50
PART V - SUBTOTAL C.O. PROPOSAL (Parts I and II and III and IV) Part V (Subtotal $ 62,139,74
PART VI - CONTRACTOR'S BOND COST ( 3% x Part V Total) Part VI $ 11864.19
PART VII - GRAND TOTAL CHANGE ORDER PROPOSAL (Sum of Totals: Parts V and VI) Grand Total $ 641003.93
PART Vill • CONTRACT TIME (CALENDAR DAYS CHANGED) 11 EXTENDED 11NO CHANGE REDUCED
THE TIME OF COMPLETION MAY CHANGE BY THE CALENDAR DAYS INDICATED (ABOVE) FROM THE TOTAL NUMBER OF DAYS
LISTED IN THE CONTRACTOR'S AGREEMENT TO COMPLETE THE ENTIRE PROJECT,
CONTRACTOR'S CERTIFICATE:
Firm: North Peak Inc.
Name &title Bryce Johnson PM
g
ARCHITECT/ENGINEER'S CERTIFICATE:
Firm:
Name &title:
Signature:
*Date: 7/9/2024 Date:
* The proposal shall remain in full force and effect far a period of calendar days from date of signature.
Owners Rep (or Authorized Delegate)
Date:
State Form SC-6.312 (Rev. 7I2015)
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D860610A30D
CS
COLORADO SITE
SERVICES
Colorado Site Services LLC
Po Box S80
Carbondale,CO 81623
Phone # 970m%3-2482
E-mail accounting@cositeservices.com
Bill To North Peak Construction
Linda Wilson
305 Main St
Grand Juntion, CO 81501
Serviced � Quantity � Description
3/4/2024 1 14 fi, 4 station Luxury Trailer For 4 Week Rental - 03/04
-04/04
3/4/2024 8 Tuesday & Thursday Service
Tax Exempt 89341005-0006
Sales Tax
You can now pay online! Visit our website at www.cositeservices.com
Invoices over 90 days past due may incur a finance charge. Total
Invoice
1412024
..
Due Date
3/4/2Q24
Rate
8,OOQ.00
250.00
9.30%
Payments/Credits
Project
110 E HalIam St, ...
Amount
8,000.00
2,000.00
0.00
$10,000.00
$ I Q,000.QO
Docusign Envelope ID: 6CE5071D9-BF784E47-98C7-1 D86061 OA30D
A
Us
COLORADO SITE
SERVICES
Bill To
Colorado Site Services LLC
Po Box S8o
Carbondale,CO 81623
Phone # 970-963-2482
E-mail accounting@cositeservices.com
North Peak Construction
Linda Wilson
305 Main St
Grand Juntion, CO 81501
Serviced � Quantity � Description
4/5/2024 � 1 114 ft, 4 station Luxury Trailer For 4 Week Rental -
Second -month extension
April Sth -May 3
8 Tuesday &Thursday Service
Tax Exempt 89341005-0006
Sales Tax
You can now pay online! Visit our website at www.cositeservices.com
Invoices over 90 days past due may incur a finance charge.
Invoice
Date Invoice #
4/5/2024 49465
Due Date
4/5/2024
Rate
8,000.00
250.00
9.30%
Total
Payments/Credits
Balance Due
Project
110 E Hallam St, ...
Amount
8,000.00
2,000.00
0.00
$10,000.00
$ l o,000.00
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D86061 OA30D
A
ass
COLORADO SITE
SERVICES
Bill To
Colorado Site Services LLC
Po Box 580
Carbondale,CO 81623
Phone # 970-963-2482
E-mail accounting@cositeservices.com
North Peak Construction
Linda Wilson
305 Main St
Grand Juntion, CO 81501
Serviced � Quantity � Description
1 114 ft, 4 station Luxury Trailer For 4 Week Rental -Third
month extension
May
a - May 31
8 Tuesday &Thursday Service
Tax Exempt 89341005=0006
Sales Tax
You can now pay online! Visit our website at www.cositeservices.com
Invoices over 90 days past due may incur a finance charge. TOta�
Invoice
Date
Invoice #
5/3/2024
52533
Due Date
5/3/2024
Rate
8,000.00
250.00
9.30%
Payments/Credits
Balance Due
Project
110 E Hallam St, ...
Amount
8,000.00
2,000.00
0.00
$10,000.00
$lo,000.00
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D86061 OA30D
A
ass
COLORADO SITE
SERVICES
Bill To
Colorado Site Services LLC
PO BOX 580
Carbondale,CO 81623
Phone 4 970-963-2482
E-mail accounting@cositeservices.com
North Peak Construction
Linda Wilson
305 Main St
Grand Juntion, CO 81501
Serviced � Quantity � Description
1 114 ft, 4 station Luxury Trailer For 4 W
meek Rental -Fourth
onth extension
June 3rd -June 28th
y y 8 Tuesda&ThursdaService
Tax Exempt 89341005-0006
Sales Tax
now pay online! Visit our website at www.cositeservices.com
Invoices over 90 days past due ma}� incur a finance charge,
Tota I
nie
ate Invoice #
6A/2024 52534
Due Date
6/ 1 /2024
D
Rate
8,000.00
250.00
9.30%
Payments/Credits
Balance Due
Project
110 E Hallam St, ...
Amount
8,000.00
2,000.00
0.00
$10,000.00
$ l o,000.00
Docusign Envelope ID: 6CE507D9-131`784E47-98C7-1 D86061 OA30D
A
ass
COLORADO SITE
SERVICES
Bill To
Colorado Site Services LLC
Po Box 580
Carbondale,CO 81623
Phone 4 970-963-2482
E-mail accounting@cositeservices.com
Notrth Peak Construction
Linda Wilson
305 Main St
Grand Juntion, CO 81501
Serviced � Quantity � Description
1 14 ft, 4 station Luxury Trailer For 4 Week Rental -Fifth
month extension
July 2- July 30th
8 Tuesday & Thursday Service
Tax Exempt 89341005-0006
Sales Tax
You can now pay online! Visit our website at www.cositeservices.com
Invoices over 90 days pasC due may incur a finance charge. TOta�
Invoice
Date
Invoice #
7/1/2024
52535
Due Date
7/ 1 /2024
8,000.00
250.00
9.30%
Payments/Credits
Balance Due
Project
110 E Hallam St, ...
Amount
8,000.00
2,000.00
0.00
$10,000.00
WN
$lo,000.00
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D860610A30D
AColorado Site Services LLC
` ass Po Box 580
coOAgo SITE Carbondale CO 81623
SERVICES
Bill To
Phone # 970-963-2482
E-mail accounting@cositeservices.com
North Peak Construction
Linda Wilson
305 Main St
Grand JuntionI CO 81501
Serviced I Quantity I Description
1 2 Station Luxury Restroom Trailer (loft)
4 Weekly Tuesday Service
Tax Exempt 89341005-0006
Sales Tax
You can now pay online! Visit our website at www.cositeservices.com
Invoices over 90 days past due may incur a finance charge.
Invoice
Date Invoice #
8/1/2024 52536
Due Date
8/ 1 /2024
Rate
4,000.00
250,00
9.30%
Total
Payments/Credits
Balance Due
Project
110 E Hallam St, ...
Amount
4,000.00
1,000.00
0.00
$5,000.00
$5,000.00
Docusign Envelope ID: 6CE507D9-131`78-4E47-98C7-1 D86061 OA30D
North Peak Construction
,qbw
NORTH
PEAK
EXIT SIGNS
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
TIME &MATERIAL PROPOSAL
T&M Date 8/5/2024
information ONLY in YELLOWED
T&M
Description of Work: (enter into text box)
Date 8/5/2024
INSTALLATION AND REMOVAL OF TEMPORARY EXIT SIGN. INSTALL NEW EXIT ;
i SIGNS WITH BATTERY BACK-UP ATTHE ENTRIES AND ALONG THE GALLERY
i
HALL.
t_ =
(Before completing this form, read instructions on reverse side.)
PART I - WORK PERFORMED BY CONTRACTOR
Line 1. Direct Labor Costs $ 11060000
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 106.00
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 11166.00
Line 4. Direct Materials Costs $
Line 5. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 4) $ 0.00
Line 6. Total Materials Costs (Lines 4 and 5) $ 0.00
Line 7. Total Equipment Costs $
Line 8. PART I - TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3,6 and 7) Part 1 $ 11166400
PART II - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $ 990.00
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 49.50
Line 11. Total Subcontractor's Labor Costs (Lines 9 and 10) $ 11039050
Line 12. Direct Materials Costs 11,996.60
Line 13. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 12) $ 599.83
Line 14. Total Subcontractor's Materials Costs (Lines 12 and 13) $ 121596043
Line 15. Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 13,635093
Line 17. Subcontractor's Overhead (Indirect costs) ( 0.0% x Line 16) $ 0.00
Line 18. Subcontractor's Profit (on line 16) DAddition or Deduct 0 $ 0.00
Line 19, PART II - TOTAL SUBCONTRACTOR'S COSTS (Lines 16,17 and 18) �Part II $ 13,635093
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20. Contractor's Overhead (Indirect costs) ( 9.0% x Part I otal) $ 104.94
Line 21. Contractor's Profit ( 5.0( x Part 1. otal) $ 58.30
Line 22. PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 163.24
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23. Contractor's Commission on Subcontractor ( 5.0% x Part II Total) $ 681.80
Line 24. Contractor's Profit (on Line 19) 1 Addition or Deduct $ 0.00
Line 25, PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) -Part IV $
PART V - SUBTOTAL C.O. PROPOSAL (Parts I and II and ill and IV) Part V (subtotal $
PART VI - CONTRACTOR'S BOND COST ( 3% x Part V Total) Part VI $
PART VII - GRAND TOTAL CHANGE ORDER PROPOSAL (Sum of Totals: Parts V and VI) Grand Total $
PART VIII •CONTRACT TIME (CALENDAR DAYS CHANGED) EXTENDED 0NO CHANGE REDUCED
681.80
15,646.97
469.41
16,116.38
THE TIME OF COMPLETION MAY CHANGE BY THE CALENDAR DAYS INDICATED (ABOVE) FROM THE TOTAL NUMBER OF DAYS
LISTED IN THE CONTRACTOR'S AGREEMENT TO COMPLETE THE ENTIRE PROJECT.
CONTRACTOR'S CERTIFICATE:
This is to certify that, to the
best of my knowledge and belief, th
e
cost/price data submitted in response to the listed T&M Bulletin,
are accurate, complete and current as of 8/5/2024
Firm: North Peak Inc.
Name &title B
Signature:
Johnson PM
*Date: 8/5/2024
* The proposal shall remain in full force and effect for a period of
Owners Rep (or Authorized Delegate)
Date:
ARCHITECT/ENGINEER'S CERTIFICATE:
This is to certify that I have analyzed the proposal and findtc the best of my
,
knowledge and belief, that the proposal represents current, fair, factual and
competitive cost/price data.
Firm:
Name &title:
Signature:
Date:
calendar days from date of signature.
Stale Farm SG6.312 (Rev. 7/2015)
Docusign Envelope ID: 6CE507D9-BF78-4E47-98C7-1 D860610A30D
Littell Electric, Inc
7094 Highway 82, Unit A
Glenwood Springs, CO 81601
Tel. 970-429-8357
www. Littell Electric.com
License # EC-7825
CUSTOMER JOB NO. 26382
New exit lights to be battery backed up
1 EA Left handed mount with both arrows
1 EA Left handed mount with Left arrow
1 EA Right handed mount with Right arrow
5 EA no arrows
1 EA Right handed mount with both arrows
X1 SF-INT-BACK-NC- GRN-B ARCHITECTURAL 5.00 $1323.52 $6617.60
SAFETY C_OMPONENT_S _ _ _____
X2 SF-INT-RIGHT-DC-GRN-B ARCHITECTURAL 4.00 $1323.52 _ $5294.08
SAFETY COMPONENTS
—.T_�__.��._�._..___.___. __.._ .--------- _--_-----_._._._ ___.—__..�_________.�.d_ .__-._.
Shipping and_ Freight _ __ __` __ 1.00 � f_ $84.92 $84.92
Journeyman 1 _ �� __ _�___� � ___ 9 �A. $110.00 $990.00
Sub -Total ex Tax $12986.60
Tax $0.00
Total inc Tax $12986.60
Thank you. Total $16427.61
Page 2/3
Docusign Envelope ID: 6CE507D9-BF784E47-98C7-1 D86061 OA30D
•�` North Peak Construction
hIORTH
PEA,:
TIME &MATERIAL PROPOSAL
T&M Date 7/31 /2024
SOUTH ENTRY CABINET
Contractor
North Peak Inc.
Institution or Agency
Red Brick Art Center
Project No./Name
(enter information ONLY in YELLOWED cells)
T&M
Description of Work: (enter into text box)
Date 7/31 /2024
i INSTALL CUSTOM RED OAK SUPPLY CABINET AT THE SOUTH ENTRANCE. ;
(Before completing this form, read instructions on reverse side.)
PART I - WORK PERFORMED BY CONTRACTOR
Line 1. Direct Labor Costs $ 840.00
Line 2. Labor Overhead (Direct Labor Burdens) ( 10% x Line 1) $ 84.00
Line 3. Total Contractor's Labor Costs (Lines 1 and 2) $ 924.00
Line 4. Direct Materials Costs $
Line 5. Materials Overhead (Delivery costs & Taxes) ( 5% x Line 4) $ 0.00
Line 6. Total Materials Costs (Lines 4 and 5) $ 0.00
Line 7. Total Equipment Costs $
Line 8. PART I _ TOTAL CONTRACTOR'S L, M & E COSTS (Lines 3, 6 and 7) Part 1 $ 924.00
PART I) - WORK PERFORMED BY SUBCONTRACTOR
Line 9. Direct Labor Costs $ 32205600
Line 10. Labor Overhead (Direct Labor Burdens) ( 5% x Line 9) $ 160.25
Line 11. Total Subcontractor's Labor Costs (Lines 9 and 10) $ 31365.25
Line 12. Direct Materials Costs
Line 13. Materials Overhead (Delivery costs &Taxes) ( 5% x Line 12) $ 0.00
Line 14, Total Subcontractor's Materials Costs (Lines 12 and 13) $ 0.00
Line 15. Total Subcontractor's Equipment Costs $
Line 16. Total Subcontractor's L, M & E Costs (Line 11, 14 and 15) $ 31365025
Line 17. Subcontractor's Overhead (Indirect costs) ( 0.0% x Line 16) $ 0.00
Line 18. Subcontractor's Profit (on line 16) FAddition or Deduct 0 $ 0.00
Line 19. PART II _ TOTAL SUBCONTRACTOR'S COSTS (Lines 16,17 and 18) Part II $ 3,365.25
PART III - CONTRACTOR'S OVERHEAD & PROFIT
Line 20. Contractor's Overhead (Indirect costs) ( 9.0% x Part I Total) .$ 83.16
Line 21. Contractor's Profit ( 5.0% x Part I Total) .$ 46.20
Line 22. PART III - TOTAL CONTRACTOR OVERHEAD & PROFIT (Lines 20 and 21) Part III $ 129.36
PART IV - CONTRACTOR'S MARKUP ON SUBCONTRACTOR
Line 23. Contractor's Commission on Subcontractor ( 5.0% x Part II Total) $ 168.26
Line 24. Contractor's Profit (on Line 19) OAddition or Deduct = $ 0.00
Line 25. PART IV - TOTAL CONTRACTOR MARKUP ON SUBCONTRACTOR (Lines 23 and 24) _Part IV $ 168.26
PART V - SUBTOTAL C.O. PROPOSAL (Parts I and II and III and IV) Part V (Subtotal $ 4,586.87
PART VI - CONTRACTOR'S BOND COST ( 3% x Part V Total) Part VI $ 137.61
PART VII - GRAND TOTAL CHANGE ORDER PROPOSAL (Sum of Totals: Parts V and VI) Grand Total $ 41724.48
PART VIII CONTRACT TIME (CALENDAR DAYS CHANGED) EXTENDED �NO CHANGE REDUCED
THE TIME OF COMPLETION MAY CHANGE BY THE CALENDAR DAYS INDICATED (ABOVE) FROM THE TOTAL NUMBER OF DAYS
LISTED IN THE CONTRACTOR'S AGREEMENT TO COMPLETE THE ENTIRE PROJECT.
CONTRACTOR'S CERTIFICATE:
This is to certify that, to the best of my knowledge and belief, the
cost/price data submitted in response to the listed T&M Bulletin,
are accurate, complete and current as of 7/31/2024
ARCHITECT/ENGINEER'S CERTIFICATE:
This is to certify that I have analyzed the proposal and find, to the best of my
knowledge and belief, that the proposal represents current, fair, factual and
competitive cost/price data.
Firm: North Peak Inc. Firm:
Name &title Bryce Johnson PM Name &title:
Signature:
*Date: 7/31 /2024
* The proposal shall remain in full force and effect for a period of
Owners Rep (or Authorized Delegate)
Date:
Signature:
Date:
calendar days from date of signature.
State Form SC-6.312 (Rev. 7/2015)
Docusign Envelope ID: 6CE507D9-BF7&4E47-98C7-1 D86061 OA30D
END OF DOCUMENT