• April 15, 2019 Secure Site with Construction Fencing Begin Demo of garage
• April 15-30 Obtain Parking permits for work in the right of way April 18—30
• April 18-30 Begin Abandonment of utilities in the transplant and receiver areas
• May 1 Begin Preparing tree for Removal
• May 1-Stake location of transplant location; get approval from project team and
CoA
• May 6-10 Remove permitted trees and remove stumps/root plates (likely a 2-3 day
project but depends upon underground root systems
• May 13 -16 Prepare receiver hole and install anchoring system for root ball (2-3
days)
• May 17 Dig and move the tree, secure anchoring systems (1 day)
• May 18 Provide after care per transplanting report
• Maintenance plan as outlined in Tree Removal Plan for three-year period.