HomeMy WebLinkAboutFile Documents.955 Chatfield Rd.0172.2018 (18).ARBK irREScheck Software Version 4.6.4
Compliance Certificate
Project Chatfield Renovation
Energy Code: 2015 IECC
Location: Aspen, Colorado
Construction Type: Single-family
Project Type: Alteration
Climate Zone: 7 (9922 HDD)
Permit Date:
Permit Number:
Construction Site: Owner/Agent: Designer/Contractor:
955 Chatfield Road Brandt Bowden David Rosenfeld
Aspen, CO 81611 955 Chatfield Road CCA
Aspen, CO 81611 610 E. Hyman
713.580.1203 Aspen, CO 81611
bbowden@hanoverco.com 970.925.5590
davidr@cunniffe.com
Compliance: Passes using prescriptive requirements for alteration projects
Envelope Assemblies
Gross Area Cavity Cont.
Assembly or R-Value R-Value U-Factor UA
Perimeter
Ceiling 1: Other Ceiling --- --- --- --- ---
Exemption: Neither sheathing nor insulation is exposed.
Wall 1: Other Framed Wall --- --- --- --- ---
Exemption: Framing cavity filled with insulation
Window 1: Metal Frame:Double Pane with Low-E 428 0.280 120
Door 1: Glass 237 0.280 66
Door 2: Solid 21 0.210 4
Floor 1: Other Floor: Over Unconditioned Space --- --- --- --- ---
Exemption: Framing cavity not exposed.
Crawl 1: Solid Concrete or Masonry --- --- --- --- ---
Wall height: 0.0'
Depth below grade: 0.0'
Insulation depth: 0.0'
Exemption: Framing cavity not exposed.
Compliance Statement: The proposed building design described here is consistent with the building plans, specifications, and other
calculations submitted with the permit application.The proposed building has been designed to meet the 2015 IECC requirements in
REScheck Version 4.6.4 and to comply with the mandatory requirements listed in the REScheck Inspection Checklist.
David Rosenfeld •Project Architect 06/01/18
Name-Title Signature Date
RECEIVED
Project Title: Chatfield Renovation Report 45E/2ST-21618
Data filename: P:\1801 Chatfield\3_Public Agency\06_Building\Chatfield RESCheck.rck Page 1 of 1
ASPEN
BUILDING DEPARTMENT