HomeMy WebLinkAboutFile Documents.1419 Crystal Lake Rd.0009.2017 (35).ARBK CILEARWACTE1R COMIST1FRUCTION MANAGEMENT INC 1419 Crystal Lake Road Construction Management Plan 2/09/2017 RECEIVED 11/01/2017 ASPEN BUILDING DEPARTMENT PROJECT CONTACT LIST - 2.4 • Owner: Big Dog Family. LLC • Site Supervisor: Bill Knutson - 970.379.4920 • Project Manager John Chromy - 970.618.6607 • Safety Officer Troy Clark, Miller Safety Consultants • Traffic Control Officer: TBD • Erosion Control Representative: Roaring Fork Engineering - 970.340.4130 • City of Aspen Community Development: 970.920.5090 • City of Aspen Engineering: 970.920.5080 • City of Aspen Parks & Recreation: 970.920.5120 • Fire Department Fire Marshal - 970.925.2690 • Police Department: Non-Emergency - 970.920.5400 • Roaring Fork Transit Authority: 970.920.1905 • Aspen School District: 970.925.3760 • Aspen Electric Department: 970.920,5148 • Aspen Department:Water De artment: 970.920.5110 RECEIVED 11/01/2017 • Aspen Sanitation District_ 970.925.3601 ASPEN • Black Hills Energy: 800-563-0012 PUILDINGDEPARTMENT • Aspen Valley Hospital: 970.925.1120 • Emergency: 9' P 970 379.3709 F 970.963.15991 P.O.Box 6236 Snvv+rnass Viage,Co TABLE OF CONTENTS 1.0 Project Introduction 1.1 Project Description 1.2 Project Disturbance Area 1.3 Project Vicinity Map 2.0 Project Documentation 2.1 Permitting 2.2 Public Notification 2.3 Project Sign 2.4 Contact List 3.0 Project Implementation 3.1 Dates of Construction 3.2 Hours of Construction 3.3 Construction Schedule 3.4 Project Fencing 3.5 Tree Protection 4.0 Project Management 4.1 Parking Management 4.2 Emergency Access and Ordinance 35 4.3 Staging Areas 4.4 Construction Trailer. Materials Storage. and Waste Management 5.0 Traffic Control 5.1 Haul Routes 5.2 Onsite Vehicle Limitations 5.3 Delivery Requirements 5.4 Traffic Control Plan 6.0 Sediment and Erosion Control 6.1 Storm Water Pollution Prevention Plan 7.0 Fugitive Dust Control 7 1 Dust Con? of P'an RECEIVED 8.0 emissions �/ 8.1 Maintenance 11/01/2017 8.2 Opacity ASPEN BUILDING DEPARTMENT - 3 - P 970.379.3709 F 970.963.15991 P.O.Box 6236 Socw ass Vitage.CO 9.0 Noise Suppression 9.1 Noise Suppression Plan 9.2 Equipment and Methods ATTACHMENTS: A - Required Project Sign C — Haul Route Map E — Construction Schedule F — CMP Site Plan and Parking plan G — Ordinance No. 35 RECEIVED 11/01/2017 ASPEN BUILDING DEPARTMENT - 4 - P 970.379.3709 F 970.963.15991 P.O.Box 6236 Sno Mnass Wage.CO PROJECT INTRODUCTION 1.1 Project Description The project consists of the renovation of a single family residence adjacent to the Aspen Club. The project is approximately 9361 square feet total area per architectural calculations including the garage. 1.2 Project Disturbance Area The disturbance will include all of the areas on the drainage. grading and landscape plans that are designated to be regraded and or landscaped_ Reference Roaring Fork Engineering civil and drainage plans for erosion controls. Soil disturbance shall be kept to a minimum. Rigid fencing shall be installed at all areas along the lower part of the property to protect the ditch and river. Construction staging and phasing shall occur, where applicable. to minimize disturbance to the surrounding neighborhood 1.3 Project Vicinity Map Reference site plan for map location PROJECT DOCUMENTATION 2.1 Permitting The following permits are being applied for by Thunderbowl Architects or will be by subcontractors awarded future contracts. As permits are deemed necessary and approved/issued the CMP will be updated to include them at the back of the CMP. • Building and MEP: February 14, 2017 2.2 Public Notification RECEIVED The first public notification will be posted 10 days prior to commencementbflrtik3ataal7 Demolition and excavation is tentatively scheduled to begin August 2017. ASPEN BUILDING DEPARTMENT 2.3 Project Sign See Attachment A - 5 - P 970.379.3709 F 970.963.1599 P.O.Box 6236 Snowrnass Vibge,CO PROJECT IMPLEMENTATION 3.1 Dates of Construction The current project start is scheduled for August 2017. Estimation of project duration is 16 months putting the projected completion date at December 2018. Any work within the City of Aspen Right of Way will not commence prior to obtaining the appropriate permit from the City of Aspen Department of Engineering. 3.2 Hours of Construction Construction hours will be limited to 7:30am —5:30pm Monday through Friday and 9:00am- 5:00pm on Saturday. All activities generating noise in excess of 80 decibels will require a noise suppression plan and be restricted to operating between 9:00am — 5:00pm Monday through Friday. Additional prohibited construction days are as follows: • Sundays • 4'h of July (Day and any associated weekend) • Memorial Day Weekend • Labor Day Weekend • Thanksgiving Day • Christmas Day • New Years Day 3.3 Sequencing of Construction See attachment E for project schedule. 3.4 Project Fencing The construction site will have a non-removable chain-link construction fence of 6 feet in height with mesh windscreens along Crystal Lake Road. with an access gate at the driveway. See CMP Site Plan —ATTACHMENT F �E 3.5 Tree Protection RE " VED 11/01/2017 Clearwater Construction Management. Inc. will implement a tree protection plan from the project landscape designer (Connect One) prior to commencement of work. ASPEN BUILDING DEPARTMENT - 6 - P 970.379.3709 F 970.963.15991 P.O.Box 6236 Snow pass Vilage.CO PROJECT MANAGEMENT 4.1 Parking Management See CMP site plan Note: any parking areas that disturb soil shall be subject to erosion control regulations. 4.2 Emergency Access and Ordinance 35 Clearwater Construction Management will maintain continuous emergency vehicle access on and around the site, including but not limited to police. fire. and ambulance services See Ordinance 35 —ATTACHMENT G 4.3 Staging Areas The number of truck trips during construction will be approximately: • 25 - Excavation Equipment and Dump Trucks • 7 - Concrete Trucks • 3 - Concrete Pumps • 8 - Crane/Boom Truck • 30 - Lumber Deliveries • 15 - Miscellaneous Deliveries The majority of the dump truck and concrete truck traffic will occur in the first 3 months. The crane and boom truck days will follow the completion of concrete work as we set structural steel and hoist framing materials. Remaining deliveries will occur throughout the duration of the project. 4.4 Construction Trailer, Materials Storage, and Waste Management Under no circumstances will loose job materials be store° in the ROW. RECEIVED See CMP Site Plan for trailer, toilet, materials, and staging —ATTACHME Iy01/2017 ASPEN BUILDING DEPARTMENT - 7 - P 970.379.3769 F 970.963.1599 P.O.Box 6236 Snowmass Viage,Co TRAFFIC CONTROL 5.1 Haul Routes See Haul Route Map —ATTACHMENT C 5.2 Onsite Vehicle Limitations The construction vehicles required for the construction phase are as follows: • Dump truck— 54.000 GVW • Excavator— 54,000 GVW • Loader— 54,000 GVW • Hydraulic Crawler Drill —27,000 GVW • Crane —54,000 GVW • Boom Truck —45,000 GVW • Concrete Truck — 26.000 GVW (66,000 Fully loaded) • Concrete Pump Truck—55.750 GVW 5.3 Delivery Requirements When the size of delivery trucks will impact traffic a traffic control will be submitted to and coordinated with the Engineering Department. Deliveries will be coordinated so that only one delivery vehicle will be on site at any given time. Delivery vehicles and all other on-site vehicles will not be allowed to idle for more than five (5) minutes. with the exception of generators or PTO type operations. Project subcontractor and suppliers will be provided with written notification of Aspen's vehicle idling regulations. 5.4 Traffic Control Plan When the project requires interference with traffic on any public right-of-way Clearwater will obtain the applicable permits along with a traffic management plan prepared by a State Certified Traffic Control Supervisor. The plan will conform to the most cvg,Terrtt, . ` ,. 1 Manual of Uniform Traffic Control Devices for Streets and Highways (MUT Dy�` • `�� submitted to the City of Aspen Department of Engineering for approval/pe i�f he location of the demolition and deconstruction activities. we do not anticipat'rfy . 6Hth6 right of way. ASPEN BUILDING DEPARTMENT - 8 - P 970.379.3709 F 970.963.1599 P.O.Box 6236 Snownass Vilage.CO SEDIMENT AND EROSION CONTROL 6.1 Storm Water Pollution Prevention Plan This project disturbance area is in less than 1 acre and therefore it does not require a Construction General Permit, or SWPPP. Clearwater and its subcontractors will adhere to all erosion and sediment control designs as completed by the civil engineer. In consideration of the proximity to the Roaring Fork River, Roaring Fork Engineers will inspect the project periodically and coordinate any additional erosion control measures required to protect these sensitive areas. RECEIVED 11/01/2017 ASPEN BUILDING DEPARTMENT - 9 - P 970.379.3709 F 970.963.15991 P.O.Box 6236 Snoxmass Vilage.CO • FUGITIVE DUST CONTROL 7.1 Dust Control Plan A construction permit from the Colorado Department of Public Health and Environment will not be required as the planned area of disturbance in less than one acre. The project's Dust Prevention and Control Plan are as follows: • Avoid unnecessary site disturbance_ • During construction operations if dry or deemed otherwise necessary a water truck or water hose will be available as needed to mitigate air born dust. • During demolition of the existing home. there will be continuous dust control with a water truck to manage dust. During the excavation stage disturbed areas will be stabilized as detailed in the erosion control section of this CMP as soon as feasible. • Exported and Imported dirt will be delivered via covered dump trucks. 24 Hour Contact John Blatz. Clearwater Construction Management, Inc.: 970.379.3709 RECEIVED 11/01/2017 ASPEN BUILDING DEPARTMENT - 12 - P 970.379.3709 F 970.963.1599 P.O.Box 6236 Snowmass Vilage.CO EMISSIONS 8.1 Maintenance All vehicles and equipment used on site will be properly maintained such that the engines will function within the manufacture's standards or parameters. 8.2 Opacity Emissions from diesel engines operated within the City of Aspen shall be of a shade or density no darker than 40% opacity, except for starting motion no longer than 10 seconds or for stationary operation not exceeding 10 seconds. RECEIVED 11/01/2017 ASPEN BUILDING DEPARTMENT 13 - P 970.379.3709 F 970.963.1599 P.O.Box 6236 Snowrnass Vitage,CO NOISE SUPPRESSION General The noise limit for construction is 80 decibels measured at the property line of the construction site. All construction equipment shall be adequately muffled and maintained to minimize project noise. The installation of noise barriers is the minimum technique to suppress noise. especially when jack hammering of concrete occurs_ 9.1 Noise Suppression Plan All activity that generates noise in excess of 80 decibels requires a noise suppression plan and is restricted to operating between the hours of 9am and 5pm Monday through Friday. See Signed Noise Suppression Plan —ATTACHMENT D 9.2 Equipment and Methods In addition to the standard practices agreed to within the signed Noise Suppression Plan. the table below from the City of Aspens complete packet has been included for quick contractor/subcontractor reference. Noise Controls for Construction Equipment (Schneider et al., 1995) Equipment Noise Controls Pile Driver Enclosure, muffler Stone saw cutting Noise control pad with water Handheld impact drills Reduction of reflected sound Circular saw blades 15° tooth angle. new tooth configuration. slotted saw blades. viscoelastic damping Pneumatic tools Muffler RFGFiVF'1I Pavement breaker/ Muffler, enclosure of cylinder case and front head, moil damping Rock drill 11/01/2017 Portable air Muffler, acoustic enclosures compressor {' �AgSPEN Bulldozer Bulldozer Cab-liner material. enclosure. sound'Ia ionpinnTNENT canopy. sealing of all openings Wheeled loader Absorption of sound cooling air route Vibratory roller Flexible mounting for pump compartment - 14 - P 970.379.3709 F 970.963.15991 P.O.Box 6236 Sianmass Wage.CO ATTACHMENT A CLEARWATER CONSTRUCTION M A N A G E M E N 1 I N C 1419 Crystal Lake Road BUILDING PERMIT # (TBD) GENERAL CONTRACTOR: Clearwater Construction Management Inc. RECEIVED CO N TA CT: Jo h n Ch rgr , 017 (970) 618. 660 isS73UILDING DEPARTMENT 24 HOUR EMERGENCY CONTACT # : (970) 379.3709 N i• 1 i y Li. 6a g o LSj d IN N N cg v ® b� s I. r - ,K CO� _ 1 O 7 -1J G _ AyC 9 ti o! a C ° V 1 J J U 8 vol eJ IVED 1 -- 11/01/2017 a rx - a ASPEN E. to pBUIL[ NG DEPARTMENT ,V . ��- '- C ix 4x tti —'fi r s ,, am i C. _— V a, 0 1 Ti. E g Q) , c' E ii t N u - J 1 i o 4 `) f 8P N se c. 1 o. O. 4_ :=7., . . .. ., ati Ti 1 E z I. v 3 -__ .. 0 (e ® v _ ai n n m d � 1 Z ® rn l' a U ooie i N RECEIVED .,.. RI c 11/01/2017 0 cc i a) ASPEN - o UILRING DEPARTMENT USA Q4 2 J �t d co t m i O o ,6 I t ; i i }. - e It . $.y i , ? . 17P- ICI t II 4 4 .: t d ; . f I S'j i i ; Lsl ii-a II = - - - _ 1 I 0] 0 i 1, Li II i .off s 1u1 1 vt. Crklii I 2 46N CVV4d I') Y ID IAOPO P NNN NN N ^M..^O O O O O O O O O O O O O O O O O O O O O V O W O CD5 aaas aA-0A0z,-aa.aa �aa�-a- '_; RECEIVED - L L C C,-- C LL't li z LLL4444Is K t� 1► K {L LLLL4ti 1.,..„, -C '--)11.�,�mr-mmmmomoom000moommoomm. 11/01/2017 4Aa�vsas� A-cA-6 aa�aaeaaaaaz�� iiiiiiiiiiiiiiiiilliii0___ ASPEN _ BUILDING DEPARTMENT Vre;i;i titilliti isill ' cc # von a o,,,coNN.p v o.�vo�ooN �; ki i b 0 i ° g v n sY a P �_ ikk `c s `9 h g€t> ' 9 Q• , .4 L 111Fa'c_ c5? ch3g it8 $: 4 Yo ilireg �iy:gZei� u138 •gA gl1V1c4, I. 9:499A99k j W u}LL LL K LL'W W W W C'� � V<1r J V LL 4111 dam; E' - - - - jilt _C i awu 3 od ONeltd Y f S = - _ - ill 3)IY7 97 a CO n�dsv V U uw. 7YlS.t�6lll Airratalla MR i ? 4----- c ` e V 6 ----------\ii\ PI �•• • __ �} \ ''. ‘ \ ' .QFJ 1...11.♦1 ot•o••wt \.,.. �. • •.••1...♦ 1 • . ♦•♦ V , -e ...... \ to •l •ii'i'•'i•. • ••es:=0• _/ "7 , .. ...21?-1:,..-i ___\ • • • • • • 1 • .1 ... 0 ••y. _11 r�.r•❖.' -:� �� + • •�.••►•• • •.'_ _ _._ �. A/ • f ® •••••. S /' i...•a• r • •..•.:0 • y. , •'i' i •1 ••••••• o •6 4r • ! / c.) r_p ) ,4 ,,- ci lo.. .::::: I i $*-- . . . . . ,z i f___ c.) , / _,..._.- 1.....-.4..._. . .. _•__ ..•.•. • •�•:: ,.; . . . . WEli tua. , :(i - , X*: '-' ‘41-..\,: .*.•.•. t_\ .1` ,I e / � :• a •...... C 'I <:::r • /6W2017 1 1►i.•a••�a...•a• _• t r , } / fat ..,....) : . • . i\:::[3 X ••• , . , , . - • •••• s) .,s,i,.. 1-,1[ARTMENT i•:!• :❖.:-* " ._- A / I / ._ z � ill ! l___ VI ill .-. e -•_-=its— _ �r/- ---'• _� /47 --r4c f-fr"1Li.) ORDINANCE NO.35 (SERIES 2013) AN ORDINANCE OF THE CITY COUNCIL OF THE CiTY OF ASPEN, COLORADO, AMENDING TITLE 8 OF THE ASPEN MUNICIPAL CODE BY AMENDING CERTAIN SECTIONS OF THE 2009 INTERNATIONAL BUILDING AND RESIDENTIAL CODES. WHEREAS.the purpose of this code is to provide for and promote the health, safety and welfare of Aspen residents and visitors: and WHEREAS,the administration of the provisions of the adopted codes is responsibility of the Chief Building Official and a matter of importance to persons engaged in construction activities:and WHEREAS,the Chief Building Official,also referred to herein as the"building official"is authorized by the City Council to administer and enforce this code: and, WHEREAS,the changes proposed herein eliminate the administrative allowance for issuing a "Conditional Certificate of Occupancy"thereby reverting to the provisions of the international Residential Code and the International Building Code for the administrative allowance for issuing a "Temporary Certificate of Occupancy'; and, WHEREAS, it is in the best interest of the development review agencies and development community and the citizens to maintain a uniform enforcement policy; and, WHEREAS, it is in the best interest of the citizens and visitors to our community to main a leadership role in efficient building code administration. NOW THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF ASPEN, COLORApO,THAT: • Section 1. Chapter 8.16.020, subsection g of the Aspen Municipal Code, which REGEWEDie administrative issuance of a Conditional Certificatc.of Occupancy. is hereby amended to read as follows: Chapterft.l6 11/01/2017 INTERNATIONAL RESIDENTIAL CODE , ASPEN 3UILDING DEPARTMENT Sec.8.16.020. Amendments. [no changes to subsections a through e] (g)reserved [no changes thereafter] 1 Add new section to read as follows: Sec.8.16.030. Violations and penalties. (a) it shall be unlawful for any person, including an owner,occupant or builder,to erect,construct, enlarge. alter,repair,move,improve, remove, convert or demolish,quip. use.occupy or maintain any building or structure in the City or cause the same to be done,contrary to or in violation of any of the provisions of this Code. (b)A violation of any of the provisions of the Code shall constitute a misdemeanor, punishable upon conviction by a tine. imprisonment, or both a fine and improvement.as set forth in Section 1.04.080 of this Code. A separate offense shall be deemed committed on each day or portion thereof that the violation of any of the provisions of this Code occurs or continues unabated after the time limit set for abatement of the violation. Section 2. Chapter 8.20.020. subsection j of the Aspen Municipal Code, which subsection describes the administrative issuance of a Conditional Certificate of Occupancy, is hereby amended to read as follows: Chapter R.20 INTERNATIONAL BUILDING CODE Sec.8.20.020. Amendments [no changes to subsections a through i] 01 reserved[no changes thereafter] RECEIVED 11/01/2017 Section 3. ASPEN This ordinance shall become effective 30 days following passage. BUILDING DEPARTMENT Section 4. This ordinance shall not have any effect on existing litigation and shall not operate as an abatement of any action or proceeding now pending under or by virtue of the ordinances repealed or amended as herein provided, and the same shall be construed and concluded under such prior ordinances. Section 5. If any section, subsection, sentence, clause,phrase or portion of this ordinance is for any reason held invalid or unconstitutional in a court of competent jurisdiction, such portion shall be deemed a separate, distinct and independent provision and shall not affect the validity of the remaining portions thereof. A public hearing on the ordinance was held on the 23th of September, in the City Council Chambers. Aspen City Hall. Aspen, Colorado. INTRODUCED,READ AND ORDERED PUBLISHED as provided by law by the City Council of the City of Aspen on the 28`h day of August. 2013. Steven Skadron, Mayor ATTEST: Kathryn S. Koch, City Clerk APPROVED AS TO FORM: James R. True, City Attorney RECEIVED FINALLY adopted.passed and approved this day of , 2013.11/01/2 017 ASPEN BUILDING DEPARTMENT Steven Skadron, Mayor ATTEST: Kathryn S. Koch, City Clerk