HomeMy WebLinkAboutFile Documents.120 S Spring St.0326.2017 (3).ARBK APPROVED
1.0 GENERAL DATE
Total soil disturbance is zero BY
Total Demo is about 600 square feet
2.0 PROJECT DETAILS
2.1 Disturbance Area is about 600 square feet
2.2 Location is 120 Spring street Aspen CO 81611 (Attached Map)
2.3 Remodel of a condo unit for owners, refinishing floors, installing new kitchen
upgrading bathrooms, moving several walls to provide extra space in bedrooms
3.0 PERMITS
3.1 Will be attached when issued
3.2 Contractor will inform all units in the condo complex of work to be done Via
Email and Contact the HOA
3.3 Project sign shall be posted per city municipal code 26.510.03064
3.4 Contacts
Owners: Garry Ruth :917-566-6035/Email: Garyruthdds@gruthdds.com
Contractor: A&L Construction:970-404-0743/Email Lior@alconstruction.org
Supervisor: Rob Fisher:9709307617/Email Rob@alconstruction.org
Architect: Tim Andrulaitis:9704298470/Email:Tim@zone4architects.com
4.0 PROJECT IMPLEMENTATION
4.1 Date of construction will start after permits approval and HOA Guideline
And will Take approximately 16 weeks
4.2 The project will follow the Central Resort Area Schedule RECEIVED
01/29/2018
ASPEN
BUILDING DEPARTMENT
4.3
4.4 Adjoining Properties N/A
4.5 Project Fencing N/A
4.6 No Negative Aspect in Anticipated within the project
4.7 No Negative on Aspen natural environment is Anticipated
5.0 SITE AND RIGTH OF WAY MANAGEMENT
5.1 No use of right of way is Anticipated
5.2 Flow of emergency Vehicle will not be interrupted
5.3 Will be using Carpool and Manager driving from parking lot
5.4 Staging of materials will occur inside the job site, delivery will use the garage
Door on the side of building
5.5 N/A
5.6
5.7 Demo Materials will be Separated and taken to landfill
6.0 N/A
7.0 N/A
8.0 N/A
9.0 N/A
10.0 EMISSIONS
10.1 No vehicles idle will be permitted on site.
10.2 The project intends to comply with city codes
RECEIVED
01/29/2018
ASPEN
BUILDING DEPARTMENT
11.0 NOISE SUPRESSION
11.1 The project intends to keep the noise level under city limit
11.2 N/A
11.3 N/A
11.4 N/A
11.5 N/A
11.6 N/A
12.0 ENFORCMENT
12.1 N/A
12.2 N/A
12.3 N/A
13.0 N/A
14.0 N/A
RECEIVED
01/29/2018
ASPEN
BUILDING DEPARTMENT