From:Hanna Werner <hanna@annegrice.com>
Sent:Thursday, May 16, 2019 11:59 AM
To:Nick Thompson
Cc:Anne Grice; Denis Murray
Subject:Re: Plan Review Comments for 610 S West End St #F304
Attachments:Asbestos Report The Gant F-304 Aspen, Co..pdf; Pella Window Schedule_REVISED
5.15.19.pdf; MILLS_F304_PROPOSED PLAN_.pdf; TMR Product data 072015.pdf
Hi Nick,
Please see below items w/ attachments.
1. Asbestos Report attached.
2. We are removing skylight at entryway and replacing with a Velux sun tunnel w/ (U-Factor 0.51) spec. attached
3. W&D duct route & vent termination shown on Electric/Mechanical plan. (A-ID.02)
4. See detail/ceiling assembly w/ 1-hr fire rated Type X board. (L-ID.03)
5. Quiet Rock ES specification is U309 & U340 compliant. (E-ID.03)
6. Combustible mantle material is 13" from fireplace opening. (J-ID.03)
7. Combustible material on the left side of fireplace does not project more than 1-1/2" from fire place face.
8. Existing hearth extension is being replaced by solid-stone (J-ID.03)
9. Exterior doors have a U-Value of 0.27 (see Pella schedule.)
Thank you,
Hanna Werner
Anne Grice Interiors
408 ABC, Suite 201
Aspen, CO 81611
970-429-4148
www.annegrice.com
To help protect your privacy, Microsoft Office prevented automatic download of this picture from the
Internet.
https://www.facebook.com/?ref=logo
To help protect your privacy, Microsoft Office prevented automatic download of this picture from
the Internet.
https://www.instagram.com/annegriceinteriors/?hl=en
To help protect your priv acy, Microsoft Office prevented automatic download of this picture from the Internet.
https://www.houzz.com/user/annegriceinteriors
2
To help protect your privacy, Microsoft Office prevented automatic download of this picture from the Internet.
46.5
On Tue, May 14, 2019 at 5:49 AM Anne Grice <anne@annegrice.com> wrote:
Sent from my iPhone
Anne Grice Interiors
www.annegrice.com
Begin forwarded message:
From: Nick Thompson <nick.thompson@cityofaspen.com>
Date: May 13, 2019 at 2:47:17 PM CDT
To: "anne@annegrice.com" <anne@annegrice.com>
Cc: Denis Murray <denis.murray@cityofaspen.com>
Subject: Plan Review Comments for 610 S West End St #F304
Hi Anne,
I've reviewed your permit application; please see the attached comment list. Please contact me directly
if you have any questions on the comments. Get in touch with your permit coordinator to schedule a
resubmittal or for questions regarding the overall status in the queue of your permit.
Address: 610 S West End St #F304
Permit Number: 0068.2019.ARBK
Code: 2015 IBC
These design documents have been reviewed for conformance to the International Codes as adopted
and amended by the City of Aspen. State and Federal regulations are administered where applicable.
You can find a copy of all adopted codes, ordinances, and policies on our website.
The attached corrections are required to be addressed. Revise and redraw the plans to clearly respond
to the attached comments and resubmit this comment letter with your written response to each
comment on this list. Indicate which detail or specification page shows the required information.
Responses such as "will comply with code" are not adequate. Revised drawings must clearly show code
compliance.
Re-submittal: When all items from all agencies have been addressed regarding the comments below,
call 970-920-5090 to schedule a required appointment for re-submittal with your Permit
Coordinator. You will be required to bring a copy of this letter with ALL responses and required
documentation. If all items listed have not been addressed, the resubmittal will be deemed
incomplete, and will not be accepted.
3
Building plan check is only one part of the often complex process by which projects are reviewed for
approval. These parts are interrelated and are sometimes conflicting. It is ultimately the applicant's
responsibility to coordinate these requirements.
Thanks,
Nick Thompson
Plans Examiner
City of Aspen Community Development
(970) 429-2757 | cell (970) 456-5165 | fax (970)920-5440
www.aspenpitkin.com
Stay up to date with Community Development changes and requirements by signing up for our
newsletter. Our new 2015 code adoption went into effect February 9, 2017.
Notice and Disclaimer:
This message is intended only for the individual or entity to which it is addressed and may contain
information that is confidential and exempt from disclosure pursuant to applicable law. If you are not
the intended recipient, please reply to the sender that you have received the message in error and
then delete it. Further, the information or opinions contained in this email are advisory in nature only
and are not binding on the City of Aspen. If applicable, the information and opinions contained in the
email are based on current adopted building codes and code administration, which are subject to
change in the future, and upon factual representations that may or may not be accurate. The opinions
and information contained herein do not create a legal or vested right or any claim of detrimental
reliance.