MEMO
Project: 21523.00 – Lot 12 (754 Moore Drive)
Permit No.: 0034.2018.ARBK
Subject: Supplemental Information for Building Comments 2
Date: 14 April 2020
To: John Barker, Lead Permit Coordinator
From: Sara Upton, Rowland+Broughton Architecture & Urban Design
Cc:
Comment – Provide handrails at all stairs with more than 3 risers. 2015 IRC R311.7.8
Response – The 3 site stairs have been revised to have 3 risers and hence do not require the
handrail. Please refer to the attached documents that illustrate this revision.
Drawings –
Civil: As requested, we are attaching the full set of Civil Documents for your records.
C6.0
o Revise BBQ patio drainage and grade
o Revise steps from BBQ area to grass area (3 risers)
o Revise grading at the grass area along the steps leading to the spa area
o Revise steps from grass area to the spa/pool (3 risers)
Landscape:
L3-02, L4-02, L6-02, L8-02, and L9-02
o Revised the site stairs at the grill area to have 3 risers
o Revised the site stairs at the spa area to have 3 risers
Comment - Outdoor Firepit - Install with clearances per manufacturer's instructions and must comply
with manufacturer's installation instructions, including clearances to combustibles and structure.
Response - The location of the outdoor firepit complies with the manufacture’s requirements. Please
refer to the attached Firepit burner manufacturer manual.
Documents - 103100-4.2 - Outdoor Fireplace Product Data
Thank You,
Sara Upton
04/15/2020