HomeMy WebLinkAboutFile Documents.395 Thunderbowl Ln.0002-2020-BCHO (15)FROM: Bob Narracci, Zoning Administrator, City of Aspen
TO: Roger Hall, David Johnston Architects
DATE: January 24, 2020
Address: 395 Thunderbowl Ln
Permit Number: 0020-2020-BCHO
Parcel Number: 273514310007
Owner: Aspen Extreme 2, LLC
Permit Coordinator: John Barker
These design documents have been reviewed for conformance with the Land Use Code as adopted and
amended by the City of Aspen. You can find a copy of the Land Use Code on our website.
Attached are the comments Zoning. All comments must be addressed. Please revise and redraw the
plans to clearly respond to the comments. Revised drawings must clearly show code compliance. Please
resubmit the attached comment letters with your written response to each comment. Your response
should indicate which detail or specific page shows the required information. Responses such as “will
comply with code” are not adequate.
Zoning plan check is only one part of the review process by which projects are reviewed for approval. If
you choose to begin updating plans prior to receiving comments from all review agencies, you assume
the risk of needing to update or otherwise redo your plans.
If you have any questions regarding the Zoning comments, please contact Zoning staff.
Re-submittal: When all comments from all agencies have been addressed, contact your Permit
Coordinator. If all comments have not been addressed, the resubmittal will be deemed incomplete, and
will not be accepted.
Zoning Comments:
Please see the attached red-marked plan sheets. Following is a summary of the red-mark comments:
1) Plan Sheet A-2.1
a. Please add topographic contours. –
Response: DJA has clarified heights of grade adjacent to patios with spot elevation
markers.
b. Per the PUD: Decks, balconies, stairways and similar features: Structures that exceed
thirty inches above Accepted or Finished Grade, and that are not covered by a roof or
architectural projection form a building, are exempt from Floor Area for up to fifteen
percent of the maximum Floor Area allowed. Any areas in excess of fifteen percent of
allowed area shall be counted toward Floor Area.
Response: DJA has clarified which features exceed 30” and have added those into the
deck calcs on sheet Z.03.
Please verify that the changes proposed are consistent with the above language and do
not change the deck exemption calculations.
03/19/2020
c. The concrete patio feature on the west side of the pool must be contained within the
Building Envelope. Please revise this sheet, and Sheet A7.29 accordingly.
Response: DJA has revised the patio feature to fit within the building envelope.
d. The trellis over the outdoor shower is counted as deck area. Please verify that the deck
calculations did not change or revise the calculations accordingly.
Response: Bob Narracci has confirmed that this comment is not applicable.
e. Fence height is measured from finished grade, inclusive of the retaining walls that the
fences are sitting on top of. For fences located behind the street facing façade of the
residence, the total allowed height is six feet from finished grade. For fences located
between the right-of-way and the street facing façade of the residence, the total
allowed height is 42 inches measured from finished grade. In both cases, please
measure the total height from both inside the mechanical pits and outside; the
maximum height applies to both sides.
Response: DJA has shown compliance to height restrictions.
(Refer to sheetsA-7.22, A-7.23, A-7.24 & A-7.25)
In addition to the clouded areas, please provide notation as to what plan sheets and
detail renderings apply to each clouded area.
Response:
-DJA has added callout to reference Sheet A-7.29. All the detail callouts on
sheet A-7.29 are applicable.
-DJA has called out the enlarged plans for the Condenser Enclosures
2) Plan Sheet A-7.29
a. The concrete patio feature on the west side of the pool must be contained within the
Building Envelope. Please revise this sheet, and Sheet A-2.1 accordingly.
Response: DJA has revised the patio feature to fit within the building envelope.
3) Plan Sheet A-7.31
a. The height of detail number three (Section at west pool edge and planter) is greater
than 30”, and therefore counts towards the deck calculations. Please either decrease
height to 30” or provide updated deck calculations.
Response: DJA has shown compliance to height restrictions.
(Refer to sheetsA-7.22, A-7.23, A-7.24 & A-7.25)
4) Plan Sheet A-7.32
a. Please clarify on Sheet A-2.1 where exactly the detailed renderings are proposed. The
height of details two and three appear to be over 30” and will change the deck
calculations. Please either decrease the height to 30” or provide updated deck
calculations.
Response: DJA has added note on a-7.32 which explains the detail callouts.
The new proposed trellis over the outdoor shower is included as deck. Please update the deck
calculations accordingly.
Response: Bob Narracci has confirmed that this comment is not applicable.
03/19/2020
Please contact me at (970) 429-2754 with any questions you may have.
Thank you,
Bob Narracci
03/19/2020