HomeMy WebLinkAboutFile Documents.837 W Smuggler St.0089-2020-BCHOThese plans must be kept at the
building site or inspection
delays may occur. Construction
shall conform to these plans. All
changes shall be approved by
the building official.
Field Plan Set Must Be Printed In Color
SEPARATE PERMITS ARE
REQUIRED FOR ELECTRICAL,
PLUMBING, MECHANICAL, OR
FIRE SPRINKLER WORK
External Energy Use Approved
RREMP CREMP
PERMIT #:_______________DATE:________
SNOWMELT:_____________________________
POOL: _____________________________
SPA: _____________________________
OFFSET:________________________________
REMP SHEET: __________________________
REVIEWED BY: _________________________
SNOWMELT SYSTEM AND EQUIPMENT MANDATORY REQ’S.
All snowmelt systems shall meet the following:
-Any portions in the Right of Way must be on a separate zone. A ROW
permit and Permanent Encroachment License are required.
-R10 insulation shall be installed under the area to be snow melted or R5
insulation shall be installed under and at the slab edges. (Ordinance 11
Series 2011)
-Automatic controls installed for system shut off when pavement
temperature is above 50°F and no precipitation is falling. (2009 IECC
Sec. 403.8 & 503.2.4.5)
-Automatic or manual controls installed for system shut off when outdoor
temperature is above 40°F. (2009 IECC Sec. 403.8 & 503.2.4.5)
-Inspection by testing hydrostatically at 1½ times max system design
pressure, but not less than 100psi, for 15minutes. (2009 IMC Sec.
1208.1)
MINIMUM BOILER AFUE: _________________
0089-2020-BCHO 11-23-20
325
DAM
ELLECTRIC 100%
MI.01 AND M1.02
0069-2020-BCHO
837 WEST SMUGGLER
2