HomeMy WebLinkAboutFile Documents.395 Thunderbowl Ln.0153.2017 (76).ARBKTHUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN Thunderbowl Lot #7 395 Thunderbowl Ln, Aspen, CO 81611 Parcel ID: 273514310007 Construction Management Plan Background: This Construction Management Plan (CMP) outlines and details the construction management measures that will be employed throughout the construction process of 395 Thunderbowl Ln. Lot #7, Aspen, CO 81611. This CMP is intended to address all items that are applicable to the scope of work in said project. Where items are not applicable to the scope of work, the CMP will note this. The provided CMP will outline supplemental information along with its location when addressed in the attached appendices. 2.0 Project Introduction 2.1 Project Location- Project is located at 395 Thunderbowl Ln. / Aspen Highlands Village Block: A Lot: 7 City of Aspen, County of Pitkin, State of Colorado. See Appendix A for a Detailed Project Vicinity Map. 2.2 Disturbance Area- .693 acres 2.3 Description of work- The scope of work will include all that is necessary for the construction of a 9,500SF single-family residence. Project duration is estimated at 27 months from acceptance of Building Permit until Close-out. All utilities connections will be coordinated and completed prior to the completion of work. Construction waste will be hauled off via Haul/Emergency Access Map to the Landfill for recycling. See Appendix B 3.0 Project Documentation 3.1 Permits- A. Building Permit- Please reference the permit application B. MEP Permits- Please reference the permit application C. Tower Crane Permit- Please reference the permit application 3.2 Public Notification- A letter shall be sent to all neighbors within 300 feet of the Project no less than ten days prior to construction, along with monthly updates until Project completion. Updates are to identify any traffic/pedestrian concerns and to outline hauling/staging operations. A pre-construction meeting between the Site Supervisor and all Sub-Contractors shall occur ten days prior to construction with all impacted stakeholders to be notified as well. 3.3 Project Sign- See Appendix C City of Aspen Received 07/26/17 Building Department THUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN 3.4 Project Contacts- Owner Rep: James I. Veshancey 1261 Juniper Hill Road Aspen, CO 81611 (970) 319-8686 Office jamesve@me.com Contractor: Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 Project Manager: Brian Hanlen (970) 945-0147 Office (970) 846-3216 Mobile Site Supervisor: Phil Perry Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 (970) 456-7370 Mobile Safety Officer: N/A (Contact Site Supervisor) Traffic Officer: N/A (Contact Site Supervisor) Erosion Control: N/A (Contact Site Supervisor) 4.0 Project Implementation: 4.1 Dates of Construction- Pending Contract Procurement 4.2 Hours of Construction- Will be limited to 7:30 a.m. to 5:30 p.m. Monday through Friday, 9:00 a.m. through 5:00 p.m. Saturdays, with no work permitted on Sundays and federally designated holidays and other construction limitations set by the City of Aspen. 4.3 Sequence of Construction- See Appendix D- Project Schedule 4.4 Adjoining Property Owners- Adjoining properties will be protected from onsite runoff by silt fencing and Project-Site isolation. Notification of all foreseen disturbances will be communicated to adjacent neighbors by the Site Supervisor. All notices will be made prior to the initiation of any such disturbances; this includes but is not limited to: noise disturbances, hauling/staging, Right of Way limitations/disruptions. 4.5 Project Fencing- See Appendix E- Site Plan City of Aspen Received 07/26/17 Building Department THUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN 4.6 Natural Environment- No adverse effects on the nearby, natural environment are anticipated. Any unforeseen environmental impacts will be promptly mitigated by Structural Associates’ management team and controlled in accordance with the City of Aspen’s building regulations. 5.0 Project Management: 5.1 Parking Management- All parking to be contained along street front or public parking areas designated by permit. 5.2 Emergency Vehicle Access- Emergency vehicle access will not be affected by the scope of work identified in this CMP. See Appendix B- Haul/Emergency Access Map 5.3 Parking Details- Public transportation and carpooling efforts will be made to reduce the amount of onsite parking required for construction. Parallel parking will be available along site-curb with additional parking available on the North end of site (as needed). See Appendix E- Site Plan 5.4 Staging Areas- Designated staging area will be limited to onsite property boundary. 5.5 Construction Trailer, Materials Storage, and Waste Management- A construction trailer will be required as a jobsite office. Material storage will be reserved to on-site and identified on the CMP site plan. A dumpster will be located on-site and efforts will be made to recycle cardboard, drywall, wood, and metal via small waste containers. A bear proof container for food will be adjacent to the dumpster. Portable restrooms will be available for workers. 6.0 Traffic Control 6.1 General- All required traffic control shall be performed on-site by supervisory staff. Professional Traffic Control Companies will be contracted as required. 6.2 Haul Routes- See Appendix B- Haul/Emergency Access Map 6.3 Delivery requirements- No affect on any public roads will occur as a result of the scope of work identified in this CMP. Due to staging limitations, only (1) delivery will be permitted at any one time. Delivery schedule shall fall within the general project hours of 7:30 to 5:30 Monday through Friday. No idling of delivery vehicles will be permitted for longer than five minutes. 6.4 Traffic Control Plan- All construction related traffic shall be controlled and maintained by the on-site Supervisor as outlined in the Haul/Emergency Access Map. See Appendix B 7.0 Pedestrian Protection 7.1 General- All construction activity will comply with safety per MUTCD chapter 6D, the Americans with Disability Act, and IBC Chapter 33. City of Aspen Received 07/26/17 Building Department THUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN 8.0 Sediment and Erosion Control 8.1 Requirements- Erosion control and storm water management will be as directed by the project’s civil engineer and shown on designated plan sheets: (Erosion Control Plan, Storm Water Management Plan). A perimeter encompassing silt fence will aid in the mitigation of onsite runoff; SA is to ensure proper installation and maintenance. 9.0 Fugitive Dust Control 9.1 Fugitive Dust Control Plan- All fugitive dust will be controlled by watering as required. 10.0 Emissions 10.1 General- All onsite vehicles/equipment will be maintained to manufacturer’s specifications. 10.2 Diesel Engines- Emissions from diesel powered engines shall have an opacity of no darker than 40% except for ten seconds during start up. 11.0 Noise Suppression 11.1 General- All construction activity shall comply with the City of Aspen’s noise limitations. Appendices: Appendix A: Project Vicinity Map Appendix B: Haul/Emergency Access Map Appendix C: Project Sign Appendix D: Project Schedule Appendix E: Site Plan City of Aspen Received 07/26/17 Building Department Structural Associates Construction Management Plan   Appendix A: Project Vicinity Map City of Aspen Received 07/26/17 Building Department Structural Associates Construction Management Plan   Appendix B: Haul Route / Emergency Access City of Aspen Received 07/26/17 Building Department Structural Associates Construction Management Plan   Appendix C: Project Sign City of Aspen Received 07/26/17 Building Department ID Task Name Duration Start Finish 1 PRE-CONSTRUCTION 38 days Thu 7/20/17 Mon 9/11/17 2 Permits 30 days Thu 7/20/17 Wed 8/30/17 3 Survey 1 day Fri 9/1/17 Fri 9/1/17 4 Jobsite layout (Trailer, Dumpster, Temp Toilet, Silt Fence, Parking, & Laydown) 5 days Tue 9/5/17 Mon 9/11/17 5 EXCAVATION 159 days Fri 9/8/17 Fri 5/4/18 6 Grub Site 1 day Fri 9/8/17 Fri 9/8/17 7 Create Jobsite Access & Parking 3 days Fri 9/8/17 Tue 9/12/17 8 Install Temporary Electrical Panel 1 day Tue 9/12/17 Tue 9/12/17 9 Strip & Stockpile Topsoil 4 days Tue 9/12/17 Fri 9/15/17 10 Excavate Foundation 11 days Fri 9/15/17 Fri 9/29/17 11 Underground Slab Prep 5 days Mon 11/13/17Fri 11/17/17 12 Install Foundation Drain 5 days Wed 11/15/17Tue 11/21/17 13 Backfill Foundation 11 days Mon 11/20/17Fri 12/8/17 14 Finish Backfill 5 days Mon 12/18/17Fri 12/22/17 15 Final Grade 5 days Mon 4/30/18Fri 5/4/18 16 UTILITIES 10 days Mon 4/23/18Fri 5/4/18 17 Install Water Line 2 days Mon 4/23/18Tue 4/24/18 18 Install Sewer Line 3 days Wed 4/25/18 Fri 4/27/18 19 Install Natural Gas Line 3 days Mon 4/30/18Wed 5/2/18 20 Install Phone & Cable Line 2 days Thu 5/3/18 Fri 5/4/18 21 CONCRETE 165 days Thu 9/28/17 Fri 6/1/18 22 Form & Pour Footings 8 days Thu 9/28/17 Mon 10/9/17 23 Form & Pour Walls 24 days Tue 10/10/17Fri 11/10/17 24 Form & Pour Lower Slab 5 days Mon 12/11/17Fri 12/15/17 25 Form & Pour Garage Slab 5 days Mon 5/28/18Fri 6/1/18 26 SITE CONCRETE 21 days Mon 11/13/17Fri 12/15/17 27 Form & Pour Site Footings 9 days Mon 11/13/17Wed 11/29/17 28 Form & Pour Site Walls 15 days Fri 11/24/17 Fri 12/15/17 29 UNDERGROUND MEP 16 days Mon 11/13/17Fri 12/8/17 30 Underground Radon Rough-in 3 days Mon 11/13/17Wed 11/15/17 31 Underground Plumbing Rough-in 4 days Thu 11/16/17Tue 11/21/17 32 Install Rigid Foam Insulation 4 days Tue 11/28/17Fri 12/1/17 33 Hydronic Rough-in 5 days Mon 12/4/17Fri 12/8/17 34 WATERPROOFING 26 days Mon 11/13/17Fri 12/22/17 35 Waterproof Foundation Walls 5 days Mon 11/13/17Fri 11/17/17 36 Waterproof Site Walls 5 days Mon 12/18/17Fri 12/22/17 37 STRUCTURAL STEEL 118 days Mon 10/2/17Fri 3/30/18 38 Structural Steel Shop Drawing Review & Approval 20 days Mon 10/2/17Fri 10/27/17 39 Main Level Steel Fabrication 16 days Mon 11/13/17Fri 12/8/17 40 Deliver & Install Main Level Structural Steel 10 days Mon 12/11/17Fri 12/22/17 41 Upper Level Steel Fabrication 15 days Mon 1/22/18Fri 2/9/18 42 Deliver & Install Upper Level Structural Steel 10 days Mon 2/12/18Fri 2/23/18 43 Roof Level Steel Fabrication 15 days Mon 2/26/18Fri 3/16/18 44 Deliver & Install Roof Level Structural Steel 10 days Mon 3/19/18Fri 3/30/18 45 FRAMING 110 days Wed 12/6/17Fri 5/18/18 46 Set Tower Crane 3 days Wed 12/6/17 Fri 12/8/17 47 Lower Level Framing 22 days Mon 12/11/17Fri 1/19/18 48 Main Level Framing 35 days Mon 1/22/18Fri 3/9/18 49 Upper Level Framing 20 days Mon 2/26/18Fri 3/23/18 50 Roof Framing 30 days Mon 3/26/18Fri 5/4/18 51 Finish Framing 20 days Mon 4/23/18Fri 5/18/18 52 ROOFING 292 days Mon 5/14/18Fri 7/12/19 53 Dry-In 15 days Mon 5/14/18Fri 6/1/18 54 Install Metal Roofing 25 days Mon 6/4/18 Fri 7/6/18 55 Install Snow Guards and Fences 10 days Mon 7/2/18 Fri 7/13/18 56 Install Chimney Caps 2 days Fri 7/13/18 Mon 7/16/18 57 Install Gutters & Downspouts 10 days Mon 7/16/18Fri 7/27/18 58 Install Heat Tape 5 days Mon 7/30/18Fri 8/3/18 59 Preparation for Green Roof 15 days Mon 6/3/19 Fri 6/21/19 60 Install Decorative Ballast 15 days Mon 6/24/19Fri 7/12/19 61 WINDOWS & DOORS 170 days Mon 11/13/17Tue 7/24/18 62 Window & Ext Door Shop Drawings 16 days Mon 11/13/17Fri 12/8/17 63 Window & Ext Door Shop Drawings Review12 days Mon 12/11/17Fri 1/5/18 64 Order Window & Exterior Doors 1 day Mon 1/8/18 Mon 1/8/18 65 Windows & Door Delivery 2 days Thu 5/24/18 Fri 5/25/18 66 Window & Ext Doors Installation 20 days Mon 5/28/18Fri 6/22/18 67 Garage Door Installation 2 days Mon 7/23/18Tue 7/24/18 68 EXTERIOR DECORATIVE STEEL 45 days Mon 4/30/18Fri 6/29/18 69 Shop Drawings & Review 15 days Mon 4/30/18Fri 5/18/18 70 Ext. Steel Fabrication 15 days Mon 5/21/18Fri 6/8/18 71 Installation of Ext. Decorative Steel 15 days Mon 6/11/18Fri 6/29/18 72 EXTERIOR FINISHES 278 days Fri 3/9/18 Fri 4/19/19 73 Order Wood Siding & Trim 1 day Fri 3/9/18 Fri 3/9/18 74 Pre-Finish Wood Siding & Trim 10 days Mon 4/30/18Fri 5/11/18 75 Install Soffit & Fascia 25 days Mon 5/14/18Fri 6/15/18 76 Install Wood Siding 45 days Mon 6/18/18Fri 8/17/18 77 Build Pergola 10 days Mon 8/20/18Fri 8/31/18 78 Install Alternative Wood Siding 35 days Mon 3/4/19 Fri 4/19/19 79 EXTERIOR MASONRY 115 days Mon 4/30/18Fri 10/5/18 80 Install Wall Veneer 60 days Mon 4/30/18Fri 7/20/18 81 Site Wall Veneer 30 days Mon 7/9/18 Fri 8/17/18 82 Install Patio 20 days Mon 8/6/18 Fri 8/31/18 83 Install Upper Patio 25 days Mon 9/3/18 Fri 10/5/18 84 MEP ROUGH-IN 66 days Mon 5/7/18 Mon 8/6/18 85 Fire Suppression System Rough-In 25 days Mon 5/7/18 Fri 6/8/18 86 HVAC Rough-In 55 days Mon 5/14/18Fri 7/27/18 87 Pluming Rough-In 30 days Mon 5/28/18Fri 7/6/18 88 Water Treatment Install 10 days Mon 6/18/18Fri 6/29/18 89 Electric Rough-In 40 days Mon 6/11/18Fri 8/3/18 90 AV Rough-In 25 days Mon 7/2/18 Fri 8/3/18 91 Security Pre-Wire 15 days Mon 7/9/18 Fri 7/27/18 92 Rough-In Inspection 1 day Mon 8/6/18 Mon 8/6/18 93 BUILD MECHANICAL ROOM 30 days Mon 9/10/18Fri 10/19/18 94 HVAC 20 days Mon 9/10/18Fri 10/5/18 95 Plumbing 10 days Mon 10/1/18Fri 10/12/18 96 Electric 10 days Mon 10/8/18Fri 10/19/18 97 INSULATION 14 days Tue 8/7/18 Fri 8/24/18 98 Insulate Walls 9 days Tue 8/7/18 Fri 8/17/18 99 Insulate Roof 8 days Mon 8/13/18Wed 8/22/18 100 Insulation Inspection 2 days Thu 8/23/18 Fri 8/24/18 101 INTERIOR MASONRY 64 days Tue 8/14/18 Fri 11/9/18 102 Install wall veneer 34 days Tue 8/14/18 Fri 9/28/18 103 Install stone floors 10 days Mon 10/29/18Fri 11/9/18 104 POOL ROUGH-IN 15 days Mon 5/21/18Fri 6/8/18 105 Excavate Pool & Spa 5 days Mon 5/21/18Fri 5/25/18 106 Rough-In for Pool & Spa 5 days Mon 5/28/18Fri 6/1/18 107 Form and Pour Pool & Spa 5 days Mon 6/4/18 Fri 6/8/18 108 DRYWALL 247 days Mon 8/6/18 Fri 8/2/19 109 Hang Drywall 30 days Mon 8/27/18Fri 10/5/18 110 Tape & Finish 35 days Mon 9/17/18Fri 11/2/18 111 Plaster 20 days Mon 4/22/19Fri 5/17/19 112 Okan Top Coat 5 days Mon 5/20/19Fri 5/24/19 113 Drywall Inspection 1 day Fri 9/7/18 Fri 9/7/18 114 Drywall Inspection 1 day Fri 9/21/18 Fri 9/21/18 115 Drywall Inspection 1 day Mon 10/8/18Mon 10/8/18 116 WOOD FLOOR 247 days Mon 8/6/18 Fri 8/2/19 117 Order Wood Floor 1 day Mon 8/6/18 Mon 8/6/18 118 Acclimate Wood Flooring 35 days Mon 9/17/18Fri 11/2/18 119 Install Wood Flooring 26 days Mon 11/5/18Fri 12/14/18 120 Sand & Finish Wood Flooring 11 days Mon 12/17/18Fri 1/11/19 121 Final Coat 10 days Mon 7/22/19Fri 8/2/19 122 INTERIOR DOORS 78 days Mon 8/6/18 Wed 11/21/18 123 Interior Door Shop Drawings & Approval20 days Mon 8/6/18 Fri 8/31/18 124 Order Interior Doors 1 day Mon 9/3/18 Mon 9/3/18 125 Interior Door Delivery 2 days Mon 10/29/18Tue 10/30/18 126 Interior Door Installation 16 days Wed 10/31/18Wed 11/21/18 127 INTERIOR CARPENTRY 182 days Mon 11/5/18Fri 8/2/19 128 Install Ceiling Paneling 35 days Mon 11/5/18Wed 1/9/19 129 Staircase Installation 35 days Mon 1/7/19 Fri 2/22/19 130 Install Case & Base 34 days Wed 11/28/18Fri 1/25/19 131 Specialty Trim Work 35 days Mon 1/7/19 Fri 2/22/19 132 Punchlist 50 days Mon 5/27/19Fri 8/2/19 133 TILE & SLAB 127 days Mon 8/27/18Fri 3/8/19 134 Shop drawing and review 30 days Mon 8/27/18Fri 10/5/18 135 Order Materials 1 day Mon 10/8/18Mon 10/8/18 136 Delivery of Tile 1 day Fri 11/30/18 Fri 11/30/18 137 Install Shower Pans 8 days Wed 11/28/18Fri 12/7/18 138 Install Tile 56 days Mon 12/10/18Fri 3/8/19 139 Lower Level 16 days Mon 12/10/18Fri 1/11/19 140 Main Level 20 days Mon 1/14/19Fri 2/8/19 141 Upper Level 20 days Mon 2/11/19Fri 3/8/19 142 Install Kitchen Backsplash 5 days Mon 3/4/19 Fri 3/8/19 143 Template & Fabrication for Shower Slab 10 days Mon 12/24/18Wed 1/16/19 144 Delivery of Slab 1 day Fri 1/11/19 Fri 1/11/19 145 Install Lower Slab 15 days Mon 1/14/19Fri 2/1/19 146 Install Main Slab 15 days Mon 2/4/19 Fri 2/22/19 147 Install Upper Slab 15 days Mon 2/25/19Fri 3/15/19 148 CABINETRY 132 days Mon 8/13/18Fri 3/1/19 149 Shop drawings and review 30 days Mon 8/13/18Fri 9/21/18 150 Sample Door / Finish Review & Approval15 days Mon 9/3/18 Fri 9/21/18 151 Order Cabinetry 1 day Mon 9/24/18Mon 9/24/18 152 Cabinetry Fabrication 76 days Tue 9/25/18 Fri 1/25/19 153 Delivery of Cabinets 2 days Mon 1/28/19Tue 1/29/19 154 Installation of Cabinets 23 days Wed 1/30/19 Fri 3/1/19 155 HARDWARE 15 days Mon 5/27/19Fri 6/14/19 156 Install Window & Ext Door Hardware 5 days Mon 5/27/19Fri 5/31/19 157 Install Int. Door Hardware 5 days Mon 6/3/19 Fri 6/7/19 158 Install Bathroom Hardware 5 days Mon 6/10/19Fri 6/14/19 159 INTERIOR DECORATIVE STEEL 49 days Wed 11/28/18Fri 2/15/19 160 Shop Drawings & Review 18 days Wed 11/28/18Fri 12/21/18 161 Int. Steel Fabrication 17 days Mon 1/7/19 Tue 1/29/19 162 Installation of Int. Decorative Steel 13 days Wed 1/30/19 Fri 2/15/19 163 GLASS 64 days Wed 11/28/18Fri 3/8/19 164 Glass Railing Shop Drawings & Review 15 days Mon 1/21/19Fri 2/8/19 165 Glass Railing Template 10 days Mon 2/11/19Fri 2/22/19 166 Installation of Glass Railing 10 days Mon 2/25/19Fri 3/8/19 167 Shower Glass Shop Drawings & Review 15 days Wed 11/28/18Tue 12/18/18 168 Installation of Shower Glass: Lower 14 days Wed 12/19/18Fri 1/18/19 169 Installation of Shower Glass: Main 15 days Mon 1/14/19Fri 2/1/19 170 Installation of Shower Glass: Upper 15 days Mon 1/28/19Fri 2/15/19 171 PAINTING 60 days Mon 2/25/19Fri 5/17/19 172 Finish Wood Ceilings 15 days Mon 2/25/19Fri 3/15/19 173 Interior Painting Stain 30 days Mon 3/11/19Fri 4/19/19 174 Exterior Paint / Stain 20 days Mon 4/22/19Fri 5/17/19 175 EXTERIOR CONCRETE 25 days Mon 4/22/19Fri 5/24/19 176 Driveway & Sidewalk Prep 5 days Mon 4/22/19Fri 4/26/19 177 Install Rigid Insulation 4 days Mon 4/29/19Thu 5/2/19 178 Install Hydronic Tubing & Manifolds 4 days Fri 5/3/19 Wed 5/8/19 179 Form Driveway & Sidewalks 5 days Thu 5/9/19 Wed 5/15/19 180 Pour Driveway & Sidewalks 7 days Thu 5/16/19 Fri 5/24/19 181 MEP TRIM 60 days Mon 5/27/19Fri 8/16/19 182 Fire Suppression System Trim-Out 10 days Mon 5/27/19Fri 6/7/19 183 HVAC Trim-Out 25 days Mon 5/27/19Fri 6/28/19 184 Plumbing Trim-Out 25 days Mon 5/27/19Fri 6/28/19 185 Electrical Trim-Out 25 days Mon 6/3/19 Fri 7/5/19 186 Security Trim-Out 10 days Mon 6/24/19Fri 7/5/19 187 Appliance Install 5 days Mon 6/24/19Fri 6/28/19 188 Water Treatment Install 5 days Mon 6/24/19Fri 6/28/19 189 HVAC Commissioning 3 days Mon 8/12/19Wed 8/14/19 190 HVAC Test & Balance 2 days Thu 8/15/19 Fri 8/16/19 191 AV 50 days Mon 6/17/19Fri 8/23/19 192 Shade Install 10 days Mon 8/12/19Fri 8/23/19 193 Build Av Room – Install Racks 15 days Mon 6/17/19Fri 7/5/19 194 AV Trim-Out 15 days Mon 6/24/19Fri 7/12/19 195 Equipment Testing 3 days Wed 8/21/19 Fri 8/23/19 196 POOL FINISH 30 days Mon 6/24/19Fri 8/2/19 197 Tile Pool & Spa 5 days Mon 6/24/19Fri 6/28/19 198 Plaster Pool & Spa 5 days Mon 7/1/19 Fri 7/5/19 199 Install Pool Mechanical System 10 days Mon 7/8/19 Fri 7/19/19 200 Acid Wash 2 days Mon 7/22/19Tue 7/23/19 201 Commission Pool 3 days Wed 7/24/19 Fri 7/26/19 202 Install Pool & Spa Covers 5 days Mon 7/29/19Fri 8/2/19 203 LANDSCAPING 50 days Mon 5/27/19Fri 8/2/19 204 Hardscape Install 20 days Mon 5/27/19Fri 6/21/19 205 Irrigation Install 10 days Mon 6/17/19Fri 6/28/19 206 Softscape Install 20 days Mon 7/1/19 Fri 7/26/19 207 Install Green Roof 15 days Mon 7/15/19Fri 8/2/19 208 PROJECT CLOSE-OUT 25 days Mon 8/5/19 Fri 9/6/19 209 Final Clean 5 days Mon 8/5/19 Fri 8/9/19 210 Demobilization 5 days Mon 8/12/19Fri 8/16/19 211 Dumpster Removal 1 day Mon 8/19/19Mon 8/19/19 212 Temp Toilet Removal 1 day Mon 8/19/19Mon 8/19/19 213 Final Inspections 5 days Mon 8/19/19Fri 8/23/19 214 Furniture & Decoration 10 days Mon 8/26/19Fri 9/6/19 Permits Survey Jobsite layout (Trailer, Dumpster, Temp Toilet, Silt Fence, Parking, & Laydown) EXCAVATION Grub Site Create Jobsite Access & Parking Install Temporary Electrical Panel Strip & Stockpile Topsoil Excavate Foundation Underground Slab Prep Install Foundation Drain Backfill Foundation Finish Backfill Final Grade UTILITIES Install Water Line Install Sewer Line Install Natural Gas Line Install Phone & Cable Line CONCRETE Form & Pour Footings Form & Pour Walls Form & Pour Lower Slab Form & Pour Garage Slab SITE CONCRETE Form & Pour Site Footings Form & Pour Site Walls UNDERGROUND MEP Underground Radon Rough-in Underground Plumbing Rough-in Install Rigid Foam Insulation Hydronic Rough-in WATERPROOFING Waterproof Foundation Walls Waterproof Site Walls STRUCTURAL STEEL Structural Steel Shop Drawing Review & Approval Main Level Steel Fabrication Deliver & Install Main Level Structural Steel Upper Level Steel Fabrication Deliver & Install Upper Level Structural Steel Roof Level Steel Fabrication Deliver & Install Roof Level Structural Steel FRAMING Set Tower Crane Lower Level Framing Main Level Framing Upper Level Framing Roof Framing Finish Framing ROOFING Dry-In Install Metal Roofing Install Snow Guards and Fences Install Chimney Caps Install Gutters & Downspouts Install Heat Tape Preparation for Green Roof Install Decorative Ballast WINDOWS & DOORS Window & Ext Door Shop Drawings Window & Ext Door Shop Drawings Review Order Window & Exterior Doors Windows & Door Delivery Window & Ext Doors Installation Garage Door Installation EXTERIOR DECORATIVE STEEL Shop Drawings & Review Ext. Steel Fabrication Installation of Ext. Decorative Steel EXTERIOR FINISHES Order Wood Siding & Trim Pre-Finish Wood Siding & Trim Install Soffit & Fascia Install Wood Siding Build Pergola Install Alternative Wood Siding EXTERIOR MASONRY Install Wall Veneer Site Wall Veneer Install Patio Install Upper Patio MEP ROUGH-IN Fire Suppression System Rough-In HVAC Rough-In Pluming Rough-In Water Treatment Install Electric Rough-In AV Rough-In Security Pre-Wire Rough-In Inspection BUILD MECHANICAL ROOMBUILD MECHANICAL ROOM HVAC Plumbing Electric INSULATION Insulate Walls Insulate Roof Insulation Inspection INTERIOR MASONRY Install wall veneer Install stone floors POOL ROUGH-IN Excavate Pool & Spa Rough-In for Pool & Spa Form and Pour Pool & Spa DRYWALL Hang Drywall Tape & Finish Plaster Okan Top Coat Drywall Inspection Drywall Inspection WOOD FLOOR Order Wood Floor Acclimate Wood Flooring Install Wood Flooring Sand & Finish Wood Flooring Final Coat Interior Door Shop Drawings & Approval Order Interior Doors Interior Door Delivery Interior Door Installation INTERIOR CARPENTRY Install Ceiling Paneling Staircase Installation Install Case & Base Specialty Trim Work Punchlist TILE & SLAB Shop drawing and review Order Materials Delivery of Tile Install Shower Pans Install Tile Lower Level Main Level Upper Level Install Kitchen Backsplash Template & Fabrication for Shower Slab Delivery of Slab Install Lower Slab Install Main Slab Install Upper Slab CABINETRY Shop drawings and review Sample Door / Finish Review & Approval Order Cabinetry Cabinetry Fabrication Delivery of Cabinets Installation of Cabinets HARDWARE Install Window & Ext Door HardwareInstall Window & Ext Door Hardware Install Int. Door HardwareInstall Int. Door Hardware Install Bathroom Hardware INTERIOR DECORATIVE STEEL Shop Drawings & Review Int. Steel Fabrication Installation of Int. Decorative Steel GLASS Glass Railing Shop Drawings & Review Glass Railing Template Installation of Glass Railing Shower Glass Shop Drawings & Review Installation of Shower Glass: Lower Installation of Shower Glass: Main Installation of Shower Glass: Upper PAINTING Finish Wood Ceilings Interior Painting Stain Exterior Paint / Stain EXTERIOR CONCRETE Driveway & Sidewalk Prep Install Rigid Insulation Install Hydronic Tubing & Manifolds Form Driveway & Sidewalks Pour Driveway & Sidewalks MEP TRIM Fire Suppression System Trim-Out HVAC Trim-Out Plumbing Trim-Out Electrical Trim-Out Security Trim-Out Appliance Install Water Treatment Install HVAC Commissioning HVAC Test & Balance AV Shade Install Build Av Room – Install Racks AV Trim-Out Equipment Testing Tile Pool & Spa Plaster Pool & Spa Install Pool Mechanical System Acid Wash Commission Pool Install Pool & Spa Covers LANDSCAPING Hardscape Install Irrigation Install Softscape Install Install Green Roof PROJECT CLOSE-OUT Final Clean Demobilization Dumpster Removal Temp Toilet Removal Final Inspections Furniture & Decoration TWT F S SMT WT F S SMTWT F S S MTWT F S S MTWTF S SMT WT FS SMTWT F SS MTWT F SSMTWTF SSMT WTFS SMTWTFSS MTW TFSSMTWT FSSMT WTF SSMTWTFS SMTW TFSSMTW T FSSM TWT F SSM TWTF S SM TWTF S SMTW T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S MTWTF S SMTWT F S S MTWT FS SMTWT FSS MTWTF SSMTWTF S SMTWTFS S MTW TFSS MTWT FSSM TWTF SSMTWTF S SMTW TFS SMTW T FSSMTW T F SSM TWT F S SM TWTF S SM TWT FS SMTWT F S SMTWT F S SMTWT F S SM TWT F S SMTWT F S SMT WT F S SMTWT F S S MTWTF S S MTWTF S SMTWT FS SMTWT F SS MTWTF S SMT WTF S SMTWTFS SMTWT FSS MTWT FSSM TWT F SSMTWTF S SMTW TFS SMTW T FSSMTW T F SSM TWT F S SM TWTF S SM TWT F S SMTW T F S SMTWT F S SMTWT F S S MTWT F S SMTWT F S SMT WT F S SMTWT F S S MTWT F S SMTWTF S SMT WT FS S MTWT FSS MTWT FSSMTWTF SSMT WTFS SMTWTFSS MTW TFSSMTWT FSSM TWTF SSM TWTF S SMTW TF S SMTW T FS SMTW T F SSMTWT F S SM TWT F S SMTW T F S SMTW T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMT WT F S SMTWT F S S MTWTF S S MTWTF S S MTWT FS SMTWT F SS MTWTF S SMT WTF S SMTWTFS SMTWT FSS MTWT FSSM TWT F SSMTWTF S SMTW TFS SMTW T FSSMT Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17 Sep 24, '17 Oct 1, '17 Oct 8, '17 Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17 Nov 26, '17 Dec 3, '17 Dec 10, '17 Dec 17, '17 Dec 24, '17 Dec 31, '17 Jan 7, '18 Jan 14, '18 Jan 21, '18 Jan 28, '18 Feb 4, '18 Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18 Mar 11, '18 Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 May 20, '18 May 27, '18 Jun 3, '18 Jun 10, '18 Jun 17, '18 Jun 24, '18 Jul 1, '18 Jul 8, '18 Jul 15, '18 Jul 22, '18 Jul 29, '18 Aug 5, '18 Aug 12, '18 Aug 19, '18 Aug 26, '18 Sep 2, '18 Sep 9, '18 Sep 16, '18 Sep 23, '18 Sep 30, '18 Oct 7, '18 Oct 14, '18 Oct 21, '18 Oct 28, '18 Nov 4, '18 Nov 11, '18 Nov 18, '18 Nov 25, '18 Dec 2, '18 Dec 9, '18 Dec 16, '18 Dec 23, '18 Dec 30, '18 Jan 6, '19 Jan 13, '19 Jan 20, '19 Jan 27, '19 Feb 3, '19 Feb 10, '19 Feb 17, '19 Feb 24, '19 Mar 3, '19 Mar 10, '19 Mar 17, '19 Mar 24, '19 Mar 31, '19 Apr 7, '19 Apr 14, '19 Apr 21, '19 Apr 28, '19 May 5, '19 May 12, '19 May 19, '19 May 26, '19 Jun 2, '19 Jun 9, '19 Jun 16, '19 Jun 23, '19 Jun 30, '19 Jul 7, '19 Jul 14, '19 Jul 21, '19 Jul 28, '19 Aug 4, '19 Aug 11, '19 Aug 18, '19 Aug 25, '19 Sep 1, '19 Sep 8, '19 Sep 15, '19 Sep 22, '19 Thunderbowl Lot #7Appendix D: Schedule 6/27/2017 City of Aspen Received 07/26/17 Building Department DRAWING ISSUE LO T 7 TH U N D E R B O W L As p e n , CO SHEET No. CONCEPTUAL DESIGN DRAWN BY: PROJECT No:1113 MTE PERMIT SET 418 East Cooper Ave Suite 206 Aspen, CO 81611 970-925-3444 970-920-2186 All ideas, designs, arrangements and plans indicated or represented by this drawing are TEL FAX 2.3 SITE PLAN (PROPOSED) (1" = 10'-0") 2/10/17 owned by and are the property of David Johnston Architects, PC and developed for use and in conjunction with the specified project. None of the ideas, designs, arrangements or plans shall be used by or disclosed for any purpose whatsoever without the written authorization of David Johnston Architects, PC. X:\Pr o j e c t s \As p e n \' 16 Pr o j e c t s \16 0 5 - Lo t 7 Th u n d e r b o w l \DW G \16 0 5 - LO T 7 TH U N D E R B O W L - CU R R E N T PL A N S .pl n | 9:27 AM | Mo n d a y , Ap r i l 24 , 20 1 7 3/06/17 SHEET No. FRO N T SET B A C K DN DW DW ST R E T C H BR E A K F A S T NO O K 12 " ST R E T C H FI R E PL A C E EL E V A T I O N 12 " SP E E D OV E N AB O V E 30 " OV E N CO F F E E UN I T OR ST E A M OV E N AB O V E 30 " OV E N A18 " PA N T R Y UN I T 18 " WI N E UN I T C 30 " RE F DR W S ? PR E P SI N K PL O T T E R / PR I N T E R B D STRETCH BREAKFAST NOOK 12" BU T L E R S PA N T R Y CH I L D R E N S TO Y S / TR A N S I T I O N A L EX P A N D E D PA N T R Y ME D I U M TA L L OP E N ST O R A G E SE R V I N G UN I T AR E A EL E V A T O R PO W D E R RO O M PA N T R Y SU G G E S T E D CL O U D AB O V E IS L A N D W/ PE R I M E T E R LI G H T DE T A I L & DO W N LI G H T I N G G H J KI CL BR E A K F A S T NO O K / DO O R OP E N I N G / SH U T T E R UN I T IN PA N T R Y FI R E P L A C E BUIL D I N G ENVE L O P E LO T 8 LO T 6 EDGE OF PAVE M E N T BU I L D I N G EN V E L O P E 10' ACTI V I T Y EASE M E N T 10' ACTI V I T Y EAS E M E N T P R O P E R Y B O U N D A R Y PROP E R Y BOU N D A R Y 5' A C T I V I T Y E N V E L O P E PROPERY BOUNDARY BUILDING ENVELOPE UTILIT Y EASE M E N T TE L E P H O N E RI S E R CA B L E RI S E R EL E C T R I C TR A N S F O R M E R 82 3 4 82 3 6 82 3 8 82 4 0 82 4 2 82 4 4 82 4 6 82 4 8 82 5 0 82 5 2 82 5 4 82 5 6 82 5 8 82 6 0 82 6 2 THUNDERBO W L LANE 5' ACTIVITY ENVELOPE B U I L D I N G E N V E L O P E LO T 7 0.69 3 AC R E S P R I V A T E S K I E A S E M E N T N FO U N D NO . 5 RE B A R WI T H YE L L O W PL A S T I C CA P MA R K E D L.S. #20 1 3 3 EL E V = 8,23 2 .43 ' FI R E HY D R A N T PO O L FI R E P I T OU T D O O R LO U N G E DN BB Q DN DN DN SP A BE N C H WA T E R FE A T U R E SITE 8,244' = ARCH 100'-0" On Site Tower Crane Dumpster, Recycling, Bear-Proof Container Construction Office Material Laydown Portable Toilets Parallel Parking Parallel Parking Concrete Washout Project Fencing / Silt Barrier Project Fencing / Silt Barrier Additional Laydown/Parking (As Necessary) Appendix E: Site Plan City of Aspen Received 07/26/17 Building Department