Loading...
HomeMy WebLinkAboutFile Documents.813 W Smuggler St.0253.2018 (27).ARBKConstruction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 PARCEL ID NUMBER: 273512428003 PERMITS APPLIED FOR: PERMIT NUMBER 0253.2018.ARBK NEW GROUND UP CONSTRUCTION OF SINGLE FAMILY RESIDENCE PROPERTY OWNER’S NAME: SMUGG, LLC C/O CURT SANDERS SHERMAN AND HOWARD, LLC 730 E DURANT AVE, SUITE 200 ASPEN, CO 81611 PHONE: 970-925-6300 OWNER’S REPRESENTATIVE’S NAME: CURT SANDERS SHERMAN AND HOWARD, LLC 730 E DURANT AVE, SUITE 200 ASPEN, CO 81611 PHONE: 970-925-6300 ARCHITECTS NAME: SINCLAIR BUILDING ARCHITECTURE DEVELOPMENT, LLC ROB SINCLAIR PO BOX 8114 ASPEN, CO 81612 PHONE: 970-948-4269 EMAIL: ROB@SIN-BAD.COM CONTRACTOR’S NAME: SINCLAIR BUILDING ARCHITECTURE DEVELOPMENT, LLC REA COULTER PO BOX 8114 ASPEN, CO 81612 PHONE: 970 379 9894 EMAIL: REA@SIN-BAD.COM 2.0 PROJECT LOCATION 2.1 DISTURBANCE AREA: THE DISTURBANCE AREA IS PROJECTED TO BE APPROXIMATELY 5,600SF AS INDICATED IN THE CITY OF ASPEN ENGINEERING SUFFICIENCY CHECKLIST. 10/1/2018 Page of 1 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 2.2 LOCATION: 813 W S MUGGLER STREET, A SPEN, C O SEE SITE PLAN A2.1 AND CMP DRAWINGS A2.3 FOR ADDITIONAL DETAIL 2.3 DESCRIPTION OF WORK: NEW, GROUND UP CONSTRUCTION OF SINGLE FAMILY RESIDENCE, REQUIRING TEMPORARY MICRO-PILE SHORING TO FACILITATE EXCAVATION AND FOUNDATIONS. WOOD FRAME CONSTRUCTION WITH CLASS A ROOF ASSEMBLY. 10/1/2018 Page of 2 13 813 W SMUGGLER STREET ASPEN, CO 81611 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 3.0 PROJECT DOCUMENTATION: 3.1 PERMITS: THE CONTRACTOR SHALL MAINTAIN ALL APPLICABLE LOCAL, STATE AND FEDERAL LICENSES AND PERMIT THAT APPLY TO THE CONSTRUCTION PROJECT. APPLICABLE PERMITS SHALL BE LISTED, DESCRIBED AND COPIES O THE DOCUMENTS SHALL BE ATTACHED IN THE PLAN APPENDICES. IN ADDITION TO PERMITS, ALL PUD’S, SUBDIVISION IMPROVEMENT AGREEMENTS AND RELATED CITY ORDINANCES MUST ALSO TO ATTACHED IN THE PLAN APPENDICES. SEE APPENDIX 3.1 3.2 PUBLIC NOTIFICATION: CONTRACTOR SHALL SEND NOTIFICATION TO NEIGHBORS ADDRESSING PROJECT PHASING, SCHEDULE, TRAFFIC AND/OR PEDESTRIAN CONCERNS, AND HAULING/ STAGING OPERATIONS. NOTIFICATIONS SHALL ADDRESS ALL ADJACENT NEIGHBORS AND ALL RESIDENTS AFFECTED BY POSSIBLE TRAFFIC DELAYS. THE NEIGHBORHOOD NOTIFICATIONS SHALL TAKE PLACE NO LATER THAN 10 DAYS PRIOR TO CONSTRUCTION AND PERIODICALLY, THROUGHOUT THE DURATION OF THE PROJECT, AS REQUIRED. ALL NEIGHBORS WITHIN 300’ (FEET) ARE INCLUDED HEREWITH AS APPENDIX 3.2. 10/1/2018 Page of 3 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 3.3 PROJECT SIGN: 3.4 CONTACT DESIGNATION: 10/1/2018 Page of 4 13 PROJECT NAME RL3 – 813 W SMUGGLER ST, ASPEN, COLORADO BUILDING PERMIT # TBD GENERAL CONTRACTOR SINCLAIR BUILDING ARCHITECTURE DEVELOPMENT 970 925 4269 OWNER’S REPRESENTATIVE ROB SINCLAIR 970 948 4269 EMERGENCY PHONE 970 379 9894 GC 970 948 4269 ARCHITECT 24 HOUR EMERGENCY PHONE 911 OR 970 379 9894 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 OWNER: SMUGG, LLC C/O CURT SANDERS SHERMAN AND HOWARD, LLC 730 E DURANT AVE, SUITE 200 ASPEN, CO 81611 PHONE: 970-925-6300 OWNER’S REPRESENTATIVE CURT SANDERS SHERMAN AND HOWARD, LLC 730 E DURANT AVE, SUITE 200 ASPEN, CO 81611 PHONE: 970-925-6300 CITY OF ASPEN COMMUNITY DEVELOPMENT PHONE: 970-920-5090 EMAIL: WWW.ASPENPITKIN.COM CONTACT: STEPHEN KANIPE PITKIN COUNTY COMMUNITY DEVELOPMENT PHONE: 970-920-5526 EMAIL: WWW.PITKINCOUNTY.COM CONTACT: BRIAN PAWL ASPEN FIRE PROTECTION DISTRICT ASPEN FIRE PROTECTION DISTRICT PHONE: 970-925-5532 OR 911 EMAIL: WWW.ASPENFIRE.COM CONTACT: EMERGENCY 911 ASPEN POLICE DEPARTMENT ASPEN POLICE DEPARTMENT PHONE: 970-920-5400 OR 911 EMAIL: PHILLIP@RDS-ASPEN.COM CONTACT: EMERGENCY 911 BLAIR FLICKINGER, COMMUNITY RELATIONS ARCHITECT: SINCLAIR BUILDING ARCHITECTURE DEVELOPMENT, LLC. PO BOX 8114 ASPEN, CO 81612 PHONE: 970-925-4269 MOBILE: 970-948-4269 EMAIL: ROB@SIN-BAD.COM CONTACT: ROB SINCLAIR GENERAL CONTRACTOR: SINCLAIR BUILDING ARCHITECTURE DEVELOPMENT, LLC 204 PARK AVE UNIT 2B BASALT, CO 81621 PHONE: 970 925 4269 EMAIL: REA@SIN-BAD.COM CONTACT: REA COULTER SUPERVISOR/SAFETY OFFICER REA COULTER PHONE: 970-379-9894 EMAIL: REA@SIN-BAD.COM CONTACT: REA COULTER RFTA ROARING FORK TRANSIT AUTHORITY PHONE: 970-925-8484 EMAIL: WWW.RFTA.COM CONTACT: RUBEY PARK ASPEN SCHOOL DISTRICT ASPEN SCHOOL DISTRICT PHONE: 970-925-3760 EMAIL: WWW.ASPENK12.NET CONTACT: DR. JOHN MALLOY, SUPERINTENDENT ASPEN VALLEY HOSPITAL ASPEN VALLEY HOSPITAL PHONE: 970-925-1120 EMAIL: WWW.ASPENVALLEYHOSPITAL.ORG CONTACT: GENERAL INFORMATION 10/1/2018 Page of 5 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 4.0 PROJECT IMPLEMENTATION 4.1 DATES OF CONSTRUCTION TENTATIVE CONSTRUCTION START: NOVEMBER 1, 2019 TENTATIVE CONSTRUCTION COMPLETION: MAY 31, 2021 (SEE SCHEDULE BELOW) 4.2 HOURS OF CONSTRUCTION 7:30AM-5:30 PM, MONDAY THROUGH FRIDAY 9:00AM-5:00PM, SATURDAY NO WORK SUNDAY NO WORK 4TH OF JULY DAY AND/OR THE WEEKEND IF IT FALLS ON A FRIDAY OR MONDAY NO WORK MEMORIAL DAY INCLUDING THE WEEKEND NO WORK LABOR DAY INCLUDING THE WEEKEND. NO WORK THANKSGIVING DAY NO WORK CHRISTMAS DAY, INCLUDING CHRISTMAS WEEK 12/26-12/31 NO WORK NEW YEARS DAY NO WORK PRESIDENTS DAY NO WORK DURING FOOD AND WINE. NO WORK DURING THE “HOLIDAY SEASON” SEE APPENDIX 4.2 4.3 SEQUENCING (PHASING) OF CONSTRUCTION: SEE DETAILED SCHEDULE: APPENDIX 4.3A 4.4 ADJOINING PROPERTIES ACCESS FOR THE PROJECT REQUIRES ENCROACHMENT ON ADJACENT PROPERTIES TO THE WEST. AN ACCESS AND IMPACT AGREEMENT WILL BE NEGOTIATED WITH THE ADJACENT PROPERTY OWNER PRIOR TO ANY WORK. 4.5 PROJECT FENCING THE PROJECT SHALL HAVE A SIX FOOT (6’) NON-REMOVABLE CHAIN LINK PERIMETER FENCE WITH WINDSCREEN FOR THE DURATION OF CONSTRUCTION. THIS WILL BE MAINTAINED CONCURRENT WITH PHASING AND ACCESS REQUIREMENTS FOR WORKERS AND PUBLIC. 4.6 PUBLIC HEALTH AND WELFARE THE PROJECT SHALL UPHOLD THE UTMOST RESPECT FOR THE PUBLIC HEALTH AND WELFARE. MOBILIZATION/SITE PREP/FENCING 2 WEEKS SHORING 4 WEEKS EXCAVATION/FOUNDATION 12 WEEKS FRAMING 20 WEEKS DRY-IN 10 WEEKS FINISHES 24 WEEKS CLOSE OUT/PUNCH LIST 6 WEEKS TOTAL 78 WEEKS 10/1/2018 Page of 6 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 4.7 NATURAL ENVIRONMENT THERE ARE NO EXISTING TREES OR LANDSCAPING WITHIN THE SCOPE OF THE PROJECT PERIMETER AND WILL THEREFORE HAVE NO IMPACT. 5.0 SITE AND RIGHT OF WAY MANAGEMENT 5.1 RIGHT OF WAY MANAGEMENT PLAN THE USE OF PUBLIC RIGHT OF WAY WILL BE LIMITED AS INDICATED ON CMP SITE PLAN A2.3 5.2 EMERGENCY VEHICLE ACCESS EMERGENCY VEHICLE ACCESS IS AS NOTED ON CMP DRAWING A2.3 5.3 CONSTRUCTION PARKING DETAILS THE PROJECT IS PROJECTED TO HAVE MINOR IMPACT AND TRANSIENT PARKING REQUIREMENTS…THOUGH DEDICATED SPACES WILL BE REQUIRED TO EXECUTE THE ACTUAL CONSTRUCTION ACTIVITY. CONTRACTOR SHALL FOLLOW CARPOOL, VAN POOL AND SHUTTLE REQUIREMENTS UNDER THE CMP. CONSTRUCTION PARKING IS AS NOTED ON CMP DRAWING A2.3. 5.4 STAGING AREAS STAGING AREAS ARE AS INDICATED ON CMP DRAWING A2.3 5.5 RIGHT OF WAY LIMITATIONS THE PROJECT IS IN COMPLIANCE WITH THE RIGHT OF WAY LIMITATIONS LISTED BELOW: •TEMPORARY CONSTRUCTION OF GUARDRAILS, PEDESTRIAN WALKWAYS, SCAFFOLDS, PROTECTIVE CANOPIES, ETC. •TEMPORARY STORAGE OF MATERIALS, MERCHANDISE, COMMODITIES, CONSTRUCTION MATERIALS, ETC. •PARK OR STAGE AND OPERATE CONSTRUCTION EQUIPMENT, CRANE, BULLDOZER, SKID STEER, ETC. •TEMPORARY PLACEMENT OF A FIELD OFFICE, DUMPSTER, LOOSE MATERIAL CONTAINER, OR CONSTRUCTION FENCING. •THERE IS NO EARTH RETENTION OR REMOVAL REQUIRED. •LOCATION: THE PROJECT IS LOCATED OUTSIDE OF ANY ROW LIMITATION ZONE •SIZE: IT IS THE INTENT TO HAVE THE SMALLEST PRACTICABLE FOOTPRINT AND IMPACT PER PHASE. THIS WILL ALIGN WITH THE LENGTH OF THE FAÇADE AS REQUIRED FOR CONSTRUCTION ACTIVITIES AND ACCESS AS INDICATED IN OUR PHASING PLANS. •SAFETY: COVERED PEDESTRIAN “WALKWAYS” WILL BE INSTALLED PER PHASE. •SCHEDULE: THE PROJECT IS LOCATED OUTSIDE OF THE CORE, BUT WILL COMPLY WITH SITE SPECIFIC REQUIRED SCHEDULE RESTRICTIONS. •AESTHETICS: ANY WALKWAYS WILL BE PAINTED GREY TO MATCH THE COLOR OF THE PROPOSED FINISH MATERIAL UPGRADES. SIGNAGE AND WAYFINDING WILL BE INCLUDED FOR PEDESTRIANS, TENANTS, PATRONS AND RESIDENTS OF THE BUILDING. 5.6 SITE PLAN SEE CMP SITE PLAN A2.2 AND A2.3 5.7 WASTE MANAGEMENT WASTE MANAGEMENT AND RECYCLING WILL FOLLOW CITY OF ASPEN GUIDELINES AND BEST PRACTICES AS REQUIRED FOR THE PITKIN COUNTY LANDFILL 10/1/2018 Page of 7 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 6.0 TRAFFIC CONTROL 6.1 GENERAL ALL TRAFFIC CONTROL OPERATIONS SHALL BE MANAGED BY REA COULTER, PROJECT SUPERINTENDENT. 970 379 9894 6.2 HAUL ROUTES HAUL ROUTES ARE DESIGNATED PER APPENDIX 6.2 6.3 ONSITE VEHICLE LIMITATIONS NO MOTORIZED VEHICLES LONGER THAN 50 FEET AND A WEIGHT MORE THAN 40,000 LBS WILL BE ALLOWED ON THIS PROJECT. 6.4 DELIVERY REQUIREMENTS DELIVERIES WILL BE ACCEPTED BETWEEN THE HOURS OF 7:30AM AND 11:30 AM AND 1:30PM AND 4:30PM, MONDAY THROUGH FRIDAY WITH THE EXCEPTION OF FEDERAL HOLIDAYS AND OTHER DESIGNATED TIMES WHERE CONSTRUCTION IS PROHIBITED. THE SITE IS LARGE ENOUGH TO HANDLE MORE THAN ONE DELIVERY AT A TIME. 6.5 TRAFFIC CONTROL PLAN TRAFFIC CONTROL PLAN BY YOUR WAY TRAFFIC SAFETY COMPANY. SEE APPENDIX 6.5 7.0 PEDESTRIAN PROTECTION 7.1 GENERAL PEDESTRIAN ACCESS PLAN SHALL COMPLY WITH PEDESTRIAN SAFETY PER CITY CODE 21.04.060 MUTCD CHAPTER 6D, THE ADA AND IBC CHAPTER 33. TEMPORARY ADA RAMPS WILL BE PROVIDED AS NECESSARY PER CMP SITE PLAN A2.2. COVERED PEDESTRIAN “WALKWAYS” WILL BE INSTALLED PER PHASE. 7.2 LIMITATIONS SIDEWALK CLOSURE IS REQUIRED FOR THE PHASED REPLACEMENT OF THE SUPERSTRUCTURE AS INDICATED ON OUR PHASING PLAN. SEE CMP SITE PLAN A2.2. 8.0 SEDIMENT AND EROSION CONTROL 8.1 REQUIREMENTS FOLLOW ALL SEDIMENT & EROSION CONTROL MEASURES AS SHOWN ON CIVIL SHEETS C.1.002, “GRADING, DRAINAGE AND EROSION CONTROL PLAN”, AND C.6.001 “MISCELLANEOUS DETAILS”, WITHOUT EXCEPTION. 8.2 SMUGGLER MOUNTAIN RESTRICTIONS N/A PROJECT IS NOT LOCATED ON SMUGGLER MOUNTAIN 9.0 FUGITIVE DUST CONTROL 9.1 FUGITIVE DUST CONTROL PLAN THERE IS NO EXCAVATION REQUIRED OR PLANNED UNDER THIS PERMIT APPLICATION. THEREFORE, THERE WILL BE NO SEDIMENT GENERATED AND NO FUGITIVE DUST CONTROL REQUIRED. 9.2 REQUIREMENTS THERE IS NO EXCAVATION REQUIRED OR PLANNED UNDER THIS PERMIT APPLICATION. THEREFORE, THERE WILL BE NO SEDIMENT GENERATED AND NO FUGITIVE DUST CONTROL REQUIRED. 10/1/2018 Page of 8 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 10.0 EMISSIONS 10.1 GENERAL ALL VEHICLES AND EQUIPMENT USED ON SITE WILL BE PROPERLY MAINTAINED SUCH THAT THE ENGINES WILL FUNCTION WITHIN MANUFACTURE’S STANDARDS OR PARAMETERS 10.2 EMISSIONS FROM DIESEL POWERED ENGINES EMISSIONS FROM DIESEL ENGINES OPERATED WITHIN THE CITY OF ASPEN SHALL BE OF A SHADE OR DENSITY NO DARKER THAN 40% OPACITY, EXCEPT FOR STARTING MOTION NO LONGER THAN 10 SECONDS OR FOR STATIONARY OPERATION NOT EXCEEDING 10 SECONDS. NO IDLING IS ALLOWED 11.0 N OISE SUPPRESSION 11.1 GENERAL. THE NOISE LIMIT FOR CONSTRUCTION IS MEASURED AT THE PROPERTY LINE OF THE CONSTRUCTION SITE. ALL CONSTRUCTION EQUIPMENT SHALL BE ADEQUATELY MUFFLED AND MAINTAINED TO MINIMIZE PROJECT NOISE. 11.2 N OISE SUPPRESSION PLAN EACH SITE MUST INCLUDE INFORMATION ON NOISE BLOCKING METHODS, TECHNIQUES, AND COMMON EQUIPMENT AND ACTIVITIES THAT REQUIRE NOISE SUPPRESSION (REFER TO APPENDIX C) TO MEET THE DECIBEL LIMITS IN THE FOLLOWING SECTION. MAJOR IMPACT PROJECTS THAT INCLUDE REINFORCED EARTH RETENTION ARE REQUIRED TO HAVE A SOUND ENGINEER/CONSULTANT MODEL THE SITE PLANS AND INSERT NOISE SOURCES AND SPECIFY NOISE MITIGATION MEASURES TO SEE HOW NOISE LEVELS WILL BE REDUCED. THE MODELS SHOULD SHOW THE ANTICIPATED NOISE LEVELS AT VARIOUS LOCATIONS SURROUNDING THE PROJECT AND CAN TAKE INTO ACCOUNT A VARIETY OF PROPOSED MITIGATION MEASURES. 11.3 N OISE LIMITS AND SUPPRESSION REQUIREMENTS PROJECTS ARE LIMITED TO 70 DECIBELS (DB) AT THE PROPERTY LINE DURING THE SUMMER ON SEASON. IN ADDITION TO THE DECIBEL LIMIT LISTED ABOVE, PROJECTS LOCATED ON THE MALL WILL BE LIMITED TO 70 DECIBELS (DB) AT THE PROPERTY LINE DURING THE WINTER ON SEASON. ALL OTHER TIMES PROJECTS WILL BE LIMITED TO 80 DECIBELS (80DB) AT THE PROPERTY LINE. ON SEASON SUMMER TIME FRAME: JUNE 1ST THRU LABOR DAY ON SEASON WINTER TIME FRAME: NOVEMBER 15TH THRU MARCH 31ST. ALLOWANCES OF AN ADDITIONAL 10 DB FROM THE LIMITS ABOVE WILL BE MADE FOR SHORT DURATIONS. HOWEVER UNDER NO CIRCUMSTANCE CAN THE DECIBEL LIMIT EXCEED 80 DB AT THE PROPERTY LINE. ALLOWANCE FOR AN EXCESS NOISE EXCEPTION FROM THE ABOVE LIMITS WILL BE REVIEWED BY THE CITY ENGINEER. CRITERIA FOR THE EXEMPTION INCLUDE: WHERE IT IS IN THE INTEREST OF PUBLIC SAFETY; PUBLIC INFRASTRUCTURE WORK WITHIN THE RIGHT OF WAY OTHER ACTIVITIES WITHIN THE RIGHT OF WAY WHERE THERE IS NO OTHER REASONABLE ALTERNATIVE SHORT DURATION RESIDENTIAL ROOFING REPAIR PROJECTS WORK ASSOCIATED WITH ANY ALLOWANCES DESCRIBED ABOVE WILL NOT BE PERMITTED TO START BEFORE 9AM ON WEEKDAYS AND WILL NOT BE PERMITTED ON SATURDAYS. 10/1/2018 Page of 9 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 SITES WILL BE REQUIRED TO OPERATE EQUIPMENT IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATIONS AND WITH ALL STANDARD MANUFACTURERS’ MUFFLERS AND NOISE-REDUCING EQUIPMENT IN USE AND IN PROPERLY OPERATING CONDITION. THE USE OF RADIOS ON THE SITE BEFORE 8:00 AM IS NOT ALLOWED. SITES MAY BE REQUIRED TO MOVE PORTABLE LOUD EQUIPMENT INCLUDING GENERATORS, COMPRESSORS, AND CEMENT MIXERS TO DIFFERENT SIDES OF THE PROPERTY TO REDUCE IMPACTS ON INDIVIDUAL NEIGHBORS. SITES ARE REQUIRED TO POST NOTICES TO INFORM WORKERS, INCLUDING SUB- CONTRACTORS, ABOUT THE BASIC NOISE REQUIREMENTS, AS WELL AS SPECIFIC NOISE RESTRICTIONS, TO THE PROJECT. APPENDIX C INCLUDES RECOMMENDED NOISE SUPPRESSION METHODS. THE PROJECT IS TIMED TO MISS “ON SEASON” LIMITATION OF 70DB. THEREFORE NOISE LIMITS ARE PLANNED NOT TO EXCEED 80DB AS ALLOWED. NOISE OF UP TO 80DB SHALL NOT START UNTIL 9AM AND CEASE AT 5PM. NO LOUD WORK IS ALLOWED ON SATURDAY. 11.4 N OISE LEVEL MEASUREMENTS NOISE LEVEL MEASUREMENTS SHALL BE MADE WITH A SOUND LEVEL METER USING THE “A” WEIGHTING SCALE SET ON “SLOW” RESPONSE. MEASUREMENTS SHALL BE TAKEN AT THE PROPERTY LINE OF THE SITE. THE METERS SHALL BE USED ACCORDING TO MANUFACTURER SPECIFICATIONS. BACKGROUND NOISE LEVELS MAY BE TAKEN FOR COMPARISON WITH A GIVEN SOURCE FOR ACCURACY OF A MEASUREMENT. EXTRANEOUS OR MOMENTARY SPIKES IN THE BACKGROUND NOISE READINGS SHALL NOT BE USED TO COMPARE WITH THE SOURCE NOISE READINGS. ENFORCEMENT ACTIONS WILL BE TAKEN IF THE SOURCE OF THE NOISE IS GREATER THAN THE PERMISSIBLE LEVELS. 11.5 C ONTINUED NOISE MONITORING MAJOR CONSTRUCTION SITES THAT REQUIRE REINFORCED EARTH STABILIZATION WILL BE REQUIRED TO PERFORM CONTINUED NOISE MONITORING. WHILE THIS PROJECT IS NOT A “MAJOR CONSTRUCTION SITE”, IT WILL INCORPORATE MICRO-PILES AND THUS REQUIRES AN ACOUSTIC BARRIER AS SHOWN ON SHEET A2.3 CMP SITE PLAN. 11.6 S PECIFIC RESTRICTIONS RELATED TO MANUFACTURING ON SITE THERE WILL BE NO ON SITE MANUFACTURING OF MATERIALS. 12.0 ENFORCEMENT 12.1 CITY CONSTRUCTION MITIGATION OFFICER A CITY CONSTRUCTION MITIGATION OFFICER SHALL BE ASSIGNED TO EACH CONSTRUCTION PROJECT. THE CITY CONSTRUCTION MITIGATION OFFICER WILL COMPLETE RANDOM SITE VISITS TO DETERMINE IF THE PROJECT IS FOLLOWING APPROVED PLAN AND CITY REQUIREMENTS. THE OFFICER IS NOT INTENDED TO TAKE THE PLACE OF A CITY OF ASPEN BUILDING INSPECTOR. 12.2 CORRECTIVE ACTION THE CITY OF ASPEN WILL ENFORCE CONSTRUCTION MITIGATION CORRECTIONS AS FOLLOWS: 10/1/2018 Page of 10 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 1. THE FIRST CORRECTIVE ACTION IS A VERBAL WARNING AND EXPLANATION OF THE VIOLATION WITH A TIMEFRAME FOR COMPLETION. 2. THE SECOND CORRECTIVE ACTION IS A WRITTEN WARNING OR CORRECTION NOTICE WITH TIMEFRAME FOR COMPLIANCE. 3. THIRD AND FINAL NOTICE IS A “STOP WORK ORDER” (RED TAG). IF A STOP WORK ORDER IS ISSUED, NO MORE WORK CAN BE COMPLETED UNTIL THE VIOLATION IS CORRECTED. 4. THE CITY MAY FORGO STEPS ONE AND TWO AS OUTLINED ABOVE AND GO DIRECTLY TO THE “STOP WORK ORDER” AND OR A SUMMONS AND COMPLIANT MAY BE ISSUED FOR VIOLATIONS UNDER THE FOLLOWING CIRCUMSTANCES: WORK WITHOUT A PERMIT WORK THAT IS ENDANGERING PUBLIC SAFETY WORK THAT IS ENDANGERING PUBLIC HEALTH INCLUDING WORK THAT MAY AFFECT WATER QUALITY. WORK ON HOLIDAYS OR SUNDAYS (UNLESS THE SITE RECEIVED AN EXEMPTION TO WORK DURING THESE TIMES) THE OWNER AND GENERAL CONTRACTOR ARE RESPONSIBLE FOR ASSURING COMPLIANCE AND BOTH WILL BE CHARGED BY SUMMONS AND COMPLAINT IN MUNICIPAL COURT WHEN NECESSARY. THIS APPLIES EVEN IF A SUB-CONTRACTOR VIOLATES THE CONSTRUCTION MITIGATION RULES, 20 FAILURE TO CORRECT VIOLATIONS AND/OR ANY THREAT TO PUBLIC SAFETY COULD SUBJECT THE OWNER, CONTRACTOR OR BOTH TO A MAXIMUM PENALTY OF UP TO A YEAR IN JAIL AND/OR A FINE OF UP TO $2,650 FOR EACH VIOLATION. EACH DAY A VIOLATION CONTINUES IS A SEPARATE OFFENSE DETERMINED BY THE MUNICIPAL COURT 12.3 INSPECTION REPORTS THE CONSTRUCTION MITIGATION OFFICER WILL COMPLETE CONSTRUCTION INSPECTION REPORTS. ALL REPORTS ARE PUBLIC AND WILL BE KEPT IN THE CITY ENGINEERING DEPARTMENT. 13.0 CONSTRUCTION MITIGATION COMMITTEE PROJECTS SEEKING EXEMPTIONS MAY SEEK AN EXEMPTION FROM PROJECT DURATIONS, NUMBER OF ENCROACHMENTS. THESE EXEMPTIONS WILL BE REVIEWED BY THE CONSTRUCTION MITIGATION COMMITTEE. THE COMMITTEE CONSISTS OF REPRESENTATIVES FROM THE ENGINEERING, PARKING AND BUILDING DEPARTMENTS. IF AN EXEMPTION IS GRANTED THEN THE PROJECT WILL BE SUBJECT TO THE EXEMPTION FEES AS OUTLINED IN TITLE 2. CONSIDERATIONS FOR EXEMPTIONS INCLUDE IMPACT OF EXEMPTION ON ADJACENT PROPERTIES, DURATION OF EXEMPTION AND SEASON THAT EXEMPTION IS BEING REQUESTED. 14.0 APPEAL PROCESS PROJECTS MAY APPEAL THE DECISION OF THE CONSTRUCTION MITIGATION COMMITTEE AND / OR THE CITY ENGINEER. ALL APPEAL WILL BE FORWARDED TO THE CITY MANAGER OR THEIR DESIGNEE. IF THE APPEAL IS APPROVED AND RESULTS IN AN EXEMPTION, THEN THE PROJECT WILL BE SUBJECT TO THE EXEMPTION FEES AS OUTLINED IN TITLE 2. 10/1/2018 Page of 11 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 10/1/2018 Page of 12 13 Construction Management Plan for: RL3 813 W Smuggler Street, Aspen, CO 81611 NOTE: REFER TO CMP SITE PLAN SHEET A2.3 FOR FURTHER DETAILS & PLACEMENT OF CONSTRUCTION PHASE STAGING AND OTHER RELATED FACILITIES. 10/1/2018 Page of 13 13