A.RESIDENTIAL RENEWABLE ENERGY MITIGATION PROGRAM
Sheets showing snowmelt, pool, spa, and solar/GSHP information:
Do you have snowmelt or a spa that has been exempted by the buiding official?
Hydro Snowmelt Electric Snowmelt Pool Spa
Existing
To be Removed
Existing to Remain 0.00 sqft 0.00 sqft 0.00 sqft 0.00 sqft
New 1381.00 sqft 51.00 sqft
New (exempt)40.00 sqft
Total on site 1381.00 sqft 0.00 sqft 0.00 sqft 91.00 sqft
Total Snowmelt on site
Boiler Efficiency 95.0%100%75.0%95.0%
Mitigation Fee -$ 9,448.42$
Total Fee for Mitigation:58,873.68$
B.ON-SITE RENEWABLE CREDITS
Supplemental System REMP Credit
Use PV Worksheet Photovoltaic System 47,242.19$
Use Thermal Worksheet Hot Water Panels -$
Use GSHP Cert Ground Source Heat Pump 13,188.00$
Other Approved System -$
Total Mitigation Credits:60,430.19$
Onsite Renewable Offsets:How many KiloWatts of PV (solar electric) would I need? 8.58
or How many square feet of SHW (solar hot water) would I need?262.07
R-REMP Fee:-$
Amount Previously Paid on This Permit:-$
TOTAL R-REMP FEE :-$
Refund (includes minus $750):-$
C. PREPARED BY:Date:7/15/2020
Print Name:
Signature:
Phone & EMail:
REVIEWED:Date:
2015 IECC RESIDENTIAL RENEWABLE ENERGY MITIGATION PROGRAM
City of Aspen Version 11.1 Updated March 28 2017
209 E Bleeker Street
2737 073 20 002 0320-2017-ARBK
seth@zgrouparchitects.com
West End House LLC
312 AABC Ste. D
tiffany@aspenstarwood.com
A1.3
$49,425.26
Melanie Noonan - Z Group Architects
(970) 404-1088 melanie@zgrouparchitects.com
Z Group Architects (Seth Hmielowski)
1381.00 sqft
411 E Main Street, #205
(970) 925-1832
Yes (enter sqft below on the exempt row)No
07/24/2020Bonnie Muhigirwa 8/28/20
**This is the new
total on site **
Parcel ID #:
Collector
Aspect, Degress
from True South
Collector Tilt,
Degrees From
Horizontal
Solar
Orientation
Adjustment
Factor
DC side capacity
(kW)
Inverter capacity
(kW)
kW for
credit
kW Mitigation
Credit
Collector Group 1 60 45 89.60%8.88 7.68 7.68 6.88 kW
Collector Group 2 87.00%0 0.00 kWCollector Group 3 87.00%0 0.00 kWCollector Group 4 87.00%0 0.00 kWCollector Group 5 87.00%0 0.00 kW
Collector Group 6 87.00%0 0.00 kW
Collector Group 7 87.00%0 0.00 kW
Collector Group 8 87.00%0 0.00 kW
Collector Group 9 87.00%0 0.00 kWCollector Group 10 87.00%0 0.00 kWCollector Group 11 87.00%0 0.00 kW
Collector Group 12 87.00%0 0.00 kW
Collector Group 13 87.00%0 0.00 kW
Collector Group 14 87.00%0 0.00 kW
Collector Group 15 87.00%0 0.00 kWCollector Group 16 87.00%0 0.00 kWCollector Group 17 87.00%0 0.00 kWCollector Group 18 87.00%0 0.00 kW
Collector Group 19 87.00%0 0.00 kW
Collector Group 20 87.00%0 0.00 kW
Total:6.88 kW
$ Mitigation Credit:47,242.19$
Instructions:
1)
2)
3)DC side capacity is the total labled panel output kW in a group.
4)Inverter capacity is the recommended input power in kW of your inverter(s).
5)
6)
7)
8)
PREPARED BY:Date:
Print Name:
Signature:
Phone & EMail:
REVIEWED:Date:
PV WORKSHEET
City of Aspen Version 11.1 Updated March 28 2017
Permit Number: 0320-2017-ARBK2737 073 20 002
Enter the aspect and tilt for each group. The solar orientation adjustment factor is automatically calculated.
PROJECT ADDRESS:
The mitigation credit will be automatically entered into your RREMP or CREMP form. If your project has both RREMP and
CREMP, it will automatically divide the credits up, with priority given to mitigating the CREMP fee.
Determine how many collector groups you have. Groups are used to differentiate between collectors
(panels) with different tilts, aspects, sizing, or inverters. If all your collectors are installed similarily, you
might have just one group.
209 E Bleeker Street
Tyler Sweeney
tyler@sunsensesolar.com
The kW mitigation credit is totalled and multiplied by $6865.32/kW to get the $ Mitigation Credit
You will be given credit for the lesser of the labeled panel output or the inverter.
The kW for credit is multiplied by the solar orientation adjustment factor to get kW mitigation credit.
07/24/2020
Bonnie Muhigirwa 8/28/20
Project Address:
Parcel ID #:
I.Please list the following information
BTUs per hour of installed GSHP:
$ Mitigation Credit:
Designer Certification:
Installer Accreditation:
Division of Water Resources Permit:
II.GSHP System Design Specifications
Number of Loops:
Depth of Loops:ft.
Total Loop Length:ft.
Total System Capacity @ 32 oF EWT:tons
ARI 330 or ISO 13256-1System Performance:COP
III.Attach the following information with application.
A. GSHP unit performance sheets certified by ARI 330 or ISO 13256-1.
B. Designer Certification Sheets
C. Installer Certification Sheets
D. Division of Water Resource Permit
IV.PREPARED BY:Date:
Print Name:
Signature:
Phone & EMail:
REVIEWED:Date:
Coefficient of Performance of the system must be at least 3 as per American Research
Institute Standard performance method (ARI 330) or ISO 13256-1 for closed loop earth-
coupled heat pump systems (for hydronic systems use an output temperature of 115
degrees F) or equivalent procedure.
4/11/2018
Provided by contractor
3.1
6
7.85
350
4200
303-424-1622 tproffer@gomajornow.com
NOTE: A GSHP is an energy-efficient option that significantly reduces energy use and
minimizes REMP payments. The REMP payment associated with a GSHP is used to offset
the coal powered electricity over 20 years. This option is calculated on REMP summary
sheet.
Terry Proffer
Permit Number: 2737 073 20 002
12131-994
94200 btu/hr
AEE CGD Number:16
GROUND SOURCE HEAT PUMP SOURCE CERTIFICATION
City of Aspen Version 11.1 Updated March 28 2017
Agency
209 E. Bleeker Street
IGSHPA Number:
please provide all the required information as part of your application.
0320-2017-ARBK
All Ground Source Heat Pump systems must be certified prior to installation;
13,188.00$
07/24/2020