HomeMy WebLinkAboutFile Documents.536 Walnut St.0118.2019 (25).ARBKThe City of Aspen
These plans must be kept at the
building site or inspection
delays may occur. Construction
shall conform to these plans. All
changes shall be approved by
the building official.
Field Plan Set Must Be Printed In Color
SEPARATE PERMITS ARE
REQUIRED FOR ELECTRICAL,
PLUMBING, MECHANICAL, OR
FIRE SPRINKLER WORK
04/17/2019
06/28/2019
ALL OUTDOOR LIGHTING
MUST COMPLY WITH
THE CITY OF ASPEN LIGHTING CODE
SECTION 26.575.150
REFERENCES FROM 2015 IRC
CV/A = crawl space ventilation required, sec. R408.1 Access required, R408.4
EE = emergency escape required sec R310.1
EU = enclosed usable space under stairs shall be ½” Gyp, sec R302.7
G/D = garage/dwelling separation, sec R302.5 and R302.6
STC = Sound transmission class not less than 45 at dwelling separations, app
K
RV = roof and rafter ventilation required, R806.1
A = attic access 22” x 30”, 30” headroom above, R807.1
SA = smoke alarms installed to NFPA 72 requirements, sec R314
CO = carbon monoxide detector per City Ordinance 41 series 2008
SG = safety glazing required, sec R308.4
GR = guardrails, 36” min ht, 4” max opening; req at 30” drop any point w/in 36”
horizontally, sec R312
WFP = window fall protection- operable window <24” AFF & >72” above
grade: use opening control device listed to ASTM F2090, sec R312.2
HR = handrails 34”-38” ht, sec R311.7.8
SI = stairway illumination, sec R303.7
PD = protect against decay, sec R317
REFERENCES FROM 2015 IMC
V = bathroom and balanced whole house mechanical ventilation req.
Ordinance 40, 2016
DE = clothes dryer exhaust, sec 504. Makeup air req’d if over 200 CFM
AS = access and service space for maintenance req’d, sec 306
MA = make up air required if hood exhausts greater than 400 CFM, sec 505.2
ET = exhausts terminate 3’ from prop line and openings, 10’ from intakes,
501.3.1
IT= intake openings 10’ from lot line & contaminant sources (vents, streets),
401.4
D = fasten and seal all ductwork per 603.9
REFERENCES FROM 2015 IFGC
DV = direct vent req’d, sec 303.3
CA = combustion air not taken from bedrooms, bathrooms or
storage sec 303.3
OD = outdoor appliances must be listed for outdoor use, sec 303.6
REFERENCES FROM 2015 IECC
F = new or replacement glazing shall not exceed 0.28 U-Value, NFRC label
required, Ordinance 40, 2016
L = 75% of lamps in permanently installed lights must be high efficacy, sec
R404.1
SE = Continuous air barrier required; all exterior joints, cracks, and holes to be
caulked, gasketed, sealed, table R402.4.1.1
REFERENCES FROM 2014 NEC
EP = electric panel 'happy space' 30"x36"x78", not in storage, sec 110.26
SMOKE ALARMS AND
CARBON MONOXIDE
DETECTORS REQUIRED
THROUGHOUT DWELLING
UNIT PER CITY OF ASPEN
MUNICIPAL CODE 8.15
SPECIAL INSPECTION REQUIRED:
-Structural steel welding: Field & Shop
-High strength bolting
-Epoxy anchors
-Intumescent paint
-Spray applied fire resistive materials
-Permanent micropiles
Special inspection is required per 2015 IBC
section 1704. Inspector to verify that copy of
agreement for inspection program to be on
the job site prior to performing any
inspections. A copy of all Special Inspector
field reports to be on the job site for
inspectors' review if requested. Failure to
comply may result in denial of inspection.
Structural steel -- S6.001
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT CONTACT SHEET
CITY OF ASPEN 130 S. GALENA ST | ASPEN, CO 81611
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
OWNER
___________________________________ _____________________ ________________________Name Phone E-mail
FOR PLAN REVIEW QUESTIONS
___________________________________ _____________________ ________________________Name Phone E-mail
FOR INSPECTION QUESTIONS
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
OWNER’S AUTHORIZED AGENT
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
APPLICATION BEST CONTACT
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
ARCHITECT OR DESIGNER OF RECORD
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
CIVIL ENGINEER OF RECORD
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
STRUCTUAL ENGINEER OF RECORD
I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions of laws and
ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does not
presume to give authority to violate or cancel the provisions of any other state or local law regulating construction or the performance
of construction. It is my responsibility to review the approved plans and any comments that are contained thereon and see that the
structure and/or project is built in compliance with all applicable codes.
________________________________________________________ _____________________ContractorSignature Date
INSPECTIONS: The General Contractor must schedule inspections online. Please visit www.aspenpitkin.com/Departments/Community-Development-Forms/ to do so.
___________________________________ _____________________ _____________________
________________________________________ __________________ _________ ____________
_______________________________________________________________________________________
Name Phone Cell Phone
CityMailing Address
E-mailAddress
State ZIP
GENERAL CONTRACTOR
Check if you are a tested owner builder (single-family homes only). You must take a test and complete the owner/building affidavit.
(CITY USE ONLY) Owner builder approved by:________________________Date:______________________ Affidavit on file
ADDRESS: ____________________________PERMIT NUMBER: _______________________________
August 2017
536 Walnut Street
970.429-8711Delvon Nemechek delvon@rowlandbroughton.com
970.948.1890Ben Allen / I.A.Sedgwick inc.beniasedgwick@yahoo.com
310.998.7248Les & Lynn Bider 310.963.4019
1017 N Roxbury Dr Beverly Hills CA 90210
lesbider@gmail.com
970.544.9006Delvon Nemechek 970.429.8711
500 W. Main St.Aspen CO 81611
alison.agley@rowlandbroughton.com
970.544.9006Delvon Nemechek 970.429.8711
500 W. Main St.Aspen CO 81611
delvon@rowlandbroughton.com
970.544.9006Sarah Broughton / Delvon Nemechek 970.429.8711
500 W. Main St.Aspen CO 81611
delvon@rowlandbroughton.com
206.910.7766Evolve Engineering 206.910.7766
1040 Main Street Carbondale CO 81623
steve@evolvestruct.com
(970) 948-1890I.A.Sedgwick Inc.(970) 948-1890
PO Box 10251 Aspen CO 81612
beniasedgwick@yahoo.com
01/06/2019
04/17/2019
Code Editions
Fire Sprinkler System
Type Of Construction Fire Alarms Installed
Required Special Inspections
Energy Code Compliance
Exterior Energy Use Total Approved On-Site Snowmelt________ Spa_______ Pool _________
Building Type/Occupancy Group
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING DESCRIPTION FORM - IRC & IBC
CITY OF ASPEN 130 S. GALENA ST | ASPEN, CO 81611
BUILDING CODE INFORMATION
2015 IRC
Existing?NFPA 13 NFPA 13 R
High-Strength Bolting Epoxy Anchors Structual Steel Welding
Permanent Micropiles Other _____________
Prescriptive Table
UNIT DESCRIPTION AS PROPOSED
# Stories Above Grade ______ # Stories Below Grade _______
Parking Spaces ______ Parking Spaces ______ Parking Spaces ______
# Bedrooms ______ # Full Baths ______ Deck Area ______
# 3/4 Baths ______ # 1/2 Baths ______
# Kitchens ______ # Wood Fireplaces ______
# Gas Appliances ______ # Gas Logs______
NFPA 13 D
RESCheck UA Alternative
Yes No
One Family Two Family
Townhouse
Reviewed By: _____________________Date:__________
BUILDING ROOMS AND USES BY LEVEL AS PROPOSED (Include Mechanical & Storage)
Basement ___________________________________________________________________________________
___________________________________________________________________________________________
Main Level __________________________________________________________________________________
____________________________________________________________________________________________
2nd Floor ___________________________________________________________________________________
__________________________________________________________________________________________
3rd Floor ___________________________________________________________________________________
___________________________________________________________________________________________
Additional ___________________________________________________________________________________
___________________________________________________________________________________________
Attached Garage Detached Garage Carport
Is there an ADU? # Living Rooms_____# Kitchens _____# Full Baths _____# 3/4 Baths _____# 1/2 Baths _____# Bedrooms _____
# Other Rooms (List)____________
ADU BUILDING DESCRIPTION
YesNo
PERMIT NUMBER: _______________________________
(As Adopted and Amended)
Other (Please Explain)
_________________
_________________
VA VB IV IIIA IIIB IIA IIB IA IB
Sprayed Fire-Resistants
COMCheck UA Alternative
(Existing + New)
A__B
B (A <50)
F__H__I __
E R__S__
UM IRC
IBC
2015 IBC
(As Adopted and Amended)
YesNo Required?YesNo Type
January 2018
2015 IEBC
(As Adopted and Amended)
Other _____________
Gross Area of Building: __________ Gross Area of Unit: __________
Occupant Load: ___________
64
3957
2 1
3
4 2 294
2 1
1 0
3 0
laundry, mechanical, storage, 3 bedrooms, 3 full baths, family room with fireplace
garage, office, entry, mudroom, master bedroom and bath
kitchen, dining, powder room, living room, 2 decks
04/17/2019
existing
External Energy Use ApprovedRREMPCREMPPERMIT #DATESNOWMELT _____________________________POOL _____________________________SPA _____________________________OFFSET:________________________________REMP SHEET: ___________________________REVIEWED BY: _________________________4tonyf8/7/20190118.2019.arbk0 sqft0 sqft0 sqftNASNOWMELT SYSTEM AND EQUIPMENT MANDATORY REQ’S.All snowmelt systems shall meet the following:-Any portions in the Right of Way must be on a separate zone. A ROWpermit and Permanent Encroachment License are required.-R10 insulation shall be installed under the area to be snow melted or R5insulation shall be installed under and at the slab edges. (Ordinance 11Series 2011)-Automatic controls installed for system shut off when pavementtemperature is above 50°F and no precipitation is falling. (2009 IECCSec. 403.8 & 503.2.4.5)-Automatic or manual controls installed for system shut off when outdoortemperature is above 40°F. (2009 IECC Sec. 403.8 & 503.2.4.5)-Inspection by testing hydrostatically at 1½ times max system designpressure, but not less than 100psi, for 15minutes. (2009 IMC Sec.1208.1)NA
External Energy Use Approved
RREMP CREMP
PERMIT #:_______________DATE:________
SNOWMELT:_____________________________
POOL: _____________________________
SPA: _____________________________
OFFSET:________________________________
REMP SHEET: __________________________
REVIEWED BY: _________________________
SNOWMELT SYSTEM AND EQUIPMENT MANDATORY REQ’S.
All snowmelt systems shall meet the following:
-Any portions in the Right of Way must be on a separate zone. A ROW
permit and Permanent Encroachment License are required.
-R10 insulation shall be installed under the area to be snow melted or R5
insulation shall be installed under and at the slab edges. (Ordinance 11
Series 2011)
-Automatic controls installed for system shut off when pavement
temperature is above 50°F and no precipitation is falling. (2009 IECC
Sec. 403.8 & 503.2.4.5)
-Automatic or manual controls installed for system shut off when outdoor
temperature is above 40°F. (2009 IECC Sec. 403.8 & 503.2.4.5)
-Inspection by testing hydrostatically at 1½ times max system design
pressure, but not less than 100psi, for 15minutes. (2009 IMC Sec.
1208.1)
MINIMUM BOILER AFUE: _________________
X
0118.2019.arbk 8/8/2019
0
0
64 existing
NA
NA
NA
TF
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT APPLICATION
CITY OF ASPEN 130 S. GALENA ST | ASPEN, CO 81611
PROPERTY INFORMATION
___________________________________ _________ ___________________________
______________ ______________ ________________________________________
_________________________ _______________ __________________________________
________________________ _______________ __________________________________
CommericalMulti-FamilySingle Family
Use of Building Class of WorkNewAdditionAlterationRepair
________YesNo
Will there be any roof/wall penetrations?
NOTICE: This permit becomes null and void if work or construction authorized is not commenced within 180 days, or if construction or work is suspended or abandoned for a period of 180 days at any time after work is commenced.
_______________
_______________
_______________ _______________ _______________
_______________
_______________ _______________
_______________
PROJECTVALUATION
SQ FT OF BUILDING WORK AREA
UNIT SQ FT
SQ FT OF SOILDISTURBANCE
BUILDING FOOTPRINT
LOT SIZE(SQ FT)
PROJECT DETAILS (READ DEFINITIONS BELOW)
Mixed-Use IFFRTenant FinishDemolitionChange Order
________
ADDRESS UNIT #PARCEL ID #
BLOCK TRACT OR SUBDIVISIONLOT
DESCRIPTION OF WORK IN DETAIL
BuildingReview BuildingPermit Fee Parks Impact
EngineeringReview Zoning Review (50%)School Lands Dedication
Zoning
Review (50%)
CMP (50%)TDM Impact
Energy CodeReview REMPPayment Pedestrian Amenity
CMP (50%)GIS Housing Cash in Lieu
Parks Review City UseTax Water Tap
Utility Review County Use
Tax Sanitation
SUBMITTAL FEES ISSUANCE FEES
APPROVALS
ISSUANCE FEES
BEST CONTACTNAME CELL EMAIL
OWNER NAME CELL EMAIL
____Toilets, Bidets ____Bathtub____Lavatory (Wash Basin)____Shower____Kitchen Sink (+Disposal)____Dishwasher____Laundry Bar, Utility Sink____Clothes Washer ____Floor Sink____Floor Drain____Water Heater (Pan Req)____# Gas Outlets____Water Treatment____Other_________
Fixture Counts Important Review Triggers
PC
Zoning
HPC
Building
Fire
Engineering
CMP
Water
Stormwater
Sanitation
Env. Health
Parks
LandscapeEfficiencyApproved
To Issue
Issuance
Date ApprovedReviewingDepartmentReviewerSign-Off
NEW SQ FT
Project Valuation: Cost of project as defined in Valuation Affadavit.Sq Ft of Building Work Area: Total square footage of interior area undergoing change or reconfiguration.Unit Sq Ft: Gross square footage, not FAR, of permitted unit.Lot Size: Total surveyed square footage of property.Sq Ft of Soil Disturbance: Exterior area of the lot where the ground is disturbedNew Sq Ft: Total added square footage for additions to net livable or net leasable space.Building Footprint: Grade floor square footage of the permitted structure.Hardscape Area: Square footage of impervious lot surface.Zone District: Underlying zone district of permitted parcel.
January 2019
DATE:___________ MASTER PERMIT:______________________ PERMIT NUMBER:__________________________
__________________________________________________________________________________
__________________________________________________________________________________
HARDSCAPEAREA
NeedsReview
DE
F
I
N
I
T
I
O
N
S
ZONEDISTRICT
Major Engineering Review• Projects involving less than 50% hardscape area and work affecting 75% or greater of unit sq ft• Projects involving greater than 50% hardscape area and work affecting 50% or greater of unit sq ft• Projects involving 1,000+ sq ft of soil disturbance area
Water Efficient Landscaping• Projects that trigger a major engineering review • Projects involving interior alterations affecting 50% or more of exisiting gross square footage
THIS SECTION MUST BE COMPLETED IN ITS ENTIRETY
4/10/19 0118.2019.ARBK
536 Walnut St.A 273707396001
9 Fox Crossing
Les & Lynn Bider (310) 998-7248 lesbider@yahoo.com
Delvon Nemechek (970) 429-8711 delvon@rowlandbroughton.com
Interior remodel to an existing Fox Crossing home, including removal of an elevator and powder
room and the addition of a small office.
1,528,860.22
5
2
6
4
1
1
2
3649
3649
4132 1
50
50
1019
9
1
4
n/a
R6
x PL 5.6.19
x BN 6.28.19
x TF 8.22.19
x TF 8/22/19
19,147.64 29,457.90 0 x JD 6/19/19
x CK 8.21.19
1,703.21 2,827.98 0 x SW 8.7.19
2,827.98 1,952.22 0 x CS 6.20.19
4,418.69 0 x
1,952.22 500.00 0
123.96 15,003.03
X630.00 3,822.15
04/17/2019
Dr 8/21/19
0118.2019.ARBK
RHODES FAM SURV TRUST
536 Walnut St
273707396001
FIRE
SPRINKLERS
REQUIRED
DAM 8/28/19
The City of Aspen
These plans must be kept at the
building site or inspection
delays may occur. Construction
shall conform to these plans. All
changes shall be approved by
the building official.
Field Plan Set Must Be Printed In Color
SEPARATE PERMITS ARE
REQUIRED FOR ELECTRICAL,
PLUMBING, MECHANICAL, OR
FIRE SPRINKLER WORK
SPECIAL INSPECTION AND TESTING AGREEMENT
To permit applicants of project requiring special inspection and\or testing per Section 1704 of the
International Building Code (IBC).
Project Address: __________________________________ Permit Number:______________________
BEFORE A PERMIT CAN BE ISSUED: The owner, or the engineer or architect of record, acting as the
owner’s agent, shall complete two copies of this agreement and the attached Special-inspection and Testing Schedule, including the required acknowledgments. A pre-construction conference with the parties
involved may be required to review the special-inspection requirements and procedures.
APPROVAL OF SPECIAL INSPECTORS: Special inspectors may have no financial interest in the
projects for which they provide special inspections. Special inspectors shall be approved by the building department prior to performing any duties. Special inspectors shall submit their qualifications and are
subject to personal interviews for pre-qualification. Special inspectors shall display approved identification, as stipulated by the building official, when performing the function of special inspector.
Special inspection and testing shall meet the minimum requirements of the International Building Code
Section 1704. The following conditions are also applicable:
A. Duties and Responsibilities of the Special Inspector
1. Signify presence at job site. Special inspectors should notify contractor personnel of
their presence and responsibilities at the job site. If required by the building official, they shall sign in on the appropriate form posted with the building permit.
Observe assigned work. The special inspector shall observe assigned work for
conformance with the building department approved (stamped) design drawings, specifications, and applicable workmanship provisions of the International Building
Code. Architect\engineer-reviewed shop drawings may be used only as an aid to inspection.
For continuous special-inspection, the special inspector shall be on site at all times
observing the work requiring special inspection. Periodic inspections, if any, must have prior approval based on a separate written plan reviewed and approved by the building
department and the engineer or architect of record.
3. Report nonconforming items. The special inspector shall bring nonconforming items to
the immediate attention of the contractor and note all such items in the daily report. If any item is not resolved in a timely manner or is about to be incorporated in the work, the
special inspector shall immediately notify the building department by telephone or in person, notify the engineer or architect, and post a discrepancy notice.
Provide timely reports. The special inspector shall complete written inspection reports
for each inspection visit and provide the reports on a timely basis determined by the building official. The special inspector or inspection agency shall furnish these reports
directly to the building official, engineer or architect of record, and others as designated. [IBC Sec. 1704.1.2] These reports should be organized on a daily format and may be
submitted weekly at the option of the building official. These reports should include: a. Description of daily inspections and tests made with applicable locations,
b. Listing of nonconforming items, c. Report on how nonconforming items were resolved or unresolved as
applicable, d. Itemized changes authorized by the architect, engineer, and building official if
not included in nonconforming items.
2.
4.
1
5. Provide Final Inspection Report. The special inspector shall submit a written final report documenting required special inspections and correction of any discrepancies
noted in the inspections prior to the final building inspection.
B. Owner Responsibilities. The project owner, the engineer or architect or record, or an agent of the owner is responsible for employing special-inspection services. The special inspector\agency shall
not be in the employ of the contractor, subcontractor or material supplier. [IBC Sec 1704.1] In case of an owner\contractor, the special inspector\agency shall be employed as specified by the
building official.
C. Engineer or Architect of Record Responsibilities
1. Prepare special inspection program. The engineer or architect of record shall list the
items for which special inspection is required; and shall indicate any items for which the IBC or the building official approves periodic inspection and the frequency of such
inspections.
Respond to field discrepancies. The engineer or architect of record shall respond to uncorrected field discrepancies in design, material, or workmanship observed by the special inspector.
Review shop drawings and submit design changes. The engineer or architect of record shall acknowledge and review for conformance with the construction drawings those
shop drawings that may detail structural information, shall submit to the building official and to the special-inspection agency written documentation of any verbally authorized
deviations from the approved construction documents, and shall submit revised documents for building official approval as required.
2.
3.
D. Contractor Responsibilities
1. Notify the special inspector. The contractor is responsible for notifying the special
inspector or agency regarding individual inspections for items listed on the attached schedule and as noted on the building department approved plans. Adequate notice shall
be provided so the special inspector has time to become familiar with the project.
Provide access to approved plans. The contractor is responsible for providing the
special inspector access to approved plans.
Retain special inspection records. Upon request, the contractor is also responsible for retaining, at the job site, all special inspection records completed by the special inspector.
2.
3.
E. Inspection of Fabricators
1. Fabrication of structural assemblies and members. Where fabrication of structural load-bearing members and assemblies is being performed on the premises of a
fabricator’s shop, IBC Section 1704.2 shall require special inspection of the fabricated items.
Fabrication and implementation procedures. The special inspector shall verify that the fabricator maintains detailed fabrication and quality control procedures that provide a
basis for inspection control of the workmanship and the fabricator’s ability to conform to approved construction documents and reference standards. The special inspector shall
review the procedures for completeness and adequacy relative to code requirements for fabricator’s scope of work.
2.
F. Approved Fabricator Responsibilities
1. Fabrication exempt inspections. Special inspections are not required where work is
done on the premise of a fabricator registered and approved to perform such work without special inspection.
2
Tony Fusaro 8/28/2019
TF
536 Walnut St 0118.2019.arbk
0118.soip.arbk