June 28, 2019
City of Aspen
Community Development
130 S Galena St
Aspen, CO 81611
Attn: John Barker, Lead Permit Coordinator
Bonnie Muhigirwa, Plans Examiner
RE: Gorsuch Lockers
555 E. Durant, Unit C-2
Building Permit Number: 0025.2019.ACBK
Dear Mr. Barker,
Please find below responses to Building Comments sent in an email from Bonnie Muhigerwa,
dated May 17, 2019. The comments reference revised architectural drawings and other
affected documents. A link to these documents will be provided in the email carrying this letter.
The following summarizes our responses to your comments:
Architectural Drawings Comments:
1. A0, Cover Sheet – Please see the additional information and calculations provided by
our mechanical design/build contractor, R&H Mechanical.
2. A0, Cover Sheet – The occupancy has been revised on the Code Plan, 2-A0, and the
Zoning and Code Data.
3. The snack area will include complimentary items for the locker room clients and there
will be no service counter or point of sale.
4. The door schedule and sheet notes on sheet A2 have been revised to indicate that door
#1 will remain unchanged and will not be replaced. As an existing door to remain, this
door is not required to comply with the 2015 IECC, C402.4.
5. Door 2 on 2-A2 has been revised to indicate the existing door will be replaced with a
new 3’-0”x7’-0” door and frame.
6. Although it is not clear, it appears that comment is referencing the height of the sink rim
above the counter top. Please see the response to the next comment below.
7. Details 5, 6 and 7, on sheet A4 have been revised to correct the height of the sink rim to
be 34”, maximum, above finished floor.
07/02/2019
Pierce + Frye Architects Vail and San Francisco 970.949.0899
www.PierceFrye.com
Lighting COMcheck Comments:
1. The form field provided in the COMcheck application has a limited character capacity.
The requested information cannot be added to the certificate. Please refer to the light
fixture cut sheet for wattage listing per linear foot of fixture on page 6 of 34, of the
lighting specs. No revisions to the COMcheck compliance certificate were made.
2. The spec page originally submitted did not print properly. Please see page 18 of 34 of
the revised lighting specs. The fixture model number and specs noted on the lighting
schedule on sheet A3 and in the COMcheck compliance certificate are correct and no
revisions were made..
3. There is a conflict between the wattage listed on page 12 and 15 of the Lighting Specs.
The higher wattage was used in the COMcheck compliance certificate. No revisions
were made.
4. Using the 150w transformer wattage for the two 7w fixtures causes the COMcheck
compliance certificate to fail. These two fixtures have been removed from the lighting
plan on 1-A3, the lighting schedule and specs, and the COMcheck compliance
certificate.
Structural Drawings Comments:
1. See 2-A2, sheet note #8 and 3-A5 for additional fire resistance details.
2. The required signatures on the Special Inspections have been added to the form. See
attached documents.
Please contact us with any questions.
Sincerely,
Tom Frye
Pierce + Frye Architects
(415)392-4433 x2
tfrye@piercefrye.com
Attachments via Drop Box folder:
Gorsuch - Aspen - Locker Rm 190628 ARCH SET.pdf
Gorsuch - Aspen - Locker Rm 190628 LIGHTING SPECS.pdf
Gorsuch - Aspen - Locker Rm 190628 COMcheck LIGHTING COMP REP.pdf
Special Inspections Forms