Page: [3] C3.0 SITE LAYOUT PLAN
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
Deliveries in this area will have
to be staged very carefully so as
not to block alley or Jail Trail.
Jail Trail is the only access to
the parking garage as stairs are
closed for a separate process.
Check with Engineering Dept
before scheduling any large
deliveries in this area.
PCCH CMP FINALVersion 1.0 4-12-19.pdf (9)
Page: [3] C3.0 SITE LAYOUT PLAN
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
Any work in this area that will
block the sidewalk, even for a
delivery, will require a
Temporary Encroachment
Permit
Page: [3] C3.0 SITE LAYOUT PLAN
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
No construction parking will be
allowed in this alley.
Page: [3] C3.0 SITE LAYOUT PLAN
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
Please show location of
necessary items for a site plan.
These include: job trailer, porta
potty, waste management and
recycling containers, and on site
material staging areas.
Page: 2
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
Please provide copy of
Certificate of Completion of City
of Aspen Construction
Management Plan Online
Training Course. Course can be
found at CMPAspen.com
Deliveries in this area will have to be
staged very carefully so as not to
block alley or Jail Trail. Jail Trail is
the only access to the parking
garage as stairs are closed for a
separate process. Check with
Engineering Dept before scheduling
any large deliveries in this area.
24"
Any work in this area
that will block the
sidewalk, even for a
delivery, will require
a Temporary
Encroachment Permit
No construction parking will be
allowed in this alley.
PI
T
K
I
N
C
O
U
N
T
Y
No.
Please show location of necessary items for a site plan. These include: job trailer, porta potty, waste management
and recycling containers, and on site material staging areas.
12-18..............................................................................................................TRAFFIC CO
19-22 .....................................SEDIMENT & EROSION CONTROL, FUGITIVE DUST CO
23.................................................................................................................................EMI
24 ..............................................................................................................NOISE SUPPR
Please provide copy of Certificate of Completion of City of Aspen
Construction Management Plan Online Training Course. Course
can be found at CMPAspen.com
Acknowledged
Acknowledged
Acknowledged
Dumpster, port a potties and material storage
areas added to site map. Our office will be in the
jail building so there will be no job trailer.
Recycling will be handled with FCI dump trailer. It
will be stored off site and utilized when needed.
Completed,
verification attached
APPROVED
Page: 6
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
This project is in the CRA. You
will be responsible for following
all applicable work restrictions.
See CMP Requirements Manual
section 4.2
Page: 11
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
No construction parking will be
allowed in Galena Plaza alley.
Page: 12
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
This statue is not applicable for
construction deliveries.
Construction deliveries are only
allowed during allowable
construction hours
Page: 22
Author: patrickh
File Name: PCCH CMP FINALVersion 1.0 4-12-19.pdf
Are you planning on using
acoustical barriers at this site? If
so, please provide more
information (type, size, exact
location, and how they are
supported).
day from 7:30AM to 5:30PM and Saturdays as
rmed on Sundays)
0db will take place between the hours of 9AM
d)
ekend
ls on a Friday or Monday
Resort Area and outside the Commercial Core:
mas Week, Holiday Season (days leading up to
ood and Wine Festival are not applicable.
This project is in the CRA. You will be
responsible for following all applicable
work restrictions. See CMP
Requirements Manual section 4.2
SITE MANAGEMENT
Parking Management
Construction workers will be encouraged to carpool to the pro
Emergency Vehicle Access & Ordinance 35
Continuous emergency vehicle access will be maintained to th
Staging Areas
Specify construction staging areas
See attached Project Site Logistics Plan for locations
No construction parking will be allowed in Galena
Plaza alley.
This statue is not applicable for
construction deliveries.
Construction deliveries are only
allowed during allowable
construction hours
NOISE SUPPRESSION
erating noises greater than 70db will be performed Monday thru Friday from
ly.
Plan
ers at the project site are planned and will include a combination of temporary
he west side of the project site—reference site logistics plan and attached
noise barriers.
contractors to follow the appropriate “Noise Blocking Methods” for any
noise greater than 70 decibels. When appropriate, equipment will be fitted
the following:
ial Grade combustion engine exhaust silencers
ic hand power tools will be fitted with a silencer on the air exhaust port
hrouds/intake & exhaust mufflers
adening material (line hoppers, storage bins or chutes)
Are you planning on using acoustical barriers at this
site? If so, please provide more information (type,
size, exact location, and how they are supported).
Acknowledged
Acknowledged
We were not planning on installing barriers around the site due to
the small amount of work that is outside and a majority of that work
is between the jail and the courthouse. We will utilize sound
barriers for specific operations such as concrete demo and
sawcutting.
Acknowledged