Revise mechanical drawings to
cloud all changes.
9001_MPE-all_09-25-20_stamped-signed.pdf (8)
Subject: PlanCheck
Page: 1
Page Index: 1
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
The backgrounds in the
basement do not match the
approved architecturals.
Subject: PlanCheck
Page: 2
Page Index: 2
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
Revise the mechanical drawings
to show the routing of the boiler
flues correctly on each floor. The
various stories appear to show
conflicting routing locations.
Subject: PlanCheck
Page: 2
Page Index: 2
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
Outside air intake opening must
be 10' from property lines. 2015
IMC 401.4.
Subject: PlanCheck
Page: 2
Page Index: 2
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
Outside air intake opening must
be 10' from property lines. 2015
IMC 401.4.
Revise mechanical
drawings to cloud all
changes.
The backgrounds inthe basement do notmatch the approvedarchitecturals.
Revise the mechanical
drawings to show the
routing of the boiler
flues correctly on each
floor. The various
stories appear to show
conflicting routing
locations.
Outside air intake
opening must be 10'
from property lines.
2015 IMC 401.4.
Outside air intake
opening must be 10'
from property lines.
2015 IMC 401.4.
Subject: PlanCheck
Page: 2
Page Index: 2
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
Revise the architectural
drawings to clearly detail a shaft
enclosure for the boiler flues.
Include sheet A6.14 and revise it
to show the actual proposed
design. Show it connecting 4
stories, which requires a 2 hour
fire rating. Show the horizontal
portion and provide a listed
horizontal shaft assembly.
Revise the vertical shaft
assemblies to separate the shaft
from the rest of the building
construction on all four sides.
2015 IBC 713.
Subject: PlanCheck
Page: 3
Page Index: 3
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
Outside air intake opening must
be 10' from property lines. 2015
IMC 401.4.
Subject: PlanCheck
Page: 4
Page Index: 4
Author: nickt
Color:
File Name: 9001_MPE-all_09-25-20_stamped-signed.pdf
Outside air intake opening must
be 10' from property lines. 2015
IMC 401.4.
Revise the architectural drawings to clearly detail a
shaft enclosure for the boiler flues. Include sheet
A6.14 and revise it to show the actual proposed
design. Show it connecting 4 stories, which requires
a 2 hour fire rating. Show the horizontal portion and
provide a listed horizontal shaft assembly. Revise the
vertical shaft assemblies to separate the shaft from
the rest of the building construction on all four sides.
2015 IBC 713.
Outside air intakeopening must be 10'from property lines.2015 IMC 401.4.
Outside air intakeopening must be 10'from property lines.2015 IMC 401.4.