HomeMy WebLinkAboutFile Documents.203 E Hallam St.0174.2018 (23).ARBKREV. 12/29/18
Division 1 GENERAL REQUIREMENTS $88,100.00 7.73%
01-140 Engineers By Others 0.00
01-150 Final Cleanup Allowance for Construction Cleaning 5,000.00
01-190 General Laborers
Added for demo, slab prep, and misc.
excavation at North patio and walkway.3,500.00
01-200 Insurance
Allowance for Prorated GL and
Umbrella - Revised due to increased
scope of work.5,000.00
01-230 Permits & Fees
To be paid seperately based on revised
calculation.0.00
01-240 Photographic/Reprographic Documentation Allowance 500.00
01-280 Project Manager No Charge 0.00
01-340 Temporary Toilet Allowance 600.00
01-370 Superintendent
Labor allowance adjusted to reflect
increased scope at North Patio and
access to Roof Deck.73,500.00
Division 2 SITEWORK $150,835.00 13.24%
02-140 Selective Demolition
Labor allowance to remove sheetrock
and framing as necessary, etc.16,250.00
02-170 Excavation
Allowance for footings for new fences,
removal of concrete on East side, prep
for new wood deck, etc. based on MW
estimate dated 6/26/18. 1.1 + $10K
buffer for removal and slab prep at
North Patio.61,260.00
02-210 Landscaping
Creative Nature estimate dated
7/1/2018 based on T&M agreement.35,325.00
02-220 Moving & Storage By Others 0.00
02-290 Site Protection Labor and Material Allowance 25,000.00
02-320 Survey
Allowance to locate fence and revised
Improvement Survey 2,000.00
02-340 Trash Removal Allowance 1,000.00
02-350 Underground Utility 10,000.00
Division 3 CONCRETE $56,917.00 5.00%
Schedule of Values for:
Styslinger Residence Remodel:
Page 1 of 5
1/7/2019
03-120 Concrete Cutting
Allowance increased due to additional
concrete cutting required at new
snowmelted area on North Patio and
walkway.5,000.00
03-130 Concrete Forms 0.00
03-150 Flatwork - Exterior
Labor and Material Allowance based
on K&W Concrete estimate dated
6/5/18. 1.1 + $25K additional
allowance for new snowmelted area at
North Patio and water feature (details
TBD).51,917.00
03-160 Foundation Spa Pad Reflected in 03-150 0.00
Division 4 MASONRY $0.00 0.00%
Division 5 METALS $202,665.00 17.79%
05-140 Metals
Labor and Material allowance for steel
structure at ships ladder per
preliminary design provided by JMD.15,000.00
05-150 Ornamental Ironwork
Myers & Co. quote #02146 and #02149
for Large planter and 2 small back
planters. Includes automotive paint.66,195.00
05-160 Railings - Exterior - Fences
Myers & Co. quote #02147 and #02148
for 42" and 72" fences. Includes
automotive paint + $20K allowance for
new glass sections and gates.103,470.00
05-165 Railings - Exterior - Deck Rails
Labor and Material allowance for
railing at Roof Deck (details TBD).18,000.00
Division 6 WOOD & PLASTICS $219,191.00 19.24%
06-110 Disposable Tools Material Allowance 3,000.00
06-140 Fasteners & Adhesives Material Allowance 4,000.00
06-150 Finish Carpentry
Labor allowance for 42" and 72"
horizontal fence pickets, wood on
planters, etc. Adjusted to reflect
custom wood treads at ships ladder,
screening for HVAC equip., etc.65,000.00
06-160 Finish Lumber
Allowance based on SWP quote dated
4/27/18 + $20K for Roof Deck
material, benches at planters, RSWO
stair treads, and misc. trim.61,191.00
06-210 Labor Rough Carpentry
Labor allowance for roof
modifications, roof deck, new West
deck, trash enclosure and misc. rough
carpentry tasks.48,750.00
06-240 Rough Lumber Material allowance 12,500.00
06-260 Siding
Material allowance for phenolic panels
and cedar siding at parapet walls,
removal and replacement as necessary.8,500.00
Page 2 of 5
1/7/2019
06-270 Siding Labor
Labor allowance for new installation at
parapet wall, removal and replacement
as necessary. 16,250.00
Division 7 THERMAL/MOIST. PROTECTION $24,000.00 2.11%
07-100 Batt Insulation
Labor and Material allowance for
Foam and Batt as needed, and under
slab at snowmelted areas.5,500.00
07-130 Flashing & Sheet Metal Material Allowance for misc. flashings.1,000.00
07-180 Roofing
Labor and Material Allowance for
removal and replacement of membrane
roofing.12,500.00
07-190 Waterproofing
Labor and material allowance for misc.
waterproofing details.5,000.00
Division 8 DOORS & WINDOWS $20,000.00 1.76%
08-120 Entrance Doors Jeld Wen door at Mudroom deleted.0.00
08-190 Skylights
Material Allowance for automatic unit
at access to Roof Deck. (Specification
TBD).20,000.00
Division 9 FINISHES $150,479.00 13.21%
09-110 Drywall
Labor and material allowance for patch
and repair as required. Increased to
reflect additional work at access to roof
Deck & Closet, shade pocket, etc.30,000.00
09-120 Exterior Painting
Labor and material allowance for wood
portions of fences, trash enclosures,
and misc.25,000.00
09-130 Interior Painting
Labor and material allowance.
Increased to reflect additional work at
"ships ladder" structure and treads,
shade pocket, etc.30,000.00
09-180 Slabwork
Labor and material allowance for Wet
Bar countertops.6,500.00
09-220 Stucco
Labor and material allowance for
repairs if necessary.5,000.00
09-230 Tile
Revised based on additional exterior
tile to be removed per latest plans and
Aspen Tile estimates dated 11/9/2018.
1.1 53,979.00
Division 10 SPECIALTIES $18,800.00 1.65%
10-100 Fireplace & Stoves Allowance for Paloform Firepit 12,000.00
10-130 Specialties Cross Creek estimate date 7/11/2018.6,800.00
Division 11 EQUIPMENT $7,937.00 0.70%
Page 3 of 5
1/7/2019
11-100 Appliances
Mountain High Appliance quote dated
12/4/2018 7,937.00
11-120 Audio-Visual Need Scope of Work.0.00
Division 12 FURNISHINGS $50,634.00 4.44%
12-110 Cabinetry
Heartwood quote dated 6/29/2018
1.1 + $22K allowance for additional
cabinetry, door, and fixed panels at
access to Roof Deck. (Final design and
details TBD)40,634.00
12-170 Shelving
Labor and Material allowance for (2)
66" steel and glass, illuminated floating
shelves.10,000.00
Division 13 SPECIAL CONSTRUCTION $48,000.00 4.21%
13-100 Fire Suppression
Labor and allowance to relocate heads
as necessary.3,500.00
13-120 Spa/Hot Tub
Allowance based on Diamond Spas
quote dated 2/1/18. 1.25 44,500.00
Division 14 CONVEYING SYSTEMS $0.00 0.00%
Division 15 MECHANICAL $62,000.00 5.44%
15-130 HVAC
Labor and material allowance to
relocate equipment and minor
modifications.12,000.00
15-150 Plumbing
Revised Labor and Material allowance
for plumbing modifications needed for
Wet Bar, gas piping to Firepit, hot tub,
new snowmelted areas, etc.50,000.00
15-160 Snowmelt Reflected in 15-150 0.00
Division 16 ELECTRICAL $39,651.00 3.48%
16-100 Electrical-120/240 Volt
Revised Labor and Material Allowance
based on CEI estimate dated 5/31/18
1.1 Adjusted for power to automatic
roof hatch, Roof Deck lighting,
motorized shade at West elevation, and
misc. modifications.39,651.00
$1,139,209.00
Contractor's Fee @ 12%$136,705.08
$1,275,914.08
P.M. / Owner @ $125.00 Per Hour $0.00
Total:$1,275,914.08
Subtotal:
Subtotal:
Page 4 of 5
1/7/2019
Page 5 of 5
1/7/2019