Loading...
HomeMy WebLinkAboutFile Documents.427 Rio Grande Pl.0016.2019 (23).ACBKStructural Plan Review First Resubmittal April 24, 2019 June 25, 2019 (Response Review) Review/Report is based on structural Construction Documents prepared by KL&A, Inc., dated 06/14/2019 (Permit Set) and architectural drawings prepared by Charles Cunniffe Architects, dated 02/07/2018 and received via electronic transfer on 03/13/2018. Structural drawings are stamped and signed by the engineer of record. Project Name: Aspen City Offices Project Location: 425 Rio Grande Place, Aspen, CO 81611 Review based on International Building Code (IBC) Edition: 2015 Building Construction Type: New City Offices. Structure consists of a four-level steel framed structure with a slab on grade lower level. Foundation system is concrete foundation walls and footings. Lateral system consists of steel braced frames and moment resisting frames. Building Department Jurisdiction: Aspen Building Department Risk Category: II (IBC 2015 Table 1604.5) Basic Wind Speed: 115 mph (ultimate) Exposure: B Seismic Site Class: C Importance Factor: Ie = 1.0 Snow Load: 70 psf uniform Ground Snow Load: 100 psf Importance Factor: Is = 1.0 Frost Depth: 36” P a g e | 2 Structural Review Comments: 1. Sheet S0.1 General Notes: Revise the risk category to III, based on the code reviewer comments. This will affect lateral loads/structural calculations. Building Department approved category II. Comment addressed. 2. Sheet S2.6 Lower Level Partial Foundation Plan – Area A: Provide Calculations verifying foundation uplift has been considered at braced frame on grid A and at two locations on grid 11. Calculations provided. Comment addressed. 3. Sheet S2.6 Lower Level Partial Foundation Plan – Area A: Provide Calculations verifying bearing pressure interaction is acceptable structurally at the two footings near grids B-1. Revised drawings show one footing removed. Comment addressed. 4. Sheet S2.7 Lower Level Partial Foundation Plan – Area B: Provide Calculations verifying foundation uplift has been considered at braced frame on grid C and along grid 3 between grids B and C. Calculations provided. Comment addressed. 5. Sheet S2.8 Lower Level Partial Foundation Plan – Area C: Micropiles are not referenced in soils report - Please provide letter from CTL/Thompson indicating micropiles are appropriate for the foundation elements east of grid PJ. Drawings revised. Micropiles removed. Comment addressed. 6. Sheet S2.9 Main Level Partial Framing Plan – Area A: Provide base connection details at the two braced frames along grid 11 and another along grid A, along with calculations. Comment not addressed. 7. Sheet S2.9 Main Level Partial Framing Plan – Area A: Provide base connection details at moment frame along grid 12, along with calculations. Comment not addressed. 8. Sheet S2.9 Main Level Partial Framing Plan – Area A: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 9. Sheet S2.10 Main Level Partial Framing Plan – Area B: Provide diagonal brace and column connection details at braced frame along grid C and frame along grid 3 between grids B and C, along with calculations. Comment not addressed. P a g e | 3 10. Sheet S2.10 Main Level Partial Framing Plan – Area B: Verify cores through precast do not adversely affect existing precast structure in any way. Provide calculations or verification that cores do not affect main precast members (typ). Comment not addressed. 11. Sheet S2.10 Main Level Partial Framing Plan – Area B: Provide calculations indicating existing precast walls and foundation at stair core are adequate with added gravity and lateral loads. Comment not addressed. 12. Sheet S2.10 Main Level Partial Framing Plan – Area B: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 13. Sheet S2.11 Main Level Partial Framing Plan – Area C: At main beam, shear stud layout needs to be revised to indicate stud count between purlins (typ). Drawings revised, composite studs changed. Comment addressed. 14. Sheet S2.11 Main Level Partial Framing Plan – Area C: Provide diagonal brace and column connection details at braced frame along grid J, along with calculations Comment not addressed. 15. Sheet S2.11 Main Level Partial Framing Plan – Area C: Provide braced frame/column connections to existing along grid P8, along with calculations. Comment not addressed. 16. Sheet S2.11 Main Level Partial Framing Plan – Area C: Verify cores through precast do not adversely affect existing precast structure in any way. Provide calculations or verification that cores do not affect main precast members (typ). Comment not addressed. 17. Sheet S2.12 Middle Level Partial Framing Plan – Area A: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 18. Sheet S2.12 Middle Level Partial Framing Plan – Area A: Provide diagonal brace and column connection details at braced frame along grid A and at two locations along grid 11, along with calculations. Comment not addressed. 19. Sheet S2.12 Middle Level Partial Framing Plan – Area A: Provide connection details at moment frame along grid 12, along with calculations. Comment not addressed. P a g e | 4 20. Sheet S2.13 Middle Level Partial Framing Plan – Area B: Provide braced frame connection details along grid C and along grid 3 between grids B and C, along with calculations. Comment not addressed. 21. Sheet S2.13 Middle Level Partial Framing Plan – Area B: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 22. Sheet S2.13 Middle Level Partial Framing Plan – Area B: Verify cores through precast do not adversely affect existing precast structure in any way. Provide calculations or verification that cores do not affect main precast members (typ). Comment not addressed. 23. Sheet S2.14 Middle Level Partial Framing Plan – Area C: Verify cores through precast do not adversely affect existing precast structure in any way. Provide calculations or verification that cores do not affect main precast members (typ). Comment not addressed. 24. Sheet S2.14 Middle Level Partial Framing Plan – Area C: Provide braced frame connection details along grids P8 and J, along with calculations. Comment not addressed. 25. Sheet S2.14 Middle Level Partial Framing Plan – Area C: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 26. Sheet S2.15 Upper Level Partial Framing Plan – Area A: Provide braced frame connection details along grid A, along with calculations. Comment not addressed. 27. Sheet S2.15 Upper Level Partial Framing Plan – Area A: Provide moment frame connection details along grids 11 and 12, along with calculations. Comment not addressed. 28. Sheet S2.15 Upper Level Partial Framing Plan – Area A: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 29. Sheet S2.16 Upper Level Partial Framing Plan – Area B: Provide braced frame connection details at 7 locations on plan, along with calculations. Comment not addressed. P a g e | 5 30. Sheet S2.16 Upper Level Partial Framing Plan – Area B: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 31. Sheet S2.17 Upper Level Partial Framing Plan – Area C: Provide braced frame connection details along grids P8 and J, along with calculations. Comment not addressed. 32. Sheet S2.17 Upper Level Partial Framing Plan – Area C: At main beams and purlins with point loads, shear stud layout needs to be revised to indicate stud count between purlins or point loads (typ). Drawings revised, composite studs changed. Comment addressed. 33. Sheet S2.19 Roof Partial Framing Plan – Area B and C: Provide braced frame connection details at 7 locations on plan, along with calculations. Comment not addressed. 34. Sheet S3.2 Brace Elevations: Finish detailing and provide calculations. Comment not addressed. 35. Sheet S3.2 Brace/Moment Frame Elevations: Finish detailing and provide calculations. Comment not addressed. 36. Sheet S4.1 Details: Cross ties are recommended at detail 7/S4.1. Detail revised, comment addressed. 37. Sheet S4.2 Details: In detail 2/S4.2, additional bolts are required each end if steel channels are required for shear. Please provide calculations. Comment not addressed. 38. Sheet S4.3 Details: In detaisl 1 and 4/S4.3, plate and bolt information is missing. Please provide calculations. Comment not addressed. Plan Review by: Andy Baturevich, P.E. HCDA Engineering, Inc. (719) 633-7784 abaturevich@hcdaengineering.com P a g e | 6 Final Report Review and Local Contact: Thomas R. Thompson, CBO and ICC Certified Plans Examiner Sunrise Engineering 6875 South 900 East Salt Lake City, UT 84047 Cell (303) 328-1546 Office (435) 743-6151 E-mail tthompson@sunrise-eng.com