HomeMy WebLinkAboutFile Documents.834 W Hallam St.0025-2021-BCHO (5)
To:
City of Aspen Building Department
Attn: John Barker
Re:
834 W Hallam – Permit # 0010.2018.ARBK
Construction Management Plan
John,
This letter is to serve as acknowledgment that Centaur Construction will abide by the
previously approved Construction Management Plan originally submitted by Madigan +
Company for 834 West Hallam, Aspen, CO 81611.
A COVID 19 plan was submitted via salesforce on 6.25.20 and additional updated
information is attached herein including the tree removal permit #0135-2019-TREE.
Regards
Brad Hribar
Centaur Construction
June 26, 2020
Construction Management Plan
834 W HALLAM
Construction Management Plan
3.1 Permits
The Contractor will apply for and comply with all applicable local, state, and federal licenses
and permits applicable to the project. The licenses and permits may include:
City of Aspen Contractor License
City of Aspen Building Permit
City of Aspen Access Infrastructure/Excavation Permit
City of Aspen Encroachment License
City of Aspen Engineering Department Right of Way Permit
City of Aspen Tree Removal/Drip Line Excavation Permit
City of Aspen Application for Construction Parking Spaces
City of Aspen Temporary Heating Plan
Construction Site Safety Rules Regarding Temporary Heat
Pitkin County Fugitive Dust Control Plan
CITY OF ASPEN
Tree Removal / Dripline Excavation
Permit # 0135-2019-TREE
DATE ISSUED: 2019-11-14
OWNER: 834 WEST HALLAM ASSOC LLC
SITE STREET ADDRESS: 834 W HALLAM ST
ASPEN, CO
81611
DESCRIPTION OF WORK:
On August 21st, 2019, David Coon, Aspen City Forester, performed an onsite inspection of the (9) trees to be removed
for construction at 834 W Hallam per the attached Tree Protection and Removal Plan L -200 dated 10/04/19. All
Cottonwood Trees in the right-of -way along Hwy 82 ( W Hallam ) and 8th Street will have a 15 foot diameter zone around
the tree where no excavation of any kind is to occur. This entire area is to be mulched with 6 inches of wood mulch, and
areas open to traffic ( outside of the tree protection zones ) will have a layer of plywood over the mulch to prevent
compaction.
The trees approved for removal have been assigned a value using a standard formula developed for all trees found within
the City of Aspen. The formula is as follows: Value=$42.00 x 3.14 x (D/2)2, where D is the diameter of the tree at breast
height. Per the attached Tree Protection and Removal Plan L -200 dated 10/04/19, the total mitigation value assessed
for the trees to be removed is $32,166.36. This amount will be o ffset by the planting of (3) 2.5” Columnar Swedish
Aspens, (2) 3” Aspens, and (3) 8 ft Spruce trees on the property at a cost of $6,430.27. The total mitigation owed is thus
$25,736.09 which must be paid cash in lieu prior to the release of this permit. Trees may not be removed until a building
permit has been issued.
This permit is valid for one year after approval date but must be posted for
2 days PRIOR to removal(s ).
City of Aspen Parks Department
970-920-5120
City Forester :
Manager:
Construction Management Plan
3.4 Project Contacts
Following is a list of the current Project Team contacts. Other project personnel will be
added as they are made part of the Project Team.
Owner
West Hallam Holdings, LLC
2001 N. Halsted St, Suite 304
Chicago, IL 60614
Tel: 312-850-1680
Fax: 312-850-1685
mhunt@mdevco.com
Contractor
Centaur Construction
121 S. Galena, Suite 200
Aspen, CO 81611
Tel: 312-644-4470
Fax: 312-644-4472
Brad Hribar
Project Manager
Cell: 312-714-8519
bhribar@centaurco.com
Michael Buglione
Site Manager- 24hr Emergency
Cell: 970-227-5425
mbuglione@centaurco.com
Architect
Forum Phi Architecture
Ryan Walterscheid
715 W. Main Street, Suite 204
Aspen, CO 81611
Tel: 970-274-9598
rwalterscheid@forumphi.com
Structural Engineer
KL&A, INC
Dan Doherty
215 North 12th ST, Unit E
Carbondale, CO 81623
Tel: 970-927-5174
ddoherty@klaa.com
Earth Rentention Engineer
B&Y Drilling, INC
Shaun Brainard
PO Box 1878
Rifle, CO 81650
Tel: 970-635-2608
shaun@bydrillinginc.com
Civil Engineer
High Country Engineering, INC
Deric Walter
1517 Blake Ave, Suite 101
Glenwood Springs, CO 81601
Tel: 970-945-7988
deric@bu-inc.com
MEP Engineer
Peak Design Group, LLC
Mitchell Hyra
1338 Grand Ave, Unit 315
Glenwood Springs, CO 81601
Tel: 970-688-0102
stan@aec-vail.com
Construction Management Plan
Landscape Architects
Stan Clauson Associates, INC
Patrick Rawley
412 North Mill St
Aspen, CO. 81611
Tel: 970-925-2323
patrick@scaplanning.com
Safety Officer
Michael Buglione
Cell: 970-227-5425
Geotechnical Engineer
H-P Kumar
Steve Pawlak
5020 County Road 154
Glenwood Springs, CO 81601
Tel: 970-945-7988
steve@hpgeotech.com
Erosion Control Officer
Brad Hribar
Cell: 312-714-8519
Traffic Control Officer
A-1 Traffic Control & Barricade, Inc.
Cesar Jaquez
32597 Hwy 6
Silt, CO. 81652
Tel: 970-876-0738
CesarJ@a1trafficcontrol.com
Additional Contact Information
City of Aspen 970-920-5000
Pitkin County 970-920-5200
Fire Department 970-920-5532
Police Department 970-920-5400
Roaring Fork Transit Authority 970-925-8484
School District 970-925-3760
Aspen Sanitary District 970-925-3601
Aspen Water District 970-920-5110
Aspen Electric 970-920-5148
Holy Cross Electric 970-945-5491
Aspen Valley Hospital 970-925-1120
For ALL EMERGENCIES – CALL 911
Construction Management Plan
4.1 Dates of Construction
The preliminary schedule is based on an eleven month construction schedule.
Summer 2020 through 2021 time-frame.
Construction Management Plan
City of Aspen
Construction Noise Suppression Plan
As the General Contractor for this construction project, I _Brad Hribar________ hereby agree to the
following restrictions and will provide the necessary noise suppression (outlined below), such that it
will lessen the impact to the properties within 300 feet of the project located at
_____834 W Hallam______. I understand that if any construction activities exceed 80 decibels and
are not covered by this document I will contact the City of Aspen Environmental Health Department
to design a specific noise suppression plan for those activities.
_______________________________ _Brad Hribar___________________
Signature Print name
On-site Contact Phone # _(312) 714-8519__________________
Many activities on construction sites are noisy. Although some noise may be unavoidable, it can
often be controlled using improved work practices. Builders should make all reasonable efforts to
minimize noise. Noise Suppression plans are required for all construction projects where activities
will generate noise that exceeds 80 decibels. Section 18.04.050(A)(2)(d)
Hours of operation
All construction activity is limited to the following days and times:
Monday thru Friday Saturday Sunday
7:30 am to 5:30 pm 9:00am to 5:00 pm No construction work is allowed
Constructions activities producing noise greater than 80 decibels are limited to the following days
and times:
Monday thru Friday
9:00 am to 5:00pm
Work that is over 80 decibels which by law requires a noise suppression plan will not be allowed for
Saturday work that includes but not limited to the use of compressors, generators, jackhammers,
power equipment, nail guns, drilling machinery, earth moving equipment and similar loud
construction activities. This does not restrict quiet work inside and outside that does not require a
power source, including a battery, on Saturday.
Construction activity is not allowed during all federal holidays.
Due to the congestion in Aspen when town is completely full, noise suppression plans will not be
approved for the following dates: Christmas Week (December 25 through Jan. 1), Food and Wine
Week in June (Friday thru Sunday), 4th of July day and/or weekend if it falls on a Friday or Monday,
and Labor Day weekend.