These plans must be kept at the
building site or inspection
delays may occur. Construction
shall conform to these plans. All
changes shall be approved by
the building official.
Field Plan Set Must Be Printed In Color
SEPARATE PERMITS ARE
REQUIRED FOR ELECTRICAL,
PLUMBING, MECHANICAL, OR
FIRE SPRINKLER WORK
0002-2021-BCHO
WEST END HOUSE LLC
209 E BLEEKER ST
273707320002
2
06/16/2021
bonniem
SEE NOTES #1 PLANS
External Energy Use Approved
RREMP CREMP
PERMIT #:0002-2021-BCHO DATE:__6/16/21
SNOWMELT:____1500 sf_(total on site)_______
POOL: ___0________________________
SPA: ___0_________________________
OFFSET:____Solar PV + GSHP____________
REMP SHEET: _A1.3____________________
REVIEWED BY: ____Bonnie M__________
SNOWMELT SYSTEM AND EQUIPMENT MANDATORY REQ’S.
All snowmelt systems shall meet the following:
-Any portions in the Right of Way must be on a separate zone. A ROW
permit and Permanent Encroachment License are required.
-R10 insulation shall be installed under the area to be snow melted or R5
insulation shall be installed under and at the slab edges. (Ordinance 11
Series 2011)
-Automatic controls installed for system shut off when pavement
temperature is above 50°F and no precipitation is falling. (2009 IECC
Sec. 403.8 & 503.2.4.5)
-Automatic or manual controls installed for system shut off when outdoor
temperature is above 40°F. (2009 IECC Sec. 403.8 & 503.2.4.5)
-Inspection by testing hydrostatically at 1½ times max system design
pressure, but not less than 100psi, for 15minutes. (2009 IMC Sec.
1208.1)
MINIMUM BOILER AFUE: __95%__________