HomeMy WebLinkAboutFile Documents.233 W Hallam St.0077.2019 (10).ARBKThe City of Aspen
These plans must be kept at the
building site or inspection
delays may occur. Construction
shall conform to these plans. All
changes shall be approved by
the building official.
Field Plan Set Must Be Printed In Color
SEPARATE PERMITS ARE
REQUIRED FOR ELECTRICAL,
PLUMBING, MECHANICAL, OR
FIRE SPRINKLER WORK
0077.2019.ARBK
JOHN BROZOVICH
223 E HALLAM
273707316008
223 W. Hallam St.KIM RAYMOND ARCHITECTS+INTERIORS
223 W. Hallam St.
April 10th, 2019
No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.All addition windows had mullions removed. HPC approved.
Wine Chiller added at Living Room.
Master Bedroom: roof pitch over sliding doors. HPC approved.
Addition Stair: Upper stringer section: treads changed to glass.
Upper Level Hot Tub Deck: Changed railing material. HPC approved.
Master Deck handrail changed to glass . HPC approved.
All addition exterior siding changed from wood shingle. HPC Approved.
Main
Level
Upper
Level
Front Porch : Updated design after additions take out. HPC approved.
Victorian Stair configuration from U shape to curbed.
AC units moved from east to west side (they are now in property setback)
Living Room: Changed location of Fireplace. Vent HPC approved.
All addition exterior siding changed from wood shingle.
All addition windows had mullions removed. HPC approved.
2019-Change Order 2
Skylight Addition by back porch to lower level family room. HPC approved.
TO: City of Aspen Building Department
SUBJECT: Change Order 2 - Items
04/11/2019
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT APPLICATION
CITY OF ASPEN 130 S. GALENA ST | ASPEN, CO 81611
PROPERTY INFORMATION
___________________________________ _________ ___________________________
______________ ______________ ________________________________________
_________________________ _______________ __________________________________
________________________ _______________ __________________________________
CommericalMulti-FamilySingle Family
Use of Building Class of Work
NewAdditionAlterationRepair
________
YesNo
Will there be any roof/wall penetrations?
NOTICE: This permit becomes null and void if work or construction authorized is not commenced within 180 days, or if construction or work is suspended or abandoned for a period of 180 days at any time after work is commenced.
_______________
_______________
_______________ _______________
_______________
_______________
_______________
_______________
_______________
PROJECTVALUATION
SQ FT OF BUILDING WORK AREA
UNIT SQ FT
SQ FT OF SOILDISTURBANCE
BUILDING FOOTPRINT
LOT SIZE(SQ FT)
PROJECT DETAILS (READ DEFINITIONS BELOW)
Mixed-Use IFFRTenant FinishDemolitionChange Order
________
ADDRESS UNIT #PARCEL ID #
BLOCK TRACT OR SUBDIVISIONLOT
DESCRIPTION OF WORK IN DETAIL
Building
Review
Building
Permit Fee Parks Impact
Engineering
Review
Zoning
Review (50%)
School Lands
Dedication
Zoning
Review (50%)
CMP (50%)TDM Impact
Energy Code
Review
REMP
Payment
Pedestrian
Amenity
CMP (50%)GIS Housing Cash in Lieu
Parks Review City Use
Tax Water Tap
Utility Review County Use
Tax Sanitation
SUBMITTAL FEES ISSUANCE FEES
APPROVALS
ISSUANCE FEES
BEST CONTACTNAME CELL EMAIL
OWNER NAME CELL EMAIL
____Toilets, Bidets ____Bathtub____Lavatory (Wash Basin)____Shower____Kitchen Sink (+Disposal)____Dishwasher____Laundry Bar, Utility Sink____Clothes Washer ____Floor Sink____Floor Drain____Water Heater (Pan Req)____# Gas Outlets____Water Treatment____Other_________
Fixture Counts Important Review Triggers
PC
Zoning
HPC
Building
Fire
Engineering
CMP
Water
Stormwater
Sanitation
Env. Health
Parks
Landscape
Efficiency
Approved
To Issue
Issuance
Date ApprovedReviewingDepartmentReviewerSign-Off
NEW SQ FT
Project Valuation: Cost of project as defined in Valuation Affadavit.Sq Ft of Building Work Area: Total square footage of interior area undergoing change or reconfiguration.Unit Sq Ft: Gross square footage, not FAR, of permitted unit.Lot Size: Total surveyed square footage of property.Sq Ft of Soil Disturbance: Exterior area of the lot where the ground is disturbedNew Sq Ft: Total added square footage for additions to net livable or net leasable space.Building Footprint: Grade floor square footage of the permitted structure.Hardscape Area: Square footage of impervious lot surface.Zone District: Underlying zone district of permitted parcel.
January 2019
DATE:___________ MASTER PERMIT:______________________ PERMIT NUMBER:__________________________
__________________________________________________________________________________
__________________________________________________________________________________
HARDSCAPEAREA
NeedsReview
DE
F
I
N
I
T
I
O
N
S
ZONEDISTRICT
Major Engineering Review•Projects involving less than 50%hardscape area and work affecting 75% or greater of unit sq ft•Projects involving greater than50% hardscape area and work affecting 50% or greater of unit sq ft•Projects involving 1,000+ sq ft ofsoil disturbance area
Water Efficient Landscaping•Projects that trigger a majorengineering review •Projects involving interioralterations affecting 50% or moreof exisiting gross square footage
THIS SECTION MUST BE COMPLETED IN ITS ENTIRETY
0016.2017.ARBK 0077.2019.ARBK
223 E. Hallam Street, Aspen CO 273707316008
F,G 48 223 E. Hallam Street Lot Split Lot: 2
John Brozovich (210)259-9059 jcbaspen@gmail.com
Kim Raymond 970-379-8938 kim@krai.us
Skylight addition for Lower Level Family Room. New wine chiller equipment. AC Condensors to change location. HPC changes: Victorian: front porch design, living room
fireplace vent. Addition: wood siding, no mullions on windows, master bedroom glass handrail, hot tub deck enclosure material, Master Bedroom roof change in pitch.
$44,000.00
8
3
14
n
5
1
2
2
20 sq ft
7,754 sq ft
6,000 sq ft 2
0
0 sq ft
0 sq ft
3819 sq ft
1
3
0
3819 sq ft
R-6
X LL 4/11/2019
X BN 4/17/2019
X AS 5/9/19
X TF 4/25/19
25.00 0 X JD 5/8/19
0
0
0
0
04/11/2019
BM 5/13/19