September 29, 2020
Project: 630 W. Hopkins—Ski Haus Remodel
Permit Comments Round 1: Jeffrey Barnhill—Zoning Review
Zoning Review Comments / Response
630 W Hopkins_0052-2020-BRES_Zoning Commentsl
A3.3 EXTERIOR ELEVATIONS PROPOSED (1)
Subject:Cloud+
- Please ensure that this is the 1/3 point of the roof.
= Page:A3.3 EXTERIOR ELEVATIONS PROPOSED
°° It appears to be lower than the 1/3 point but could
Page Index:52 just be an optical illusion
i Author:jeffreyb
o File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: This 1/3 point is correct. See A3.3&A3.4 attached with equal dimensions confirming the 1/3 point.
Height over topography is correct and well under code.
A3.4 EXTERIOR ELEVATIONS PROPOSED (1)
Subject:Cloud+
�■iiie= = Page:A3.4 EXTERIOR ELEVATIONS PROPOSED This does not match the approved RDS elevations.
MITI=- 3 Page Index: 53 Please resubmit for RDS or change back to the
= Author:jeffreyb approved elevations.
! File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: Sorry dimension of the center section of the garage door was deleted. We've added this back and
submitted to RDS for the back elevation window changes.
L7.00 LIGHTING PLAN DIAGRAM (1)
Subject:Cloud+
Page:L7.00 LIGHTING PLAN DIAGRAM The city requires cutsheets and specifications for
,,,,,Yi Page Index:29 all exterior lighting, including security lighting
I Il11 l - Author:jeffreyb
_- File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: Thought we submitted these with the permit, but see attached and will be uploaded.
RECEIVED
215 S. Monarch Suite G-102 Aspen, Colorado 81611 10/19/2 0 2 0
P 970.544.4856 Email joseph@S2architects.com
ASPEN
BUILDING DEPARTMENT
Comment Resubmittal — Round 1 —Zoning —630 W. Hopkins_0052-2020-BRES Page 2
P-112 UPPER LEVEL PLUMBING PLAN (1)
Subject:Cloud+ This fire-pit is located between the street and
Page: P-112 UPPER LEVEL PLUMBING PLAN
Page Index:98 structure and would need to meet section
Author:jeffreyb 26.575.020(E)m
File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: This is to be a movable feature and we've removed the piped connection. See revised P-112
T-112 MAIN LEVEL SECURITY PLANS (1)
Subject:Cloud+
E a The city requires cutsheets and specifications for
` Ih� Page:T-112 MAIN LEVEL SECURITY PLANS
Page Index: 106 all exterior lighting, including security lighting
jiff r Author:jeffreyb please refer to section 26.575.150(f)5
File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: Security cameras do not have lights. See cut sheets attached and uploaded.
Z0.1 LOT AREA/FAR/ZONING (1)
Subject:Text Box
Page:Z0.1 LOT AREA/FAR/ZONING Please provide an existing and proposed site plan
Page Index:4
2. Author:jeffreyb
File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: Enclosed is the proposed Site Plan A1.1
Z0.4 ROOF DEMOLITION CALCULATIONS(1)
Subject:Cloud+
Page:Z0.4 ROOF DEMOLITION CALCULATIONS This percentage of demolition will push the project
Page Index:7 into the heightened demolition zoning policy that I
—=I Author:jeffreyb will send wheno I send comments.If you are to
File Name:Ski Haus Remodel_Permit Progress exceed 40%demolition then certain aspects of this
Set_5_22_20.pdf property would have to be brought into conformity.
Response: Understood,see attached signed Demolition Verification Policy
r Subject:Cloud+
Page:Z0.6 FLOOR AREA CALCULATIONS This table just looks like the I was skipped and
® _ = shows JK instead of IJ please have this table
Page Index:9
=_== Author:jeffreyb match the wall segments
File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: See correct on Z0.6
RECEIVED
215 S. Monarch Suite G-102 Aspen, Colorado 81611 10/19/2 0 2 0
P 970.544.4856 Email joseph@S2architects.com
ASPEN
BUILDING DEPARTMENT
Comment Resubmittal — Round 1 —Zoning —630 W. Hopkins_0052-2020-BRES Page 3
Z0.8 FLOOR AREA CALCULATIONS(2)
Subject:Cloud+
Il4i°it Page:Z0.8 FLOOR AREA CALCULATIONS I do not see any proposed floor area calculations in
;PSI_" - Page Index: 11 this submittal,those will be needed.
Author:jeffreyb
File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: Sorry we thought if we were not expanding the FAR we'd just do the existing. See attached both
Existing and Proposed FAR on the same Z0.6—Z0.8. We are reducing the existing FAR by filling in the large
light well and reducing the stair width at the upper level.
Subject:Cloud+
Page:Z0.8 FLOOR AREA CALCULATIONS What is this area?
Page Index: 11
1_---- Author:jeffreyb
File Name:Ski Haus Remodel_Permit Progress
Set_5_22_20.pdf
Response: This is a double height space not being counted. See new Z0.8 for clarification.