HomeMy WebLinkAboutFile Documents.205 S Mill St.0009-2022-BCHO nvma �► i
r .aD p`al.\ MEMORANDUM
TO: City of Aspen, Community Development Department
FROM: Dave Rybak
DATE: February 14, 2022
RE: Las Montanas - REV 2 Change Order Scope
Master Permit #0043-2021-BCOM
Upon removal of the previous tenant improvements, numerous conditions became
apparent requiring a change to implement the Tenant Improvements for the
referenced Building Permit. Revisions to the Permit submitted drawings and project
scope of work are as follows:
ARCHITECTURAL SET
A-001 GENERAL REFERENCE
Update added sheets to the drawings set.
A-002 - SPECIFICAITONS
Added U.L Y615 to document the requirements for Intumescent paint protection
on existing steel columns.
A-003 - FIRE RATED ASSEMBLIES
Demolition exposed structural steel studs were the framing members of the
exterior walls. Inserted U.L> U418 1 Et 2 Hr. Fire assembly for steel studs.
A-101 ROOF PLAN - ZONING
Identified locations of roof curbs for MAU units, span of curbs spreads unit load
over roof joists running perpendicular below.
Swamp Cooler identified had been serving Kitchen of Las Montanas, unit no longer
required, can be removed.
A-102 CODE COMPLIANCE PLAN
Documenting plan revisions and affect of life safety and accessibility compliance.
a. Restroom 6 - plan revision to incorporate niche at bar.
b. Dining Seating arrangements changed which revised exit paths and distances;
and locations of accessible seating.
c. Slight Room area revisions within the occupancy calculation chart
A-201 DEMOLITION FLOOR PLAN
a. Bar/Restroom Area, demo portion of partition wall to create niche for bar
equipment.
600 East Hopkins Avenue, Suite 303 RECEIVED
Aspen, Colorado 81611
PH / FX9709251125 02/15/2022
daverybak.com
ASPEN
BUILDING DEPARTMENT
Las Montanas REV 2
February 14, 2022
b. Kitchen/Tortilla area; removal of drywall exposed water damage and scabbed
framing within existing partition walls. Noting removal of walls for to reframe with
metal studs for better finish consistency.
c. South Wall Kitchen; removal of furred wall that had housed electrical panels.
A-202 R.C.P. DEMO PLAN
Document removal of soffits within Dining area to enable installation of fire rated
assembly onto roof structure.
A-211 FLLOR PLAN
a. Restroom 6; revise plan to accommodate niche for bar equipment.
b. Tortilla Station 10;
i. Reframe partition walls due to discovery after drywall removal.
ii. Add furred wall at West wall to accommodate pluming vent pipe discovered
during demolition.
c. Kitchen 13:
i. Add wall at south side of cookline
ii. Box out on South wall at plumbing pipes.
iii. Extend partition wall at East side to house electrical panels
A-401 BUILDING SECTIONS
Change to finish ceiling along East wall of Dining Area.
A-601 DETAILS
Change to details for found conditions of existing metal studs.
G.C. selected to utilize metal studs vs. wood, updated details.
Added details 4, 11 Et 12 for new conditions.
A-602 DETAILS
a. Revised ceiling/roof details to locate fire rated assembly onto roof structure.
b. Added details at existing structural columns to incorporate fire rated
assemblies previously non-existent.
c. Revised Restroom 6 plan to create niche for Bar equipment.
d. Added detail for existing sloped roof at East side of Dining Area.
INTERIORS SET
ID1.10 INTERIOR FLOOR PLAN
Dining Area 7
i. Booths at West wall reduced from 6 to 5
ii. New Detail at East windows, fur out at mullions and columns to accommodate
window treatment and sconces.
ID1.20 FINISH PLAN
Finish Plan and schedule updates
RECEIVED
0�2/15/2022
ASPEN
BUILDING DEPARTMENT
Las Montanas REV 2
February 14, 2022
ID1.30 EQUIPMENT PLAN
Equipment updated
ID1.40 REFLECTED CEILING PLAN
Dining Ceiling revised, seam locations for acoustic panels.
ID2.10 INTERIOR ELEVATIONS
Revised soffit above bar, removed existing, construct new plaster soffit
ID2.12 INTERIOR ELEVATIONS
Revised booth layouts and corresponding decorative lighting
Coordinated HVAC diffuser locations
Coordinated window treatment along East wall Et corresponding decorative
lighting
Revised aesthetic of wait station on North wall
ID2.13 INTERIOR ELEVATIONS
Added sheet to document Kitchen area elevations
ID4.00 ENLARGED RR PLANS
Revised Restroom 6 plan
Added vanity clearance detail
Added tile wainscot detail
ID4.1 ENLARGED TORTILLA STATION PLAN + DETAILS
Added sheet for Tortilla layouts and detailing
ID8.0 ENLARGED BAR PLAN
Revised detailing at bar soffit
Equipment niche added to West end of bar
ID8.1 ENLARGED BAR PLAN AND DETAILS
Additional detailing for back bar shelving
ID9.0 DETAILS
Additional details
ID9.1 MILLWORK DETAILS
Sheet removed from set, details placed on other sheets
ID9.2 MILLWORK DETAILS
Additional details for banquettes and bench RECEIVED
O /15/2022
ASPEN
BUILDING DEPARTMENT
Las Montanas REV 2
February 14, 2022
ID9.3 MILLWORK DETAILS
Additional details for bench at Vestibule
ID9.4 SERVER STATION DETAILS
Additional details for server stations
LD1.00
Revised lighting plan to accommodate revised ceiling layouts.
M-001 MECHANICAL SCHEUDLES
Revision to MUA-1 Et MUA-2 specifications
Added Mop sink to Plumbing Fixture Schedule
M-201 HVAC FLOOR PLAN
a. Bar / Restroom 6 Area; revisions to accommodate new soffits and plan layouts.
b. Dining 7; diffuser coordination
c. Kitchen Area; new ducts required, existing found to be in poor condition.
d. Restroom 12; added rooftop termination for exhaust fan. Existing fan dumped
into ceiling plenum.
M-301 PLUMBING FLOOR PLAN
a. Restroom 6; plan revision
b. Tortilla Station, relocate floor drain to accommodate equipment
c. Dry Storage 14; add mop sink
d. Kitchen 13; Equipment location adjustments
MD-201 MECHANICAL DEMO FLOOR PLAN
a. Coord w/ new Restroom 6 plan
b. Kitchen - existing ducts found to be unusable, demo all
c. Restroom 12; exhaust fan not connected to duct work
E-000 ELECTRICAL COVER SHEET
Include use of metal clad cable.
E-001 ELECTRICAL ONE-LINE AND PANEL SCHEDULES
Panel schedule revisions for equipment adjustments
E-002 ELECTRICAL SCHEDULES
Luminaire Schedule adjustments
Kitchen Equipment Schedule adjustments
E-201 POWER FLOOR PLAN
Power location adjustments due to equipment revisions or field conditions RECEIVED
0 /15/2022
ASPEN
BUILDING DEPARTMENT
Las Montanas REV 2
February 14, 2022
E-301 LIGHTING LFOOR PLAN
Lighting adjustments per ceiling revisions.
E-701 ELECTRICAL COMCHECK
Revised per new lighting plan
STRUCTURAL
Memorandum from Albright E. Associates addressing the roof framing, and Mechanical
Rooftop unit replacement. Submitted as additional information.