HomeMy WebLinkAboutFile Documents.315 Dean St.0024-2024-BCOM (4) DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
•
4A k► COMMUNITY
�IOi'DEVELOPMENT
CITY OF ASPEN
City of Aspen Wireless Development Application Packet
Attached is an Application for review of Development that requires Land Use Review pursuant to The City of
Aspen Land Use Code. Included in this package are the following attachments:
1. Application Fee Policy and Agreement to Pay Application Fees Form
2. Land Use Application Form
3. Wireless Supplement
4. HOA Compliance Form
5. Development Review Procedure
All Applications are reviewed based on the criteria established in Title 26 of the Aspen Municipal Code.Title 26
of the Aspen Municipal Code is available at the City Clerk's Office on the second floor of City Hall and on the
internet at http://www.cityofaspen.com/1223, City Departments, City Clerk, Municipal Code, and search Title
26.
We require all applications on private property,and strongly encourage applications in the Right-of-Way,
to hold a Pre-Application Conference with a Planner in the Community Development Department so that
the requirements for submitting a complete application can be fully described.This meeting can occur in
person or by phone or e-mail. Also, depending upon the complexity of the development proposed,
submitting one copy of the development application to the Case Planner to determine accuracy,
inefficiencies, or redundancies can reduce the overall cost of materials and Staff time.
Please recognize that review of these materials does not substitute for a complete review of the Aspen Land
Use Regulations. While this application package attempts to summarize the key provisions of the Code as they
apply to your type of development, it cannot possibly replicate the detail or the scope of the Code. If you have
questions which are not answered by the materials in this package, we suggest that you contact the staff
member assigned to your case,contact Planner of the Day, or consult the applicable sections of the Aspen Land
Use Code.
RECEIVED
05/09/2024
Page 1 of 13
ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
NINE'/ COMMUNITY
NSd l DEVELOPMENT
CITY OF ASPEN
Application Fee Policy
The City of Aspen has established a review fee policy for the processing of land use applications. A flat fee or
deposit is collected for land use applications based on the type of application submitted.
A flat fee is collected by Community Development for applications which normally take a minimal and
predictable amount of staff time to process. Review fees for other City Departments reviewing the application
(referral departments)will also be collected when necessary. Flat fees are cumulative- meaning an application
with multiple flat fees must be pay the sum of those flat fees. Flat fees are not refundable.
A review fee deposit is collected by Community Development when more extensive staff time is required.
Actual staff time spent will be charged against the deposit. Various City staff may also charge their time spent
on the case in addition to the case planner. Deposit amount may be reduced if, in the opinion of the Community
Development Director, the project is expected to take significantly less time to process than the deposit
indicates.
A determination on the deposit amount shall be made during the pre-application conference by the case
planner. Hourly billing shall still apply.
All applications must include an Agreement to Pay Application Fees. One payment including the deposit for
Planning and referral agency fees must be submitted with each land use application, made payable to the City
of Aspen. Applications will not be accepted for processing without the required fee.
The Community Development Department shall keep an accurate record of the actual time required for the
processing of a land use application requiring a deposit. The City can provide a summary report of fees due at
the applicant's request. The applicant will be billed for the additional costs incurred by the City when the
processing of an application by the Community Development Department takes more time or expense than is
covered by the deposit. Any direct costs attributable to a project review shall be billed to the applicant with no
additional administrative charge. In the event the processing of an application takes less time than provided for
by the deposit,the department shall refund the unused portion of the deposited fee to the applicant. Fees shall
be due regardless of whether an applicant receives approval.
The Community Development Director may cease processing of a land use application for which an unpaid
invoice is 30 or more days past due. Unpaid invoices of 90 days or more past due may be assessed a late fee of
1.7% per month. An unpaid invoice of 120 days or more may be subject to additional actions as may be assigned
by the Municipal Court Judge. All payment information is public domain.
All invoices shall be paid prior to issuance of a Development Order or recordation of development agreements
and plats. The City will not accept a building permit for a property until all invoices are paid in full. For permits
already accepted, and unpaid invoice of 90 days or more days may result in cessation of building permit
processing or issuance of a stop work order until full payment is made.
The property owner of record is the party responsible for payment of all costs associated with a land use
application for the property. Any secondary agreement between a property owner and an applicant
representing the owner (e.g. a contract purchaser) regarding payment of fees is solely between those private
parties.
RECEIVED
05/09/2024
Page 2 of ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
te
LA '► COMMUNITY
NI10iI DEVELOPMENT
CITY OF ASPEN
Agreement to Pay Application Fees
An agreement between the City of Aspen ("City") and
Property Owner Name: Aspen Owner LLC--_—_—_—_
Address of Property: 315 E Dean St Representative Name (if different from Property Owner): Lance Bleyhl
Billing Name and Address - Send Bills to: Contact Email for Billing:
Lance Bleyhl lance.bleyhl@retherfordenterprises.com
7093 Silverhorn Dr_ Contact Phone for Billing:
Evergreen, CO 80439 720-201-7385
I understand that the City has adopted, via Ordinance No.40, Series of 2018, as may be amended,
review fees for Land Use applications and payment of these fees is a condition precedent to
determining application completeness. I understand that as the property owner that I am responsible
for paying all fees for this development application.
For flat fees and referral fees: I agree to pay the following fees for the services indicated. I understand
that these flat fees are non-refundable.
$ 0 flat fee for Select Dept
$0 Select Dept
flat fee for
$0 flat fee for Select Dept $0 flat fee for Select Dept
For Deposit cases only: The City and I understand that because of the size, nature or scope of the
proposed project, it is not possible at this time to know the full extent or total costs involved in
processing the application. I understand that additional costs over and above the deposit may accrue.
I understand and agree that it is impracticable for City staff to complete processing, review and
presentation of sufficient information to enable legally required findings to be made for project
consideration, unless invoices are paid in full.
The City and I understand and agree that invoices mailed by the City to the above listed billing address
and not returned to the City shall be considered by the City as being received by me. I agree to remit
payment within 30 days of presentation of an invoice by the City for such services.
I have read, understood, and agree to the Land Use Review Fee Policy including consequences for no-
payment. I agree to pay the following initial deposit amounts for the specified hours of staff time. I
understand that payment of a deposit does not render and application complete or compliant with
approval criteria. If actual recorded costs exceed the initial deposit, I agree to pay additiokacttivED
05/09/2024
Page 3 of 13
ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID_B89FDED0-24B0-46EA-A5F7-E29D1187DC23
'1► COMMUNITY
d1 DEVELOPMENT
CITY OFASPEN
billings to the City to reimburse the City for the processing of my application at the hourly rates
hereinafter stated.
$_______ deposit for______ hours of Community Development Department staff time. Additional
time above the deposit amount will be billed at$325.00 per hour.
$_______deposit for__ _ _ hours of Engineering Department staff time. Additional time above the
deposit amount will be billed at $325.00 per hour.
City of Aspen: Property Owner, or Representative
------------------------ ___ Signature:
Jennifer Phelan, AICP La n c B I eyh l
Acting Community Development Director PRINT Name:__________________
Title: Consultant
City Use: Fees Due: $
Received $_
Case #
RECEIVED
05/09/2024
Page aof 13
ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
h4k%'0 COMMUNITY
�� i�DEVELOPMENT
CITY OF ASPEN
Land Use Application Form
Project Name and Address:Verizon CO3 Aspen Highlands/St. Regis Hotel/315 E Dean St.
Parcel ID #, if on Private Property (REQUIRED): 273718285033
Location, if in Right-of-Way, include Lat/Long (REQUIRED): 315 E Dean St
Zone District: PUD/L-TR Historic District? ❑ Yes n No
Historic Building (Designated)? I I Yes ✓ No
Applicant:
Name: Verizon Wireless
Address: 10000 Park Meadows Dr. 3rd Floor, Lone Tree, CO 80124
Phone#: 303-842-1720
Email: Jennifer.brooks3@verizonwireless.com
Representative:
Name: Retherford Enterprises, Lance Bleyhl
Address: 7093 Silverhorn Dr. Evergreen, CO 80439
Phone#: 720-201-7385
Email: lance.bleyhl@retherfordenterprises.com
Property Owner:
Name: Aspen Uwner LLC;
Address: 31 b East Uean Street, Aspen C;U
Phone#: 19 f U-9 f 4b f b
Email: stepnane(a)_elevatedreturns.com
Identification of Proposed Wireless Facility type (please select all applicable):
My project meets the definition of"Small Cell Facility" pursuant to Land Use Code Section 26.505.03o
(3 cubic feet)
New Deployment of Small Cell Wireless Facility
Collocation of Small Cell Wireless Facility. Collocation is defined in Land Use Code Section
26.505.030, and includes installation of a wireless facility on an existing structure.
V Eligible Facilities Request. Eligible Facilities Requests are defined in Land Use Code Section
26.505.030, and means a modification of an existing tower or base station that involves either the
collocation of new transmission equipment, or the removal of transmission equipment, or the
replacement of transmission equipment, and that does not substantially change the physical
dimensions of the existing tower or base station.
Non-Eligible Facilities Request Collocation
New Deployment of non-Small Cell Wireless Facility RECEIVED
My project is located in a Right-of-Way RECEIVED
05/09/2024
Page 5 of 13
ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
4N0'i 0► COMMUNITY
� DEVELOPMENT
CITY OF ASPEN
Wireless Communication Facilities Shot Clock Table
Small Wireless Small Wireless Eligible Non-Eligible Non-Small
Facility - New Facility - Facilities Facilities Wireless
Deployment Collocation Request Request Facility WCF -
Collocation New
Deployment
(E.g. a standalone (E.g. a small (e.g. modification (e.g. a request (e.g.a new Tower)
monopole in the wireless facility on of transmission for installation of
Right-of-way) an existing equipment on an new transmission
structure such as existing tower or equipment on an
a traffic light) base station that existing tower or
does not base station, but
-substantially that would
change" the substantially
physical change
dimensions of the dimensions of
tower or base the tower or
station) base station)
90 days 60 days 60 days 90 days 150 days
Please describe the proposed wireless facility that is the subject of this application.
The
proposed modification will reduce total antennas from twelve to nine. with 3 antennas per
additional height is required. Antennas will also be painted same color
as existing antennas.
Existing rooftop equipment cabinets will remain as currently configured with no additional
space needed. All equipment changes will be within existing cabinets.
Please describe the current site on which the wireless facility is proposed, including any existing buildings
or wireless infrastructure,as well as parcel boundaries. "Site"means the building or tower on which the Wireless
Facility is proposed to be located.
Existing site is located on roof top of St. Regis Hotel. It is comprised of three sectors of roof
mounted-an-tern; ^pit"�,rh 4 ntennars per sectGc—These are painted to match building. There is
also a rooftop equipment platform with radio cabinets. Height of antennas is 76'.
RECEIVED
05/09/2024
Page 6 of 13
ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
4N�'0► COMMUNITY
Nadige DEVELOPMENT
I CITY OF ASPEN
Please provide the following information for all proposed facilities. Additional pages may be used if
multiple wireless facilities are proposed.
• What is the proposed height of the proposed wireless facility from the point of attachment to the ground
or building?
Proposed height will equal existing height of 76'
• What is the proposed cubic feet of the proposed wireless facility?
N/A Since this is not a small cell we do not factor the cubic feet of the site.
• What electric and internet connectivity requirements does the proposed facility have? Who are the utility
providers of these services?
The current utility service to the site will not be affected. No AC power changes only DC
power for back up battery system will be modified. Providers are Aspen Electric and Lumen
• Does this application involve any excavation or location of equipment outside the boundaries of the Site?
(If so, please describe):
NO
• Describe the number and dimension of any equipment cabinets.
Rooftop equipment cabinets are approximately 30"x30"x 54" there are four cabinets.
• Describe the equipment type, model number and manufacturer specifications (ex. Dimensions and weight):
See equipment specs on drawing set.
• Describe the noise levels from equipment to be installed (if applicable):
Noise levels arc minimal and located on top of roof where no one will notice
RE EIVED
05/09/2024
Page 7 of 13ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
•
4N)'0► COMMUNITY
\Igo.,DEVELOPMENT
CITY OF ASPEN
For all Eligible Facilities Requests, please provide the following additional information:
• Documentation of previous land use or building permit approval. Please provide all information
documenting how the structure previously received land use approval for the existing facilities. Include
the date(s) of land use approval, the Notice of Approval or other documentation for the land use
approval, any permit numbers related to the construction of the facilities, and any conditions contained
in the permit and/or land use approval. Existing Towers, Existing Support Structures, or Existing Base
Stations are defined in the Land Use Code as those that have been previously reviewed and approved
under the applicable zoning process in place at the time of their construction.
I was not able to access the existing/previous approval through Aspens website. But,
the site was previously approved.
• Is this a c cation • mew transmission equipment?
Yes 12 No
• Is this a removal of existing transmission equipment?
Yes_ No
• Is this a replacement of existing transmission equipment?
_`/ _Yes_I _ No
• What is the height of the existing structure? 76 feet to top of antennas
• What will the height of the structure be after the collocation, removal, and/or replacement of
transmission equipment from the point of attachment on the ground or building? If the infrastructure
is roof mounted, provide a measurement from either the point of attachment or from the top of
screening (if behind a parapet wall or screen).
Proposed height will match existing height of 76'
RECEIVED
05/09/2024
Page 8 of 13ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
4N�'$ COMMUNITY
�Sd DEVELOPMENT
CITY OF ASPEN
Please indicate if the following applicable requirements have been met with the proposed facility.
✓ For all projects proposed on private property, all required Application Contents, as outlined in Aspen Land
Use Code Subsection 26.304.030.B, are included, including specifically:
6/ The completed HOA Form (attached)
V Letter of Authorization from the Property Owner. This must be from the property owner, not a
carrier.
v Proof of ownership consisting of a current certificate from a title insurance company or attorney
licensed to practice in the State of Colorado.
`/ The proposed WCF meets all Federal Requirements, including those of the FAA, FCC,and any other federal
agency with the authority to regulate WCFs. A written statement explaining compliance is required. (See
26.505.040, Operational Standards)
V The design and siting of the WCF does not interfere with the normal operation of public safety
communications, radio, television, telephone, or other communications services. A written statement from
a qualified radio frequency engineer is required (See 26.505.040.C, Signal Interference)
V All required Application Items, as outlined in Aspen Land Use Code Subsection 26.505.060, Application
Contents, are included in the application.
V Plan Submittal Standards, meeting requirements of Title 29, Engineering Design Standards -
Submittal Requirements Chapter 1, and showing the location of existing and proposed facilities and
equipment to scale. This can be multiple sheets showing existing versus proposed.
6/ Before and After pictures or other visual simulations.
✓ Building Façade Elevations showing the location of the existing and proposed facilities and
equipment, to scale.
V/ Site Improvement survey, including topography, vegetation, utilities, utility services, easements,
vacated rights-of-way, and any other requirements outlined in Title 29, Engineering Design
Standards, stamped and signed by a registered land surveyor.
Landscape Plan, as applicable
Lighting Plan, illustrating how any lighting complies with the requirements of the City's Lighting
Code (See 26.575)
V A structural integrity report from a Professional Engineer licensed in the State of Colorado.
6/ Evidence that efforts were undertaken to locate on an existing wireless facility.
Written documentation regarding site selection that demonstrates a good faith effort PFIVED
n
City's location preferences (See Section 26.505.070.B, Site Selection, for the listed pre ereces .
05/09/2024
Page 9 of ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
•
4A ,► COMMUNITY
ISO,'DEVELOPMENT
CITY OF ASPEN
Complete responses to all Design Standards, including those in Chapter 26.505.080, Design Standards, and
the Design Standards adopted by the Community Development Director, as amended from time to time,
pursuant to Subsection 26.505.0801.5, Director to adopt design standards.
Building Permit / Right-of-Way Application Requirements.
The documents listed below are required, based on the specific type of facility that is proposed. All documents
are required as part of the initial land use application submission.
Building permit requirements for roof-mounted appliances:
✓ Completed building permit application packet
✓ A letter, signed and stamped by a structural engineer, verifying that the building can handle the additional
load of the proposed units
✓ Existin and proposed scaled drawings
riProposed drawings must show compliance with 2015 IMC Section 306 and 2015 IBC Section 1015.6
Building permit requirements for free-standing towers:
Completed building permit application packet
A letter, signed and stamped by a structural engineer, verifying that the building can handle the additional
load of the proposed units
Existing and proposed scaled drawings
Proposed drawings must show compliance with 2015 IMC Section 306 and 2015 IBC Section 1015.6
A narrative or spec sheet describing the materials and construction methods of the proposed structure
Signed special inspection agreement, if applicable
Completed Construction Mitigation Plan, if triggered, refer to Title 29 for thresholds
Right-of-Way permit requirements refer to Title 21 for any work in the right-of-way:
❑ Completed right-of-way application packet
nA copy of a valid Maintenance Bond
Professionally drawn detailed Traffic Control Plan (TCP)
nA narrative or spec sheet describing the materials and construction methods of the proposed structure
❑ A letter, signed and stamped by a structural engineer, verifying that the proposed pole / structure can
handle the additional load of the proposed facilities
nA letter stating fiber and electric capacity exists for the proposed wireless facility
O Separate 14 Day Written Notification in the form of a right-of-way application, submitted electronically, to
City Engineering Department prior to start of right-of-way work for each individual facility. This will include
the approved TCP, valid and updated Maintenance Bond, and approved site plan(s).
❑ Completed Construction Mitigation Plan
Electric Permit Requirements
Completed Electric permit application packet
For Internal Use:
Date of Application Received
Date of Completeness Review
Date Deemed Complete RECEIVED
Date of applicable review timeline
05/09/2024
Page 10 of 13ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
NIA '6'► COMMUNITY
Nil IIDEVELOPMENT
CITY OF ASPEN
Homeowner Association Compliance Policy
All land use applications within the City of Aspen are required to include a Homeowner Association Compliance
Form (this form) certifying the scope of work included in the land use application complies with all applicable
covenants and homeowner association policies. The certification must be signed by the property owner or
Attorney representing the property owner.
Name: Aspen Owner LLC
Property
Owner("I"): Email: Stephane@elevatedreturns.corn Phone No.: 1970-9874575
Address of -- —
_ 15 E Dean St
Property:
(subject of
application)
I certify as follows: (pick one)
✓ This property is not subject to a homeowners association or other form of private covenant.
This property is subject to a homeowners association or private covenant and the improvements proposed
in this land use application do not require approval by the homeowners association or covenant beneficiary.
This property is subject to a homeowners association or private covenant and the improvements proposed
in this land use application have been approved by the homeowners association or covenant beneficiary.
I understand this policy and I understand the City of Aspen does not interpret, enforce, or manage the
applicability, meaning or effect of private covenants or homeowner association rules or bylaws. I understand
that this document is a public document. o Signed by:
Owner signature: S{-19 - ,)t- badS Date: January 19, 2024
EFi187B19C1A941
Owner printed name: Stephane DeBaets
or,
Attorney signature: Date:
Attorney printed name:
RECEIVED
05/09/2024
Page 11 of 13ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
NIA ' '► COMMUNITY
NIoie DEVELOPMENT
CITY OF ASPEN
DEPARTMENT DEVELOPMENT REVIEW PROCEDURE
1. Attend pre-application conference. During this one-on-one meeting, staff will determine the
review process which applies to your development proposal and will identify the materials
necessary to review your application.
2. Submit Development Application. Based on your pre-application meeting, you should
respond to the application package and submit the requested number of copies of the
complete application and the application and the appropriate processing fee to the Community
Development Department.
3. Determination of Completeness. Within five working days of the date of your submission,
staff will review the application, and will notify you in writing whether the application is
complete or if additional materials are required. Please be aware that the purpose of the
completeness review is to determine whether or not the information you have submitted is
adequate to review the request, and not whether the information is sufficient to obtain
approval.
4. Staff Review of Development Application. Once your application is determined to be
complete, it will be reviews by the staff for compliance with the applicable standards of the
Code. During the staff review stage, the application will be referred to other agencies for
comments. The Planner assigned to your case or the agency may contact you if additional
information is needed or if problems are identified. A memo will be written by the staff member
for signature by the Community Development Director. The memo will explain whether your
application complies with the Code and will list any conditions which should apply if the
application is to be approved. Final approval of any Development Application which amends a
recorded document, such as a plat, agreement or deed restriction, will require the applicant to
prepare an amended version of that document for review and approval by staff. Staff will
provide the applicant with the applicable contents for the revised plat, while the City Attorney
is normally in charge of the form for recorded agreements and deed restrictions. We suggest
that you not go to the trouble or expense of preparing these documents until the staff has
determined that your application is eligible for the requested amendment or exemption.
5. Board Review of Application. If a public hearing is required for the land use action that you
are requesting, then the Planning Staff will schedule a hearing date for the application upon
determination that the Application is complete. The hearing(s) will be scheduled before the
appropriate reviewing board(s).The applicant will be required to nail notice (one copy provided
by the Community Development Department) to property owners within 30 feet of the subject
property and post notice (sign available at the Community Development Department)of the
public hearing on the site at least fifteen (is) days prior to the hearing date (please see
Attachment 6 for instructions).The Planning Staff will publish notice of the hearing in (i,aa tIVED
for land use requests that require publication. The Planning Staff will then
05/09/2024
Page 12 of 13
ASPEN
BUILDING DEPARTMENT
DocuSign Envelope ID B89FDED0-24B0-46EA-A5F7-E29D1187DC23
gAl'�'► COMMUNITY
NIhie DEVELOPMENT
CITY OF ASPEN
recommendation on the land use request and draft a memo to the reviewing board(s). Staff will
supply the Applicant with a copy of the Planning Staff's memo approximately 5 days prior to
the hearing. The public hearing(s) will take place before the appropriate review boards. Public
Hearings include a presentation by the Planning Staff, a presentation by the Applicant
(optional), consideration of public comment, and the reviewing board's questions and decision.
6. Issuance of Development Order. If the land use review is approved, then the Planning Staff
will issue a Development Order which allows the Applicant to proceed into Building Permit
Application.
7. Receipt of Building Permit. Once you have received a copy of the signed staff approval, you
may proceed to building permit review. During this time, your project will be examined for its
compliance with the City's Adopted Building Codes. It will also be checked for compliance with
applicable provisions of the Land Use Regulations which were not reviewed in detail during the
one step review (this might include a check of floor area ratios, setbacks, parking, open space
and the like). Fees for water, sewer, parks and employee housing will be collected if due. Any
document required to be recorded, such as a plat, deed restriction or agreement, will be
reviewed and recorded before a Building Permit is submitted.
Iiiiiii;
RECEIVED
05/09/2024
Page 13 of 13
ASPEN
BUILDING DEPARTMENT