215 S. Monarch Suite G-102 Aspen, Colorado 81611
P 970.544.4856 Email joseph@S2architects.com
August 10, 2022
Project: 634 W. Hopkins – Ski Haus Remodel
Permit Comments Round 2: Haley Hart – Zoning Review
Zoning Review Comments / Response
Response: I have added these values current Assessor land value and
Response: This is a piece of art inside on the wall.
Response: I’ve added those points to the section drawing
Comment Resubmittal – Round 1 – Zoning Comments – 634 W. Hopkins_0106-2021-BRES
Page 2
215 S. Monarch Suite G-102 Aspen, Colorado 81611
P 970.544.4856 Email joseph@S2architects.com
Response: We moved the dishwashing sink. This is just a stone backsplash behind the sink. This is the
interior north wall of the kitchen.
Response: You mean Z0.9. I have rounded this up to 44%
Response: Corrected
Comment Resubmittal – Round 1 – Zoning Comments – 634 W. Hopkins_0106-2021-BRES
Page 3
215 S. Monarch Suite G-102 Aspen, Colorado 81611
P 970.544.4856 Email joseph@S2architects.com
Response: Yes, I added the 96 SF, I also had the upper deck at 355 SF on the drawings, but listed on the chart
at 349, so I added that 6 SF to make it all accurate now.
Comment Resubmittal – Round 1 – Zoning Comments – 634 W. Hopkins_0106-2021-BRES
Page 4
215 S. Monarch Suite G-102 Aspen, Colorado 81611
P 970.544.4856 Email joseph@S2architects.com
Response: I have removed the light well. Both Arch & Structural.
Response: The deck is just open joists, not sheathing exists. Rain drips through. We are just replacing the
boards as needed. As anyone would do for maintenance. The structural joints and everything else to remain. Doesn’t seem practical to call this into the demo calculations??
Response: Stairs are just built up wood blocks over the lower deck existing frame and meeting up with upper existing deck framing. Doesn’t seem practical to call this into the demo calculations??